variation of prices - diesel
TRANSCRIPT
Variation of Prices foe Automotive Gas Oil (Diesoline)Fuel Oil and Bitumen
Estimated of Materials subjected to Price Variation
1 Estimation of Diesel Consumption
(a) The Tenderer is required ti fill all plants and equipment (diesel engine type) which shall beemployed by him for the Works together with the estimation of consumption of diesoline of each plantbut excluding plant an equipment located outside the limits of the Site.
(b) The quantities estimated by the Tenderer shall be supported with documentary evidence and are subject to verification and adjustment by the S.O. The attached Table 1 for estimation of quantity ofdiesel consumed may be used as a guide.
(c) All plant and equipment shall be categories as follows :-
Category A - Earth Moving Plant and other Equipment (Diesel EngineType) e.g. Track-type tractors (bulldozers), motor grades, excavators,backhoe/loaders, self-propelled scrapes, off-highway trucks (dumptrucks), earth compactors, wheel loaders, tracks loaders, asphalt pavers, agricultural tractors, rollers, compressors, mobile cranes etc.
Category B - Vehicles (Diesel Engine Type) e.g. Tippers (5 cu.m.7 cu.m.) 5-Ton Lorry flat bottom etc.
Category C - Miscellaneous Equipment e.g. water pumps, concretemixers
SUMMARY OF ESTIMATED DIESEL CONSUMPTION
Category A - Earth moving Plant and other = 307,008.00 Litresequipment
Category B - Vehicles = 3,094.84 Litres
Category C - Miscellanous = 12,480.00 Litres
TOTAL ESTIMATED DIESEL CONSUMPT= 322,582.84 Litres
6
employed by him for the Works together with the estimation of consumption of diesoline of each plant
The quantities estimated by the Tenderer shall be supported with documentary evidence and are subject to verification and adjustment by the S.O. The attached Table 1 for estimation of quantity of
"Table 1"
Variation of Prices foe Automotive Gas Oil (Diesoline)Fuel Oil and Bitumen
Estimated Diesel Consumption for Category A- Earth Moving Plant and Other Equipment
Item Plant Capacity No. of Total Plant Average Total No. (in b.h.p) Units Hours to be Consumption Estimated
Employed (per plant- Consumption hours) (in litres)
1 Excavator - PC200 150 1 624.00 22.50 14,040.00
2 Excavator - PC300 220 1 624.00 33.00 20,592.00
3 Excavator - PC100 75 1 1,872.00 11.25 21,060.00
4 Buldozer - D6 250 2 624.00 37.50 46,800.00
5 Roller 125 2 624.00 18.75 23,400.00
6 Tyre Roller 150 1 624.00 22.50 14,040.00
7 Motor Grader 140 1 312.00 21.00 6,552.00
8 Asphalt Paver 270 1 312.00 40.50 12,636.00
9 Dump Truck 215 3 1,040.00 32.25 100,620.00
10 Mixer Truck 215 2 624.00 32.25 40,248.00
11 Rig (to install vertical drain) 150 1 312.00 22.50 7,020.00
Total Carried to Summary : 307,008.00
Note : Use separate attachment if necessary
"Table 1"
8
Variation of Prices foe Automotive Gas Oil (Diesoline)Fuel Oil and Bitumen
Estimated Diesel Consumption for Category B- Vehicles (Diesel Engine Type)
Item Plant Capacity No. of Total Plant Average Total No. (in b.h.p) Units Hours to be Consumption Estimated
Employed (per plant- Consumption hours) (in litres)
1 Pick-up - 5 ton 80 1 5,616.00 0.20 1,132.26
2 Pick-up - double cabin 2 4,867.20 0.20 1,962.58
Total Carried to Summary : 3,094.84
Note : Use separate attachment if necessary
9
Variation of Prices foe Automotive Gas Oil (Diesoline)Fuel Oil and Bitumen
Estimated Diesel Consumption for Category C- Miscellaneous Plant and Equipment
Item Plant Capacity No. of Total Plant Average Total No. (in b.h.p) Units Hours to be Consumption Estimated
Employed (per plant- Consumption hours) (in litres)
1 Water Pump 5 2 624.00 2.50 3,120.00
2 Bending & Cutting Machine 5 2 624.00 2.50 3,120.00
3 Welding Machine 5 2 624.00 2.50 3,120.00
4 Vibrator 5 2 624.00 2.50 3,120.00
Total Carried to Summary : 12,480.00
Note : Use separate attachment if necessary
10
APPENDIX SP1
SPECIAL PROVISION FOR VARIATION OF PRICE
List Of Materials Together With Quantiites And Basic Unit Price
Item Materials Unit Quantity Basic Unit Price No. (RM)
A ROUND STEEL BARS, B.S. 4449
1 6 mm Metric Ton - - 2 10 mm Metric Ton 1.00 2,445.00 3 12 mm Metric Ton - - 4 16 mm Metric Ton - - 5 20 mm to 25 mm Metric Ton - - 6 28 mm & above Metric Ton - -
B MYCON 60
1 6 mm Metric Ton - - 2 10 mm Metric Ton 4.00 2,479.00 3 12 mm Metric Ton 3.00 2,445.00 4 16 mm to 25 mm Metric Ton 15.00 2,392.50 5 28 mm Metric Ton - - 6 32 mm Metric Ton - - 7 40 mm Metric Ton - -
C ORDINARY PORTLAND CEMENT Metric Ton 930.00 273.00 - BS12
D AUTOMOTIVE GAS OIL Litre 322,582.84 2.66 (DIESOLINE)
E FUEL OIL (LIGHT/MEDIUM) Litre 16,129.14 1.62
F BITUMEN
1. 80/100 Penetration Grade Metric Ton 186.12 1,500.00
For The Month Of December 2007
APPENDIX SP1
15
Notes :-
1 Quantities for items A,B and C have been pre-ascertained by the S.O. at the time of tendering.
2 Quantities for items D, E and F shall be estimated by the Contractor at the time of tender. Such quantities shallbe verified and adjusted by the S.O. as may be necessary before the signing of the Contract.
3 The above quantities are intended for the purpose of Price Variation only does not necessarily reflect theactual quantities required for the Contract. The contractor shall for himself the actual quantitiesrequired upon which his tender is deemed to have been based.
4 Price Variation shall be applied to the above quantities fixed or actual quantities used, whichever is the lesser.
5 Tenderes are not required to insert the Basic Unit Prices shall be as stated in the Special Release published by the Department of Statistics, Kuala Lumpur for the re Kota Kinabalufor the month of December 2007 during which the tender closes and shall be stated prior to thesigning of the Contract Document.
16
Quantities for items D, E and F shall be estimated by the Contractor at the time of tender. Such quantities shall
The above quantities are intended for the purpose of Price Variation only does not necessarily reflect the
Price Variation shall be applied to the above quantities fixed or actual quantities used, whichever is the lesser.
during which the tender closes and shall be stated prior to the