Variation of Prices foe Automotive Gas Oil (Diesoline) Fuel Oil and Bitumen Estimated of Materials subjected to Price Variation 1 Estimation of Diesel Consumption (a) The Tenderer is required ti fill all plants and equipment (diesel engine type) w employed by him for the Works together with the estimation of consumption of die but excluding plant an equipment located outside the limits of the Site. (b) The quantities estimated by the Tenderer shall be supported with documentary evi subject to verification and adjustment by the S.O. The attached Table 1 for esti diesel consumed may be used as a guide. (c) All plant and equipment shall be categories as follows :- Category A - Earth Moving Plant and other Equipment (Diesel Engine Type) e.g. Track-type tractors (bulldozers), motor grades, e backhoe/loaders, self-propelled scrapes, off-highway trucks trucks), earth compactors, wheel loaders, tracks loaders, as pavers, agricultural tractors, rollers, compressors, mobile Category B - Vehicles (Diesel Engine Type) e.g. Tippers (5 cu.m. 7 cu.m.) 5-Ton Lorry flat bottom etc. Category C - Miscellaneous Equipment e.g. water pumps, concrete mixers SUMMARY OF ESTIMATED DIESEL CONSUMPTION Category A - Earth moving Plant and other = 307,008.00 equipment Category B - Vehicles = 3,094.84 Category C - Miscellanous = 12,480.00 TOTAL ESTIMATED DIESEL CONSUMPTION = 322,582.84

Upload: penjejak-awan

Post on 27-Nov-2014

249 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Variation of Prices - Diesel

Variation of Prices foe Automotive Gas Oil (Diesoline)Fuel Oil and Bitumen

Estimated of Materials subjected to Price Variation

1 Estimation of Diesel Consumption

(a) The Tenderer is required ti fill all plants and equipment (diesel engine type) which shall beemployed by him for the Works together with the estimation of consumption of diesoline of each plantbut excluding plant an equipment located outside the limits of the Site.

(b) The quantities estimated by the Tenderer shall be supported with documentary evidence and are subject to verification and adjustment by the S.O. The attached Table 1 for estimation of quantity ofdiesel consumed may be used as a guide.

(c) All plant and equipment shall be categories as follows :-

Category A - Earth Moving Plant and other Equipment (Diesel EngineType) e.g. Track-type tractors (bulldozers), motor grades, excavators,backhoe/loaders, self-propelled scrapes, off-highway trucks (dumptrucks), earth compactors, wheel loaders, tracks loaders, asphalt pavers, agricultural tractors, rollers, compressors, mobile cranes etc.

Category B - Vehicles (Diesel Engine Type) e.g. Tippers (5 cu.m.7 cu.m.) 5-Ton Lorry flat bottom etc.

Category C - Miscellaneous Equipment e.g. water pumps, concretemixers

SUMMARY OF ESTIMATED DIESEL CONSUMPTION

Category A - Earth moving Plant and other = 307,008.00 Litresequipment

Category B - Vehicles = 3,094.84 Litres

Category C - Miscellanous = 12,480.00 Litres

TOTAL ESTIMATED DIESEL CONSUMPT= 322,582.84 Litres

Page 2: Variation of Prices - Diesel

6

Page 3: Variation of Prices - Diesel

employed by him for the Works together with the estimation of consumption of diesoline of each plant

The quantities estimated by the Tenderer shall be supported with documentary evidence and are subject to verification and adjustment by the S.O. The attached Table 1 for estimation of quantity of

Page 4: Variation of Prices - Diesel

"Table 1"

Variation of Prices foe Automotive Gas Oil (Diesoline)Fuel Oil and Bitumen

Estimated Diesel Consumption for Category A- Earth Moving Plant and Other Equipment

Item Plant Capacity No. of Total Plant Average Total No. (in b.h.p) Units Hours to be Consumption Estimated

Employed (per plant- Consumption hours) (in litres)

1 Excavator - PC200 150 1 624.00 22.50 14,040.00

2 Excavator - PC300 220 1 624.00 33.00 20,592.00

3 Excavator - PC100 75 1 1,872.00 11.25 21,060.00

4 Buldozer - D6 250 2 624.00 37.50 46,800.00

5 Roller 125 2 624.00 18.75 23,400.00

6 Tyre Roller 150 1 624.00 22.50 14,040.00

7 Motor Grader 140 1 312.00 21.00 6,552.00

8 Asphalt Paver 270 1 312.00 40.50 12,636.00

9 Dump Truck 215 3 1,040.00 32.25 100,620.00

10 Mixer Truck 215 2 624.00 32.25 40,248.00

11 Rig (to install vertical drain) 150 1 312.00 22.50 7,020.00

Total Carried to Summary : 307,008.00

Note : Use separate attachment if necessary

Page 5: Variation of Prices - Diesel

"Table 1"

8

Page 6: Variation of Prices - Diesel

Variation of Prices foe Automotive Gas Oil (Diesoline)Fuel Oil and Bitumen

Estimated Diesel Consumption for Category B- Vehicles (Diesel Engine Type)

Item Plant Capacity No. of Total Plant Average Total No. (in b.h.p) Units Hours to be Consumption Estimated

Employed (per plant- Consumption hours) (in litres)

1 Pick-up - 5 ton 80 1 5,616.00 0.20 1,132.26

2 Pick-up - double cabin 2 4,867.20 0.20 1,962.58

Total Carried to Summary : 3,094.84

Note : Use separate attachment if necessary

Page 7: Variation of Prices - Diesel

9

Page 8: Variation of Prices - Diesel

Variation of Prices foe Automotive Gas Oil (Diesoline)Fuel Oil and Bitumen

Estimated Diesel Consumption for Category C- Miscellaneous Plant and Equipment

Item Plant Capacity No. of Total Plant Average Total No. (in b.h.p) Units Hours to be Consumption Estimated

Employed (per plant- Consumption hours) (in litres)

1 Water Pump 5 2 624.00 2.50 3,120.00

2 Bending & Cutting Machine 5 2 624.00 2.50 3,120.00

3 Welding Machine 5 2 624.00 2.50 3,120.00

4 Vibrator 5 2 624.00 2.50 3,120.00

Total Carried to Summary : 12,480.00

Note : Use separate attachment if necessary

Page 9: Variation of Prices - Diesel

10

Page 10: Variation of Prices - Diesel

APPENDIX SP1

SPECIAL PROVISION FOR VARIATION OF PRICE

List Of Materials Together With Quantiites And Basic Unit Price

Item Materials Unit Quantity Basic Unit Price No. (RM)

A ROUND STEEL BARS, B.S. 4449

1 6 mm Metric Ton - - 2 10 mm Metric Ton 1.00 2,445.00 3 12 mm Metric Ton - - 4 16 mm Metric Ton - - 5 20 mm to 25 mm Metric Ton - - 6 28 mm & above Metric Ton - -

B MYCON 60

1 6 mm Metric Ton - - 2 10 mm Metric Ton 4.00 2,479.00 3 12 mm Metric Ton 3.00 2,445.00 4 16 mm to 25 mm Metric Ton 15.00 2,392.50 5 28 mm Metric Ton - - 6 32 mm Metric Ton - - 7 40 mm Metric Ton - -

C ORDINARY PORTLAND CEMENT Metric Ton 930.00 273.00 - BS12

D AUTOMOTIVE GAS OIL Litre 322,582.84 2.66 (DIESOLINE)

E FUEL OIL (LIGHT/MEDIUM) Litre 16,129.14 1.62

F BITUMEN

1. 80/100 Penetration Grade Metric Ton 186.12 1,500.00

For The Month Of December 2007

Page 11: Variation of Prices - Diesel

APPENDIX SP1

15

Page 12: Variation of Prices - Diesel

Notes :-

1 Quantities for items A,B and C have been pre-ascertained by the S.O. at the time of tendering.

2 Quantities for items D, E and F shall be estimated by the Contractor at the time of tender. Such quantities shallbe verified and adjusted by the S.O. as may be necessary before the signing of the Contract.

3 The above quantities are intended for the purpose of Price Variation only does not necessarily reflect theactual quantities required for the Contract. The contractor shall for himself the actual quantitiesrequired upon which his tender is deemed to have been based.

4 Price Variation shall be applied to the above quantities fixed or actual quantities used, whichever is the lesser.

5 Tenderes are not required to insert the Basic Unit Prices shall be as stated in the Special Release published by the Department of Statistics, Kuala Lumpur for the re Kota Kinabalufor the month of December 2007 during which the tender closes and shall be stated prior to thesigning of the Contract Document.

Page 13: Variation of Prices - Diesel

16

Page 14: Variation of Prices - Diesel

Quantities for items D, E and F shall be estimated by the Contractor at the time of tender. Such quantities shall

The above quantities are intended for the purpose of Price Variation only does not necessarily reflect the

Price Variation shall be applied to the above quantities fixed or actual quantities used, whichever is the lesser.

during which the tender closes and shall be stated prior to the