vc summer unit 2/3 update - nrc: home page · vc summer unit 2/3 update 1 . cv assembly mab...

23
Alan Torres New Nuclear Deployment SCANA/South Carolina Electric & Gas NUCLEAR | South Carolina’s Clean Energy Solution VC Summer Unit 2/3 Update 1

Upload: others

Post on 21-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –

Alan Torres New Nuclear Deployment

SCANA/South Carolina Electric & Gas

NUCLEAR | South Carolina’s Clean Energy Solution

VC Summer Unit 2/3 Update

1

Page 2: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –

CV Assembly

MAB

Contractor Support

Personnel

Unit 3

Unit 2 Storage

HLD

Cooling Towers

VC Summer 2 & 3 – Construction Site 2014

2

Page 3: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –

3

Placement of the Containment Vessel Bottom Head

Placement of Containment Vessel Ring 1

Placement of Module CA-20

3

Unit 2 Nuclear Island

Page 4: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –

4

Unit 2 NI/TB from Southeast Corner

4

Unit 2 Nuclear Island

Unit 2 NI from Southwest Corner

4

Page 5: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –

5

• Four Courses

• A lower and an Upper Equipment Hatch

• A lower and an Upper

Personnel Hatch

• An external Stiffener

Unit 2 Containment Vessel Lower Ring

5

Page 6: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –

6

Page 7: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –

7

Page 8: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –

8

Containment Vessel Concrete Layers

Layer A

NI Basemat

Layer B Layer C

Pedestal Layer 1

8

Page 9: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –

9

WaterBoxes

CH-80

Condenser A

CH-81B

Condenser B

Condenser C CH-81A

Turbine Building Layout

CH-82

CH-81C

9

Page 10: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –

10

Condenser C

CH81B CH81A CH80

Condenser B

U2 Turbine Building

Condenser A

CH82

10 10

Page 11: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –

11

Feedwater Heaters

U2 Turbine Building Eastside

Continued Progress on Turbine Building

11

Page 12: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –

12

U2 Turbine Building Northside

12

Page 13: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –

13

13

Unit 2 Nuclear Island • Place Concrete in CA20 • Fabricate and Set CA05—CVS / Access Tunnel / PXS-B Walls • Fabricate and Set CA01—Steam Generator and Refueling Canal • Fabricate and Set CA02 —IRWST / Pressurizer Wall • Fabricate and Set CA03 —IRWST Southwest Walls • Set First-Floor Mechanical Modules • Start Shield Building

Turbine Building • Complete Condenser component installation • Complete foundation at Elevation 100’0” • Start First-Bay foundation

Upcoming 2014 Construction Milestones

13

Page 14: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –

14

Unit 3 Nuclear Island

CVBH

Column line 1 wall

Column line I wall

14

Page 15: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –

15

Unit 3 Nuclear Island

Column line 1 wall Column line

N wall

15

Page 16: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –

16

Unit 3 Containment Vessel Bottom Head

16

Page 17: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –

17

Unit 3 Turbine Building Area

17

Circ Water Risers

Circ Water Pipes

Page 18: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –

18 18

Upcoming 2014 Construction Milestones

18 First Quarter 2014 | Earnings Conference Call

Unit 3 Nuclear Island • Set Containment Vessel Bottom Head (CVBH) • Grout CVBH • Place first level of concrete in CVBH • Fabricate and Set CA04—Reactor Vessel Cavity • Place Auxiliary Building walls – A2 Elevation (66’6”-82’6”) Turbine Building • Complete Backfill • Install 82’6” basement foundation and walls • Fabricate and install Condenser components • Install CH Structural Steel modules

18

Page 19: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –

19

• Unit 2 FNC, 3/11/13, 7000 cubic yards of concrete

• Unit 2 CR10 set, 4/3/13

• Unit 2 Containment Vessel Bottom Head placed, 5/22/13

• Unit 3 FNC, 11/4/13

• Unit 2 CV Ring 1

• Unit 3 CV Bottom Head

• Switchyard energized

• Cooling Tower 2A structure erected

• Unit 2 Turbine Building Basemat & Basement Walls placed

• Unit 2 Condensers set 12/30/13

• Unit 2 CH80 & CH82 steel set

Units 2 & 3 Construction Milestones – Completed

19

Page 20: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –

20

Units 2 & 3 Accumulator Tanks Unit 3 Core Makeup Tanks

Units 2 Turbine Waterbox Unit 2 Turbine Stator 20

Page 21: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –

21

• Assembly weight with oil - 529,800lbs each

• 3 in service, 1 spare

• 12,720 gallons each

• Stored Air Filled

Unit 2 Main Step Up Transformers - 230/26kV

21

Page 22: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –

22

Lesson Learned

• Green NCV of 10 CFR Part 50, Appendix B, Criterion VII “for failure to assure purchased equipment met procurement and ITAAC requirements”

• Vendor provided the average wall thickness and average outer diameter, but did not provide/retain the data that supported the average

• The average values were used to obtain the “calculated volume” of the accumulator tanks

• Error required the tanks to be re-measured onsite

• ITAAC team is now more involved in the procurement process to ensure documentation will support ITAAC closure

22

Page 23: VC Summer Unit 2/3 Update - NRC: Home Page · VC Summer Unit 2/3 Update 1 . CV Assembly MAB Contractor Support Personnel Unit 3 Unit 2 Storage HLD Cooling Towers VC Summer 2 & 3 –

23

Questions

23