very large hadron collider
TRANSCRIPT
-
7/30/2019 Very Large Hadron Collider
1/142
Appendix DTBM Tunnel Assumptions and Cost Estimating Output
-
7/30/2019 Very Large Hadron Collider
2/142
Appendix D TBM Tunnel Assumptions and Cost Estimating Output
Discussion:
The tunnel costs were estimated using TBM cost estimating software and cost database
developed by Hatch Mott MacDonald. Appendix D contains output from the software for eachTBM type and tunnel diameter. Please note the following about the output:
1. Rock Types are called TBM Types in the main body of the report.
2. Rock Type A/B is called TBM Type B in the main body of the report.
3. The costs for concrete inverts were not included in the output in the appendices.
These were added in the CNA cost estimating spreadsheet. The inverts are needed toprovide a flat working surface. Inverts were added to TBM Types A and C only becauseit was assumed that the TBM Type B cast-in-place liner could be formed with a flat
bottom.
4. The costs of grouting for water control were not included in the appendices. These
were added in the CNA cost estimating spreadsheet. Grouting was added to TBM TypesA and B only. TBM Type C is a sealed system that does not allow water to enter the
tunnel so grouting is not required.
List of Abbreviations:
CIP Cast-in-place
H Hour
m2 Square meters of tunnel face
Nr Number (equivalent to Each)
W Week
mW per meter per week
kWh Kilowatt hour
l Liter
m Meter
m3 Cubic meter
-
7/30/2019 Very Large Hadron Collider
3/142
Page 1 of 2
s:\fermi_vlhc\pm\ reports\hmm assumptions.doc TEXT-P.DOT, 00/01v
Fermilab Tunnels
Cost Estimates
Assumptions
General
The following assumptions apply to all tunnel drives:
4800 metres of tunnel from shaft to shaft
2 ten hours shifts undertaken daily, 5 days per week
Tunnels excavated using 3.66 metre or 4.88 metre finished diameter rock TBM
75 percent of TBM cost written off in first drive, 15 percent in second drive, 10 percent inthird drive, and 0 percent in fourth and fifth drives
Labour rates based on Minneapolis Project for Year 2001. (Similar to Illinois)
Specific
Assumptions used for 3.66m (12ft) diameter tunnel in Rock Type A as follows:
No areas of difficult excavation
A total of 400 3 metre long rockbolts installed sporadically in the tunnel crown in jointed
or potentially weak zones
Average tunnel advance rate of 225 metres per week
No secondary lining required
Assumptions used for 3.66m (12ft) diameter tunnel in Rock Type A/B (requiring CIP liner) asfollows:
No areas of difficult excavation
Three rockbolts, 3 metres in length, installed in each 6 metre length of tunnel
Average tunnel advance rate of 211 metres per week
Secondary cast-in-place concrete lining installed to prevent long term degradation of therock
Assumptions used for 3.66m (12ft) diameter tunnel in Rock Type C as follows:
Areas of difficult excavation encountered, slowing normal advance rate by 20 percent,
over 20 percent of the tunnel length
-
7/30/2019 Very Large Hadron Collider
4/142
Page 2 of 2
s:\fermi_vlhc\pm\ reports\hmm assumptions.doc TEXT-P.DOT, 00/01v
No primary support provided with a 200mm thick segmental concrete lining installedimmediately behind the TBM following each excavation cycle
Average tunnel advance rate of 102 metres per week
Assumptions used for 4.88m (16ft) diameter tunnel in Rock Type A as follows:
No areas of difficult excavation
A total of 400 3 metre long rockbolts installed sporadically in the tunnel crown in jointedor potentially weak zones
Average tunnel advance rate of 225 metres per week
No secondary lining required
Assumptions used for 4.88m (16ft) diameter tunnel in Rock Type A/B (requiring CIP liner) asfollows:
No areas of difficult excavation
Three rockbolts, 3 metres in length, installed in each 4.5 metre length of tunnel
Average tunnel advance rate of 195 metres per week
Secondary cast-in-place concrete lining installed to prevent long term degradation of the
rock
Assumptions used for 4.88m (16ft) diameter tunnel in Rock Type C as follows:
Areas of difficult excavation encountered, slowing normal advance rate by 20 percent,over 20 percent of the tunnel length
No primary support provided with a 225mm thick segmental concrete lining installedimmediately behind the TBM following each excavation cycle
Average tunnel advance rate of 102 metres per week
-
7/30/2019 Very Large Hadron Collider
5/142
Fermilab Tunnels
Estimate Summary
12 ft dia tunnel (3.66 m)
Rock Type Tunnel Drive Tunnel Length Drive Cost TBM setup Total
(m)
A First 4800 8,160,000 400,000 8,560,000
A Second 4800 6,070,000 200,000 6,270,000
A Third 4800 5,910,000 200,000 6,110,000
A Fourth 4800 5,600,000 200,000 5,800,000
A Fifth 4800 5,600,000 200,000 5,800,000
A/B with CIP First 4800 18,930,000 400,000 19,330,000
A/B with CIP Second 4800 16,350,000 200,000 16,550,000
A/B with CIP Third 4800 16,140,000 200,000 16,340,000
A/B with CIP Fourth 4800 15,710,000 200,000 15,910,000A/B with CIP Fifth 4800 15,710,000 200,000 15,910,000
C First 4800 26,630,000 400,000 27,030,000
C Second 4800 23,190,000 200,000 23,390,000
C Third 4800 22,940,000 200,000 23,140,000
C Fourth 4800 22,430,000 200,000 22,630,000
C Fifth 4800 22,430,000 200,000 22,630,000
16 ft dia tunnel (4.88 m)
Rock Type Tunnel Drive Tunnel Length Drive Cost TBM setup Total
(m)
A First 4800 10,930,000 400,000 11,330,000
A Second 4800 7,360,000 200,000 7,560,000
A Third 4800 7,080,000 200,000 7,280,000
A Fourth 4800 6,520,000 200,000 6,720,000
A Fifth 4800 6,520,000 200,000 6,720,000
A/B with CIP First 4800 24,410,000 400,000 24,810,000
A/B with CIP Second 4800 20,160,000 200,000 20,360,000
A/B with CIP Third 4800 19,810,000 200,000 20,010,000
A/B with CIP Fourth 4800 19,100,000 200,000 19,300,000
A/B with CIP Fifth 4800 19,100,000 200,000 19,300,000
C First 4800 33,360,000 400,000 33,760,000
C Second 4800 27,830,000 200,000 28,030,000
C Third 4800 27,400,000 200,000 27,600,000
C Fourth 4800 26,550,000 200,000 26,750,000
C Fifth 4800 26,550,000 200,000 26,750,000
-
7/30/2019 Very Large Hadron Collider
6/142
-
7/30/2019 Very Large Hadron Collider
7/142
-
7/30/2019 Very Large Hadron Collider
8/142
-
7/30/2019 Very Large Hadron Collider
9/142
-
7/30/2019 Very Large Hadron Collider
10/142
-
7/30/2019 Very Large Hadron Collider
11/142
-
7/30/2019 Very Large Hadron Collider
12/142
-
7/30/2019 Very Large Hadron Collider
13/142
-
7/30/2019 Very Large Hadron Collider
14/142
-
7/30/2019 Very Large Hadron Collider
15/142
-
7/30/2019 Very Large Hadron Collider
16/142
-
7/30/2019 Very Large Hadron Collider
17/142
-
7/30/2019 Very Large Hadron Collider
18/142
-
7/30/2019 Very Large Hadron Collider
19/142
-
7/30/2019 Very Large Hadron Collider
20/142
-
7/30/2019 Very Large Hadron Collider
21/142
-
7/30/2019 Very Large Hadron Collider
22/142
-
7/30/2019 Very Large Hadron Collider
23/142
-
7/30/2019 Very Large Hadron Collider
24/142
-
7/30/2019 Very Large Hadron Collider
25/142
-
7/30/2019 Very Large Hadron Collider
26/142
-
7/30/2019 Very Large Hadron Collider
27/142
-
7/30/2019 Very Large Hadron Collider
28/142
-
7/30/2019 Very Large Hadron Collider
29/142
-
7/30/2019 Very Large Hadron Collider
30/142
-
7/30/2019 Very Large Hadron Collider
31/142
-
7/30/2019 Very Large Hadron Collider
32/142
-
7/30/2019 Very Large Hadron Collider
33/142
-
7/30/2019 Very Large Hadron Collider
34/142
-
7/30/2019 Very Large Hadron Collider
35/142
-
7/30/2019 Very Large Hadron Collider
36/142
-
7/30/2019 Very Large Hadron Collider
37/142
-
7/30/2019 Very Large Hadron Collider
38/142
-
7/30/2019 Very Large Hadron Collider
39/142
-
7/30/2019 Very Large Hadron Collider
40/142
-
7/30/2019 Very Large Hadron Collider
41/142
-
7/30/2019 Very Large Hadron Collider
42/142
-
7/30/2019 Very Large Hadron Collider
43/142
-
7/30/2019 Very Large Hadron Collider
44/142
-
7/30/2019 Very Large Hadron Collider
45/142
-
7/30/2019 Very Large Hadron Collider
46/142
-
7/30/2019 Very Large Hadron Collider
47/142
-
7/30/2019 Very Large Hadron Collider
48/142
-
7/30/2019 Very Large Hadron Collider
49/142
-
7/30/2019 Very Large Hadron Collider
50/142
-
7/30/2019 Very Large Hadron Collider
51/142
-
7/30/2019 Very Large Hadron Collider
52/142
-
7/30/2019 Very Large Hadron Collider
53/142
-
7/30/2019 Very Large Hadron Collider
54/142
-
7/30/2019 Very Large Hadron Collider
55/142
-
7/30/2019 Very Large Hadron Collider
56/142
-
7/30/2019 Very Large Hadron Collider
57/142
-
7/30/2019 Very Large Hadron Collider
58/142
-
7/30/2019 Very Large Hadron Collider
59/142
-
7/30/2019 Very Large Hadron Collider
60/142
-
7/30/2019 Very Large Hadron Collider
61/142
-
7/30/2019 Very Large Hadron Collider
62/142
-
7/30/2019 Very Large Hadron Collider
63/142
-
7/30/2019 Very Large Hadron Collider
64/142
-
7/30/2019 Very Large Hadron Collider
65/142
-
7/30/2019 Very Large Hadron Collider
66/142
-
7/30/2019 Very Large Hadron Collider
67/142
-
7/30/2019 Very Large Hadron Collider
68/142
-
7/30/2019 Very Large Hadron Collider
69/142
-
7/30/2019 Very Large Hadron Collider
70/142
-
7/30/2019 Very Large Hadron Collider
71/142
-
7/30/2019 Very Large Hadron Collider
72/142
-
7/30/2019 Very Large Hadron Collider
73/142
-
7/30/2019 Very Large Hadron Collider
74/142
-
7/30/2019 Very Large Hadron Collider
75/142
-
7/30/2019 Very Large Hadron Collider
76/142
-
7/30/2019 Very Large Hadron Collider
77/142
-
7/30/2019 Very Large Hadron Collider
78/142
-
7/30/2019 Very Large Hadron Collider
79/142
-
7/30/2019 Very Large Hadron Collider
80/142
-
7/30/2019 Very Large Hadron Collider
81/142
-
7/30/2019 Very Large Hadron Collider
82/142
-
7/30/2019 Very Large Hadron Collider
83/142
-
7/30/2019 Very Large Hadron Collider
84/142
Appendix ETBM Tunnel Assumptions and Cost Estimating Output (Not
Used)
-
7/30/2019 Very Large Hadron Collider
85/142
Appendix E TBM Tunnel Assumptions and Cost Estimating Output (NotUsed)
Discussion:
The tunnel costs were estimated using TBM cost estimating software and cost databasedeveloped by Hatch Mott MacDonald. Appendix E contains output from the software for TBM
types and tunnel diameters not used in the final estimate, but is included here forcompleteness. Please note the following about the output:
1. Rock Types are called TBM Types in the main body of the report.
2. Appendix E contains Rock Types B and B+, which are not used in the final estimate.
List of Abbreviations:
CIP Cast-in-place
H Hour
m2 Square meters of tunnel face
Nr Number (equivalent to Each)
W Week
mW per meter per week
kWh Kilowatt hour
l Liter
m Meterm3 Cubic meter
-
7/30/2019 Very Large Hadron Collider
86/142
Page 1 of 2
s:\fermi_vlhc\pm\ reports\hmm assumptions (not used).doc TEXT-P.DOT, 00/01v
Fermilab Tunnels
Cost Estimates
Assumptions
General
The following assumptions apply to all tunnel drives:
4800 metres of tunnel from shaft to shaft
2 ten hours shifts undertaken daily, 5 days per week
Tunnels excavated using 3.66 metre or 4.88 metre finished diameter rock TBM
75 percent of TBM cost written off in first drive, 15 percent in second drive, 10 percent inthird drive, and 0 percent in fourth and fifth drives
Labour rates based on Minneapolis Project for Year 2001. (Similar to Illinois)
Specific
Assumptions used for 3.66m (12ft) diameter tunnel in Rock Type B as follows:
Areas of difficult excavation encountered, slowing normal advance rate by 35 percent,
over 20 percent of the tunnel length
Tunnel support consists of 3 metre long rockbolts with steel straps, installed in sets of 3in the tunnel crown, with each set spaced at 3 metre centres. Additional support in theform of 2 sq.m. of timber laggings per metre of tunnel and associated ribs over 50percent of the tunnel length.
Average tunnel advance rate of 122 metres per week
No secondary lining required
Assumptions used for 3.66m (12ft) diameter tunnel in Rock Type B+ as follows:
Areas of difficult excavation encountered, slowing normal advance rate by 35 percent,
over 20 percent of the tunnel length
Tunnel support consists of 3 metre long rockbolts with steel straps, installed in sets of 3in the tunnel crown, with each set spaced at 3 metre centres. Additional support in theform of 2 sq.m. of timber laggings per metre of tunnel and associated ribs over 50percent of the tunnel length.
Average tunnel advance rate of 122 metres per week
300mm thick concrete secondary lining installed on completion of tunnel boring
-
7/30/2019 Very Large Hadron Collider
87/142
Page 2 of 2
s:\fermi_vlhc\pm\ reports\hmm assumptions (not used).doc TEXT-P.DOT, 00/01v
Average lining installation rate of 225 metres per week
Assumptions used for 4.88m (16ft) diameter tunnel in Rock Type B as follows:
Areas of difficult excavation encountered, slowing normal advance rate by 40 percent,over 20 percent of the tunnel length
Tunnel support consists of 3 metre long rockbolts with steel straps, installed in sets of 3in the tunnel crown, with each set spaced at 3 metre centres. Additional support in theform of 3 sq.m. of timber laggings per metre of tunnel and associated ribs over 50percent of the tunnel length.
Average tunnel advance rate of 114 metres per week
No secondary lining required
Assumptions used for 4.88m (16ft) diameter tunnel in Rock Type B+ as follows:
Areas of difficult excavation encountered, slowing normal advance rate by 40 percent,over 20 percent of the tunnel length
Tunnel support consists of 3 metre long rockbolts with steel straps, installed in sets of 3
in the tunnel crown, with each set spaced at 3 metre centres. Additional support in theform of 3 sq.m. of timber laggings per metre of tunnel and associated ribs over 50percent of the tunnel length.
Average tunnel advance rate of 114 metres per week
300mm thick concrete secondary lining installed on completion of tunnel boring
Average lining installation rate of 225 metres per week
-
7/30/2019 Very Large Hadron Collider
88/142
Fermilab Tunnels
Estimate Summary
12 ft dia tunnel (3.66 m)
Rock Type Tunnel Drive Tunnel Length Drive Cost TBM setup Total
(m)
B First 4800 13,900,000 400,000 14,300,000
B Second 4800 11,570,000 200,000 11,770,000
B Third 4800 11,390,000 200,000 11,590,000
B Fourth 4800 11,030,000 200,000 11,230,000
B Fifth 4800 11,030,000 200,000 11,230,000
B+ First 4800 23,380,000 400,000 23,780,000B+ Second 4800 20,610,000 200,000 20,810,000
B+ Third 4800 20,400,000 200,000 20,600,000
B+ Fourth 4800 19,970,000 200,000 20,170,000
B+ Fifth 4800 19,970,000 200,000 20,170,000
16 ft dia tunnel (4.88 m)
Rock Type Tunnel Drive Tunnel Length Drive Cost TBM setup Total
(m)
B First 4800 17,740,000 400,000 18,140,000B Second 4800 13,560,000 200,000 13,760,000
B Third 4800 13,250,000 200,000 13,450,000
B Fourth 4800 12,610,000 200,000 12,810,000
B Fifth 4800 12,610,000 200,000 12,810,000
B+ First 4800 29,000,000 400,000 19,031,000
B+ Second 4800 24,380,000 200,000 14,206,000
B+ Third 4800 24,020,000 200,000 13,852,000
B+ Fourth 4800 23,320,000 200,000 13,144,000
B+ Fifth 4800 23,320,000 200,000 13,144,000
-
7/30/2019 Very Large Hadron Collider
89/142
-
7/30/2019 Very Large Hadron Collider
90/142
-
7/30/2019 Very Large Hadron Collider
91/142
-
7/30/2019 Very Large Hadron Collider
92/142
-
7/30/2019 Very Large Hadron Collider
93/142
-
7/30/2019 Very Large Hadron Collider
94/142
-
7/30/2019 Very Large Hadron Collider
95/142
-
7/30/2019 Very Large Hadron Collider
96/142
-
7/30/2019 Very Large Hadron Collider
97/142
-
7/30/2019 Very Large Hadron Collider
98/142
-
7/30/2019 Very Large Hadron Collider
99/142
-
7/30/2019 Very Large Hadron Collider
100/142
-
7/30/2019 Very Large Hadron Collider
101/142
-
7/30/2019 Very Large Hadron Collider
102/142
-
7/30/2019 Very Large Hadron Collider
103/142
-
7/30/2019 Very Large Hadron Collider
104/142
-
7/30/2019 Very Large Hadron Collider
105/142
-
7/30/2019 Very Large Hadron Collider
106/142
-
7/30/2019 Very Large Hadron Collider
107/142
-
7/30/2019 Very Large Hadron Collider
108/142
-
7/30/2019 Very Large Hadron Collider
109/142
-
7/30/2019 Very Large Hadron Collider
110/142
-
7/30/2019 Very Large Hadron Collider
111/142
-
7/30/2019 Very Large Hadron Collider
112/142
-
7/30/2019 Very Large Hadron Collider
113/142
-
7/30/2019 Very Large Hadron Collider
114/142
-
7/30/2019 Very Large Hadron Collider
115/142
-
7/30/2019 Very Large Hadron Collider
116/142
-
7/30/2019 Very Large Hadron Collider
117/142
-
7/30/2019 Very Large Hadron Collider
118/142
-
7/30/2019 Very Large Hadron Collider
119/142
-
7/30/2019 Very Large Hadron Collider
120/142
-
7/30/2019 Very Large Hadron Collider
121/142
-
7/30/2019 Very Large Hadron Collider
122/142
-
7/30/2019 Very Large Hadron Collider
123/142
-
7/30/2019 Very Large Hadron Collider
124/142
-
7/30/2019 Very Large Hadron Collider
125/142
-
7/30/2019 Very Large Hadron Collider
126/142
-
7/30/2019 Very Large Hadron Collider
127/142
-
7/30/2019 Very Large Hadron Collider
128/142
-
7/30/2019 Very Large Hadron Collider
129/142
-
7/30/2019 Very Large Hadron Collider
130/142
-
7/30/2019 Very Large Hadron Collider
131/142
-
7/30/2019 Very Large Hadron Collider
132/142
-
7/30/2019 Very Large Hadron Collider
133/142
-
7/30/2019 Very Large Hadron Collider
134/142
-
7/30/2019 Very Large Hadron Collider
135/142
-
7/30/2019 Very Large Hadron Collider
136/142
-
7/30/2019 Very Large Hadron Collider
137/142
-
7/30/2019 Very Large Hadron Collider
138/142
-
7/30/2019 Very Large Hadron Collider
139/142
-
7/30/2019 Very Large Hadron Collider
140/142
-
7/30/2019 Very Large Hadron Collider
141/142
-
7/30/2019 Very Large Hadron Collider
142/142