vaswani brentwood - status of work progress as on … · 12 th floor (2flat completed) in progress....
TRANSCRIPT
R E P O R T I N G
L I V E F R O M T H E
F I E L D
S T A T U S O F W O R K P R O G R E S S
A S O N
11/ 0 5 / 2 0 1 5
BLOCK A
BLOCK B
BLOCK C
BLOCK D
EXTERNAL WORKS
EXTERNAL WORKS
BLOCK-WISE PROGRESS STATUS
BLOCK A
Structural work
OHT- 100% Plaster work Completed.
Parapet wall 100% Plaster work completed.
Block work
Block work Completed.
Internal plastering
14th Floor 3 flat completed, 1 flat in progress.
14th Floor staircase area plaster in progress.
Plumbing work
4th & 5th floor utility work Completed.
Cistern tank fixing complete till 11th floor.
CPVC and PVC in toilets 11th & 12th floor in progress.
Electrical work
14th floor work is completed.
Waterproofing work
12th 13th & 14th floor bore packing Completed.
12th Floor toilet concreting completed
External plastering work
North side 800sqm completed (Total Qty 1252 sqm)
Tiling work
2nd floor work in Progress.
BLOCK-WISE PROGRESS STATUS
BLOCK B
Structural work
Super Terrace Works completed.
Block work
SBM work in 12th floor completed, 11th 4 flats completed, 13th floor
3 flats completed & 14th floor work is in progress. Super terrace &
terrace block work completed
Internal plastering
11th floor work in progress.
12th floor (2flat completed) in progress.
Plumbing work
Cistern fixed up to 9th floor.
Diverter fixing in progress 6th Floor to 9th floor.
Electrical work
13th floor work is in progress.
Waterproofing work
4th & 5th floor utility plaster is in progress.
11th and 12th floor bore packing Completed.
Tiling work
Tiling work is progress in 3rd & 4th floor.
BLOCK-WISE PROGRESS STATUS
BLOCK C
Structural work
Parapet wall- 60% complete.
OHT wall ready for concrete.
Block work
SBM work in 14th floor work in progress.
Internal plastering
12th floor work in progress.
Plumbing work
10th floor work is in progress.
Electrical work
13th floor work in progress.
Waterproofing work
12th floor work completed.
13th floor bore packing in progress.
Tiling work
3rd floor work in progress.
BLOCK-WISE PROGRESS STATUS
BLOCK D
Structural work
Parapet wall is completed.
OHT- Top slab concrete completed.
Block work
SBM work in 14th floor work completed.
Internal plastering
12th floor work completed.
13th floor work in progress.
Plumbing work
10th floor work is in progress.
Electrical work
14th floor work is in progress.
Waterproofing work
13th floor work is in progress toilets only.
Tiling work
3rd floor work in progress.
External Works
1. Pour 12/Swimming pool concrete completed.
2. Basement soling work in progress from tower D to Tower C.
3. External compound wall 25mt concrete casted near north-
east corner.