Page 1: V.C. Summer Construction Update. · Placement of Module CA-20 Second Quarter 2014 | Earnings Conference Call 9 Unit 2 Nuclear Island. 10. 11. Condenser A CH82 CH81B CH81A Condenser

NUCLEAR | South Carolina’s Clean Energy Solution

Construction UpdateNew Nuclear Deployment

SCANA/South Carolina Electric & Gas

NOV 2014

NUCLEAR | South Carolina’s Clean Energy Solution

Page 2: V.C. Summer Construction Update. · Placement of Module CA-20 Second Quarter 2014 | Earnings Conference Call 9 Unit 2 Nuclear Island. 10. 11. Condenser A CH82 CH81B CH81A Condenser

SCE&G 533Management 4NND 89Operational Readiness 312Training 54Unit 1 36SCANA IT 7SCANA Insurance 1SCANA – Financial 12Contractors 18

Total New Nuclear Staffing

Consortium 3,300CB&I 2,620Westinghouse 150Subcontractors 530

2

Page 3: V.C. Summer Construction Update. · Placement of Module CA-20 Second Quarter 2014 | Earnings Conference Call 9 Unit 2 Nuclear Island. 10. 11. Condenser A CH82 CH81B CH81A Condenser

VC Summer - November 2008 3

VCS Unit 1

New Nuclear Deployment

Office

Page 4: V.C. Summer Construction Update. · Placement of Module CA-20 Second Quarter 2014 | Earnings Conference Call 9 Unit 2 Nuclear Island. 10. 11. Condenser A CH82 CH81B CH81A Condenser

4 VC Summer - October 2011

Page 5: V.C. Summer Construction Update. · Placement of Module CA-20 Second Quarter 2014 | Earnings Conference Call 9 Unit 2 Nuclear Island. 10. 11. Condenser A CH82 CH81B CH81A Condenser

Safety Message

5Units 2 & 3 – May 2014 Site Overview

Page 6: V.C. Summer Construction Update. · Placement of Module CA-20 Second Quarter 2014 | Earnings Conference Call 9 Unit 2 Nuclear Island. 10. 11. Condenser A CH82 CH81B CH81A Condenser

CA Modules in Nuclear Island

CA20

CVBH

CA05

CA04

Upcoming Construction Milestones

Page 7: V.C. Summer Construction Update. · Placement of Module CA-20 Second Quarter 2014 | Earnings Conference Call 9 Unit 2 Nuclear Island. 10. 11. Condenser A CH82 CH81B CH81A Condenser

CA Modules Inside Containment

Upcoming Construction Milestones

Page 8: V.C. Summer Construction Update. · Placement of Module CA-20 Second Quarter 2014 | Earnings Conference Call 9 Unit 2 Nuclear Island. 10. 11. Condenser A CH82 CH81B CH81A Condenser

Unit 2 Containment Vessel Ring 1

Page 9: V.C. Summer Construction Update. · Placement of Module CA-20 Second Quarter 2014 | Earnings Conference Call 9 Unit 2 Nuclear Island. 10. 11. Condenser A CH82 CH81B CH81A Condenser

Placement of the Containment Vessel Bottom Head

Placement of Containment Vessel Ring 1

Placement of Module CA-20

9Second Quarter 2014 | Earnings Conference Call

Unit 2 Nuclear Island

Page 10: V.C. Summer Construction Update. · Placement of Module CA-20 Second Quarter 2014 | Earnings Conference Call 9 Unit 2 Nuclear Island. 10. 11. Condenser A CH82 CH81B CH81A Condenser

10

Page 11: V.C. Summer Construction Update. · Placement of Module CA-20 Second Quarter 2014 | Earnings Conference Call 9 Unit 2 Nuclear Island. 10. 11. Condenser A CH82 CH81B CH81A Condenser

11

Page 12: V.C. Summer Construction Update. · Placement of Module CA-20 Second Quarter 2014 | Earnings Conference Call 9 Unit 2 Nuclear Island. 10. 11. Condenser A CH82 CH81B CH81A Condenser

Condenser A

CH81A CH81BCH82

Condenser B

U2 Turbine Building

Condenser C

CH80

Page 13: V.C. Summer Construction Update. · Placement of Module CA-20 Second Quarter 2014 | Earnings Conference Call 9 Unit 2 Nuclear Island. 10. 11. Condenser A CH82 CH81B CH81A Condenser

93

Page 14: V.C. Summer Construction Update. · Placement of Module CA-20 Second Quarter 2014 | Earnings Conference Call 9 Unit 2 Nuclear Island. 10. 11. Condenser A CH82 CH81B CH81A Condenser

14

Page 15: V.C. Summer Construction Update. · Placement of Module CA-20 Second Quarter 2014 | Earnings Conference Call 9 Unit 2 Nuclear Island. 10. 11. Condenser A CH82 CH81B CH81A Condenser

15

Page 16: V.C. Summer Construction Update. · Placement of Module CA-20 Second Quarter 2014 | Earnings Conference Call 9 Unit 2 Nuclear Island. 10. 11. Condenser A CH82 CH81B CH81A Condenser

Upcoming Construction Milestones

Unit 2 Auxiliary Building First Floor Mechanical Modules

Page 17: V.C. Summer Construction Update. · Placement of Module CA-20 Second Quarter 2014 | Earnings Conference Call 9 Unit 2 Nuclear Island. 10. 11. Condenser A CH82 CH81B CH81A Condenser

17

Page 18: V.C. Summer Construction Update. · Placement of Module CA-20 Second Quarter 2014 | Earnings Conference Call 9 Unit 2 Nuclear Island. 10. 11. Condenser A CH82 CH81B CH81A Condenser

96

Page 19: V.C. Summer Construction Update. · Placement of Module CA-20 Second Quarter 2014 | Earnings Conference Call 9 Unit 2 Nuclear Island. 10. 11. Condenser A CH82 CH81B CH81A Condenser

19

Page 20: V.C. Summer Construction Update. · Placement of Module CA-20 Second Quarter 2014 | Earnings Conference Call 9 Unit 2 Nuclear Island. 10. 11. Condenser A CH82 CH81B CH81A Condenser

CA20 Transport 20

Page 21: V.C. Summer Construction Update. · Placement of Module CA-20 Second Quarter 2014 | Earnings Conference Call 9 Unit 2 Nuclear Island. 10. 11. Condenser A CH82 CH81B CH81A Condenser

CA01 Module Assembly On Site

21

Page 22: V.C. Summer Construction Update. · Placement of Module CA-20 Second Quarter 2014 | Earnings Conference Call 9 Unit 2 Nuclear Island. 10. 11. Condenser A CH82 CH81B CH81A Condenser

CA05 Module Assembly On Site

22

Page 23: V.C. Summer Construction Update. · Placement of Module CA-20 Second Quarter 2014 | Earnings Conference Call 9 Unit 2 Nuclear Island. 10. 11. Condenser A CH82 CH81B CH81A Condenser

Units 2 & 3 Cooling Towers

Fan & Shroud Installation

Cooling Tower 2A , 2B & 3A South Side

Page 24: V.C. Summer Construction Update. · Placement of Module CA-20 Second Quarter 2014 | Earnings Conference Call 9 Unit 2 Nuclear Island. 10. 11. Condenser A CH82 CH81B CH81A Condenser

24

Page 25: V.C. Summer Construction Update. · Placement of Module CA-20 Second Quarter 2014 | Earnings Conference Call 9 Unit 2 Nuclear Island. 10. 11. Condenser A CH82 CH81B CH81A Condenser

25

Unit 2 Turbine Components at the Port of Charleston

Unit 2 Reactor Vessel at Site

Unit 2 Deaerator Transport

Page 26: V.C. Summer Construction Update. · Placement of Module CA-20 Second Quarter 2014 | Earnings Conference Call 9 Unit 2 Nuclear Island. 10. 11. Condenser A CH82 CH81B CH81A Condenser

Unit 3 Deaerator Transport 26

Length: 140 feetDiameter: 18 feetWeight: 300 tons

Page 27: V.C. Summer Construction Update. · Placement of Module CA-20 Second Quarter 2014 | Earnings Conference Call 9 Unit 2 Nuclear Island. 10. 11. Condenser A CH82 CH81B CH81A Condenser

Unit 2 Main & Auxiliary

Transformers

Unit 2 & 3 Core Makeup Tanks

Unit 2 & 3 Accumulator Tanks

27Components Arriving on Site

Page 28: V.C. Summer Construction Update. · Placement of Module CA-20 Second Quarter 2014 | Earnings Conference Call 9 Unit 2 Nuclear Island. 10. 11. Condenser A CH82 CH81B CH81A Condenser

Unit 2 Diesel Generators

Unit 2 Integrated Head Package

Unit 2

More Components Arriving on Site 28

Unit 2 Generator Stator

Page 29: V.C. Summer Construction Update. · Placement of Module CA-20 Second Quarter 2014 | Earnings Conference Call 9 Unit 2 Nuclear Island. 10. 11. Condenser A CH82 CH81B CH81A Condenser

Steam Generator Load Out 29

Page 30: V.C. Summer Construction Update. · Placement of Module CA-20 Second Quarter 2014 | Earnings Conference Call 9 Unit 2 Nuclear Island. 10. 11. Condenser A CH82 CH81B CH81A Condenser

Questions?

30