vegetative stabilization...(minimize compaction in areas where infiltration is to occur) •...

58
VEGETATIVE STABILIZATION Darl Rosenquest PE, PG An Overview of Erosion Sediment Controls and Permitting FALL 2019

Upload: others

Post on 23-Jan-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

VEGETATIVE STABILIZATION

Darl Rosenquest PE, PG An Overview of Erosion Sediment Controls

and Permitting FALL 2019

Page 2: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Erosion is a natural process. Human activities which alter the natural process increase the rate of erosion. It is the accelerated erosion by human activities which is regulated under the State’s Department Environmental Protection Chapter 102 regulations. The goal is to minimize accelerated erosion & the resultant of sedimentation.

PURPOSE

Page 3: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

What are temporary E&S BMPs?

BMP – Best Management Practice

Temporary E&S BMPs - Erosion and sedimentation E&S controls, which are designed to minimize the potential for accelerated erosion

Temporary Controls must be maintained and functional until the site is stabilized.

Stabilization - 70% uniform perennial vegetative cover

Page 4: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Common E&S

BMPs

Page 5: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Site Access BMPS

Page 6: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Rock Construction Entrance Maintenance Thickness shall be constantly maintained. A stockpile shall

be maintained on site for this purpose. All sediment deposited on paved roadways shall be

removed and returned to the construction site immediately.

If excessive amounts of sediment are being deposited on roadway, extend length of rock construction entrance by 50 foot increments until condition is alleviated or install wash rack.

Page 7: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Perimeter

Controls

Sheet Flow Treatment 1

Sized based on slope percent and distance

Must be installed properly to function

2

3

Page 8: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Compost Filter Sock

Page 9: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

CFS Trap

Page 10: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Compost Filter Sock Trap

Page 11: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Inlet Protection

Page 12: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Filter Bags

Page 13: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Concrete Washout

Page 14: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Conveyance Channel

Direct clean water around work area Direct dirty water to a BMP

Page 15: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Channels (Dirty Water Interceptor)

Channels Lined ASAP

Ensure Positive Drainage Throughout

Page 16: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Stabilization

As soon as a disturbed area

is brought to final grade it

must be stabilized

1

Disturbed area left inactive for

4 days or more should be

temporarily stabilized

Stabilization must be kept

current with earthmoving

2

3

Page 17: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Sediment Basins

and Traps

Structural E&S BMPs

Page 18: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Sediment Traps & Sediment Basins

Should be

installed before

general

clearing and

grubbing, follow

plan

Page 19: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Sediment Trap

Outlet barrels should be installed before embankment is completed

Page 20: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Trap Maintenance

Sediment should be removed when it reaches the clean-out level

Marked by a line on the clean out stake

Page 21: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

• Excavation of key trench • Excavation of basin

(Minimize compaction in areas where infiltration is to occur)

• Construction of embankment (Compaction)

• Installation of barrel pipe and outlet structure

• Installation of antiseep collars

• Installation of emergency spillway

Sediment Basins

Critical Stages

of Construction

PA Title 25, Chapter 102.8(k)

Permit Part A, Condition 2(b)

Page 22: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Sediment Basin

Page 23: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Outfall Protection-Rock Apron

Page 24: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Outlet Barrel &

Embankment

Outlet barrels should be installed before embankment is completed

Page 25: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Outlet Structure Orifices on Permanent Risers should be sealed

Page 26: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Standard Construction Detail 7-8

Page 27: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Temporary Outlet Riser

What is wrong with this picture?

Page 28: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Skimmer

Page 29: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Skimmer Attachment Problems

Page 30: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Emergency Spillway

Emergency Spillways should have suitable protective linings

Page 31: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Sediment Basin Maintenance

Sediment should be

removed when it reaches

the clean-out level

Clogged risers should be

reopened

Leaking structures and

spillways should be repaired

Page 32: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Protecting Stormwater Facilities DURING Construction

Page 33: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Minimize Compaction

Use long arm excavators for infiltration facility construction

What are Infiltration Facilities • Raingardens/Bio-retention basins • Infiltration basins • Underground infiltration systems • Permeable pavement • Infiltration trenches

READ THE PLAN

Page 34: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Record Keeping

Visual Inspections

Permit Part A, Condition 2(a)

Page 35: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Visual Site Inspection Report

Weekly & after every runoff event

Make copies of blank form

Keep reports in job trailer

Revised May 2018

Page 36: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Converting Sediment

Basins to Stormwater

Facilities

Stormwater Facilities PCSM

Page 37: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Should the Sediment Basin Be Converted?

Sediment Basin

Directly Upstream

Page 38: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Should the Sediment Basin Be Converted?

Sediment Basin

Directly Upstream

Page 39: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Dewatering Basins

Don’t work in wet conditions

Page 40: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Conversion of Pond Structures

Removal of Temporary E&S Structure

Addition of Permanent Structure

Components

Baffles

Plywood Boxes

Barrel Risers

Skimmers

Restriction plates Seals

Trash racks

Underdrains

Bio-soil media Plantings

-

+

Page 41: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Critical stages of construction Follow Construction

Sequence on approved plan

PA Title 25, Chapter 102.8(k)

Permit Part A, Condition 2(b)

Page 42: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Non-Grandfathered NOTs

PA Title 25, Chapter 102.8(m)(2)

Permit Part C, Condition 14(b), 14(d), 14(f) and 14(g)

• Initial instrument recording

• New Property Owner Notices

• Long-term O&M Agreements

Notice of Termination (NOT) Process

PA Title 25, Chapter 102.8(k)(l)

Permit Part C, Condition 5(d)

• Licensed Professional for Critical Stages of Construction

NOT process starts when

permittee obtains NPDES

permit

Page 43: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

• Applied after Nov 19, 2010

OR

• Applied before Nov 19, 2010 AND renewed after Jan 1, 2013

Non-Grandfathered NOTs

PA Title 25, Chapter 102.8(a) Permit Part C, Condition 14

Page 44: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

PA Title 25, Chapter 102.8(m)(2)

*Documents required for Initial Recording

Note: PCSM FILING NOTICE has been removed

Required documents for Instrument Filing Recording Documents

Legal Instrument*

PCSM Plan*/Record Drawing/As-builts

Long-Term O&M Plan*

Long-Term O&M Agreements

Permit Part C, Condition 14(f)(g)

Page 45: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Legal Instrument

Initial Recording Documents

Page 46: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

PCSM Plan

Initial Recording Documents

Page 47: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Long-Term O&M Plan

Initial Recording Documents

Easy to read

Be Specific

Page 48: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Recorder of Deeds Receipt

Initial Recording Documents

PA Title 25, Chapter 102.7(b)(5) Permit Part C, Condition 14(f)(g) Proof of Filing

Page 49: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Developer and contractor remain responsible for long-term operation and maintenance of stormwater facilities.

Permit Termination

PA Title 25, Chapter 102.7(c)

Permit Part C, Condition 14(e)

Page 50: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

NOT Documents

PA Title 25, Chapter 102.7(b)

Permit Part C, Condition 14

Required documents for NOT submittal

NOT Form B 1/2018, Page 8 NOT Checklist

Page 51: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Non-Grandfathered NOTs

PA Title 25, Chapter 102.8(m)(2)

Required documents for Instrument Filing

Recording Documents NOT

NOT Form B 1/2018, Page 3 Section 7b

Page 52: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Record Drawing/As-Builts

NOT & Amended Recording Documents

Page 53: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Recorder of Deeds Receipt

NOT Documents

PA Title 25, Chapter 102.7(b)(5) Permit Part C, Condition 14(f)(g) Proof of Filing

Page 54: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Copy of Landowner Notices & O&M Maintenance Agreement

NOT & Amended Recording Documents

Complies w/ 102.8(m)(2) • Location of PCSM BMPs • Inspection and reporting • O&M Person/Entity • Access for each PCSM BMP • O&M Plan

Permit Part C, Condition 14(g)

Page 55: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

DEP Forms https://www.dep.pa.gov/Business/Water/CleanWater/StormwaterMgmt/Stormwater%20Construction/Pages/default.aspx

Search Engine “PA DEP Construction

Stormwater”

Includes updated Alternative BMP List

Page 56: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

DEP Forms https://www.conservationsolutioncenter.org/solution-center/soils/chapter-102-permit-types-and-resources

accdpa.org

Page 57: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

Melinda Muehlbronner

[email protected] | 412-291-8002

Chapter 102 Program Lead

Page 58: VEGETATIVE STABILIZATION...(Minimize compaction in areas where infiltration is to occur) • Construction of embankment (Compaction) • Installation of barrel pipe and outlet structure

? Questions