200 North Glebe Road Facility Condition Assessment Arlington, Virginia The subject property is located at 200 North Glebe Road in Arlington, Virginia. There were extensive upgrades to various systems throughout the property, but many systems were reaching the end of their expected useful lives. Facility Engineering Associates, P.C. (FEA) performed a facility condition assessment for property systems including the parking structure, facade elements, roof system, mechanical systems, HVAC systems, electrical systems, plumbing systems, and fire and life safety systems. The study also included a boiler feasibility study for replacement of the boiler with either an in-kind electric boiler or with a gas boiler. FEA visited the project site, reviewed available building drawings and previous reports, previous project documentation, and interviewed available building personnel. The intended use of the condition assessment was for capital planning for replacement of capital systems. FEA developed recommendations for replacement of building components based on overall condition, and not just remaining useful life. Operations and maintenance were also considered when assigning remaining useful life to building components. Recommendations were discussed with the building management to ensure that the PRIMARY CLIENT REFERENCE Monty Farfan Chief Building Engineer The Plaza at Walnut Creek 1333 N. California Blvd., Suite 680 Walnut Creek, CA 94596 (703) 522-1010 [email protected] START DATE: April 8, 2013 COMPLETION DATE: June 3, 2013 PROJECT SIZE: 154,000 SQFT VALUE OF CONTRACT: $18,500 CLIENT BENEFITS Furnished a 10-year capital expenditure report of expected capital costs for each building system Suggested projects to implement for improvements in energy efficiency and their respective payback periods Recommended boiler feasibility for replacement with a gas or electric boiler Provided improvement recommendations made by an independent consultant rather than equipment vendors SCOPE ITEMS Parking structure Surface parking lots Facade elements Roof system Structural system Mechanical systems HVAC systems

Upload: vuongtu

Post on 07-Feb-2018

224 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Vision Word Macro for Deltek Vision 5.1 - feapc.com Web viewThe study also included a boiler feasibility study for replacement of the boiler with either an in-kind electric ... Vision

200 North Glebe Road Facility Condition AssessmentArlington, Virginia

The subject property is located at 200 North Glebe Road in Arlington, Virginia. There were extensive upgrades to various systems throughout the property, but many systems were reaching the end of their expected useful lives.Facility Engineering Associates, P.C. (FEA) performed a facility condition assessment for property systems including the parking structure, facade elements, roof system, mechanical systems, HVAC systems, electrical systems, plumbing systems, and fire and life safety systems. The study also included a boiler feasibility study for replacement of the boiler with either an in-kind electric boiler or with a gas boiler.FEA visited the project site, reviewed available building drawings and previous reports, previous project documentation, and interviewed available building personnel.The intended use of the condition assessment was for capital planning for replacement of capital systems. FEA developed recommendations for replacement of building components based on overall condition, and not just remaining useful life. Operations and maintenance were also considered when assigning remaining useful life to building components. Recommendations were discussed with the building management to ensure that the recommendations were viable and reasonable.

PRIMARY CLIENT REFERENCEMonty FarfanChief Building EngineerThe Plaza at Walnut Creek1333 N. California Blvd., Suite 680Walnut Creek, CA 94596(703) [email protected]

START DATE: April 8, 2013COMPLETION DATE: June 3, 2013

PROJECT SIZE: 154,000 SQFTVALUE OF CONTRACT: $18,500

CLIENT BENEFITS Furnished a 10-year capital

expenditure report of expected capital costs for each building system

Suggested projects to implement for improvements in energy efficiency and their respective payback periods

Recommended boiler feasibility for replacement with a gas or electric boiler

Provided improvement recommendations made by an independent consultant rather than equipment vendors

SCOPE ITEMS Parking structure Surface parking lots Facade elements Roof system Structural system Mechanical systems HVAC systems Electrical systems Plumbing systems Fire and life safety systems Boiler feasibility study