R E P O R T I N G L I V E F R O M T H E F I E L D S T A T U S O F W O R K P R O G R E S S A S O N 11/ 0 5 / 2 0 1 5

Upload: others

Post on 02-Jun-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: VASWANI BRENTWOOD - STATUS OF WORK PROGRESS AS ON … · 12 th floor (2flat completed) in progress. Plumbing work Cistern fixed up to 9th floor. Diverter fixing in progress 6 th Floor

R E P O R T I N G

L I V E F R O M T H E

F I E L D

S T A T U S O F W O R K P R O G R E S S

A S O N

11/ 0 5 / 2 0 1 5

Page 2: VASWANI BRENTWOOD - STATUS OF WORK PROGRESS AS ON … · 12 th floor (2flat completed) in progress. Plumbing work Cistern fixed up to 9th floor. Diverter fixing in progress 6 th Floor

BLOCK A

Page 3: VASWANI BRENTWOOD - STATUS OF WORK PROGRESS AS ON … · 12 th floor (2flat completed) in progress. Plumbing work Cistern fixed up to 9th floor. Diverter fixing in progress 6 th Floor

BLOCK B

Page 4: VASWANI BRENTWOOD - STATUS OF WORK PROGRESS AS ON … · 12 th floor (2flat completed) in progress. Plumbing work Cistern fixed up to 9th floor. Diverter fixing in progress 6 th Floor

BLOCK C

Page 5: VASWANI BRENTWOOD - STATUS OF WORK PROGRESS AS ON … · 12 th floor (2flat completed) in progress. Plumbing work Cistern fixed up to 9th floor. Diverter fixing in progress 6 th Floor

BLOCK D

Page 6: VASWANI BRENTWOOD - STATUS OF WORK PROGRESS AS ON … · 12 th floor (2flat completed) in progress. Plumbing work Cistern fixed up to 9th floor. Diverter fixing in progress 6 th Floor

EXTERNAL WORKS

Page 7: VASWANI BRENTWOOD - STATUS OF WORK PROGRESS AS ON … · 12 th floor (2flat completed) in progress. Plumbing work Cistern fixed up to 9th floor. Diverter fixing in progress 6 th Floor

EXTERNAL WORKS

Page 8: VASWANI BRENTWOOD - STATUS OF WORK PROGRESS AS ON … · 12 th floor (2flat completed) in progress. Plumbing work Cistern fixed up to 9th floor. Diverter fixing in progress 6 th Floor

BLOCK-WISE PROGRESS STATUS

BLOCK A

Structural work

OHT- 100% Plaster work Completed.

Parapet wall 100% Plaster work completed.

Block work

Block work Completed.

Internal plastering

14th Floor 3 flat completed, 1 flat in progress.

14th Floor staircase area plaster in progress.

Plumbing work

4th & 5th floor utility work Completed.

Cistern tank fixing complete till 11th floor.

CPVC and PVC in toilets 11th & 12th floor in progress.

Electrical work

14th floor work is completed.

Waterproofing work

12th 13th & 14th floor bore packing Completed.

12th Floor toilet concreting completed

External plastering work

North side 800sqm completed (Total Qty 1252 sqm)

Tiling work

2nd floor work in Progress.

Page 9: VASWANI BRENTWOOD - STATUS OF WORK PROGRESS AS ON … · 12 th floor (2flat completed) in progress. Plumbing work Cistern fixed up to 9th floor. Diverter fixing in progress 6 th Floor

BLOCK-WISE PROGRESS STATUS

BLOCK B

Structural work

Super Terrace Works completed.

Block work

SBM work in 12th floor completed, 11th 4 flats completed, 13th floor

3 flats completed & 14th floor work is in progress. Super terrace &

terrace block work completed

Internal plastering

11th floor work in progress.

12th floor (2flat completed) in progress.

Plumbing work

Cistern fixed up to 9th floor.

Diverter fixing in progress 6th Floor to 9th floor.

Electrical work

13th floor work is in progress.

Waterproofing work

4th & 5th floor utility plaster is in progress.

11th and 12th floor bore packing Completed.

Tiling work

Tiling work is progress in 3rd & 4th floor.

Page 10: VASWANI BRENTWOOD - STATUS OF WORK PROGRESS AS ON … · 12 th floor (2flat completed) in progress. Plumbing work Cistern fixed up to 9th floor. Diverter fixing in progress 6 th Floor

BLOCK-WISE PROGRESS STATUS

BLOCK C

Structural work

Parapet wall- 60% complete.

OHT wall ready for concrete.

Block work

SBM work in 14th floor work in progress.

Internal plastering

12th floor work in progress.

Plumbing work

10th floor work is in progress.

Electrical work

13th floor work in progress.

Waterproofing work

12th floor work completed.

13th floor bore packing in progress.

Tiling work

3rd floor work in progress.

Page 11: VASWANI BRENTWOOD - STATUS OF WORK PROGRESS AS ON … · 12 th floor (2flat completed) in progress. Plumbing work Cistern fixed up to 9th floor. Diverter fixing in progress 6 th Floor

BLOCK-WISE PROGRESS STATUS

BLOCK D

Structural work

Parapet wall is completed.

OHT- Top slab concrete completed.

Block work

SBM work in 14th floor work completed.

Internal plastering

12th floor work completed.

13th floor work in progress.

Plumbing work

10th floor work is in progress.

Electrical work

14th floor work is in progress.

Waterproofing work

13th floor work is in progress toilets only.

Tiling work

3rd floor work in progress.

Page 12: VASWANI BRENTWOOD - STATUS OF WORK PROGRESS AS ON … · 12 th floor (2flat completed) in progress. Plumbing work Cistern fixed up to 9th floor. Diverter fixing in progress 6 th Floor

External Works

1. Pour 12/Swimming pool concrete completed.

2. Basement soling work in progress from tower D to Tower C.

3. External compound wall 25mt concrete casted near north-

east corner.

Page 13: VASWANI BRENTWOOD - STATUS OF WORK PROGRESS AS ON … · 12 th floor (2flat completed) in progress. Plumbing work Cistern fixed up to 9th floor. Diverter fixing in progress 6 th Floor

Vaswani Group

Vaswani Victoria,

30 Victoria Road

BANGALORE – 560 047

Call: 080 – 4911 0000

Email: [email protected]

www.vaswanigroup.com