value of flexibility an introduction using a spreadsheet analysis of a multi-story parking garage

28
Value of Flexibility an introduction using a spreadsheet analysis of a multi-story parking garage Tao Wang and Richard de Neufville

Upload: joanne

Post on 12-Feb-2016

24 views

Category:

Documents


0 download

DESCRIPTION

Value of Flexibility an introduction using a spreadsheet analysis of a multi-story parking garage. Tao Wang and Richard de Neufville. Intended “Take-Aways”. Design for fixed objective (mission or specifications) is engineering base case - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Value of Flexibility an introduction using a spreadsheet analysis of a multi-story parking garage

Value of Flexibilityan introduction

using a spreadsheet analysisof a multi-story parking garage

Tao Wang and Richard de Neufville

Page 2: Value of Flexibility an introduction using a spreadsheet analysis of a multi-story parking garage

Intended “Take-Aways”• Design for fixed objective (mission or

specifications) is engineering base case

• Recognizing variability => different design (because of system non-linearities)

• Recognizing flexibility => even better design (it avoids costs, expands only as needed)

Page 3: Value of Flexibility an introduction using a spreadsheet analysis of a multi-story parking garage

Outline of presentation

• Value at Risk

• Analyzing flexibility using spreadsheet

• Parking garage case

• Mining case

Page 4: Value of Flexibility an introduction using a spreadsheet analysis of a multi-story parking garage

Value at Risk Concept• Value at Risk (VAR) recognizes

fundamental reality: actual value of any design can only be known probabilistically

• Because of inevitable uncertainty in – Future demands on system– Future performance of technology– Many other market, political factors

Page 5: Value of Flexibility an introduction using a spreadsheet analysis of a multi-story parking garage

Value at Risk Definition• Value at Risk (VAR) definition:

– A loss that will not be exceeded at some specified confidence level

– “We are p percent certain that we will not lose more than V dollars for this project.”

• VAR easy to see on cumulative probability distribution (see next figure)

Page 6: Value of Flexibility an introduction using a spreadsheet analysis of a multi-story parking garage

• Look at distribution of NPV of designs A, B:– 90% VAR for NPVA is -$91– 90% VAR for NPVB is $102

CDF

0%

20%

40%

60%

80%

100%

-400 -200 0 200 400 600

NPV

Cum

ulat

ive

Prob

abili

ty

NPVA NPVB 90% VAR for NPVA90%VAR for NPVB 10% Probability

Page 7: Value of Flexibility an introduction using a spreadsheet analysis of a multi-story parking garage

Notes:• Cumulative distribution function (CDF)

shows the probability that the value of a variable is < or = to quantity on x axis

• VAR can be found on the CDF curve:– 90% VAR => 10% probability the value is

less or equal– NPV corresponding to the 10% CDF is

90% VAR

Page 8: Value of Flexibility an introduction using a spreadsheet analysis of a multi-story parking garage

VAR and Flexibility

• VAR is a common financial concept• It stresses downside losses, risks • However, designers also need to look at

upside potential: “Value of Gain” • Flexible design provides value by both:

– Decreasing downside risk– Increasing upside potential– See next figure

Page 9: Value of Flexibility an introduction using a spreadsheet analysis of a multi-story parking garage

Sources of value for flexibility

Cumulative Probability

Value

Original distribution

Distribution with flexibility

Cut downside risks

Expand upside potential

Cut downside ; Expand Upside

Page 10: Value of Flexibility an introduction using a spreadsheet analysis of a multi-story parking garage

Excel Analysis Sequence toillustrate value of flexibility

1: Examine situation without flexibility – This is Base case design

2: Introduce variability (simulation)=> a different design (in general)

3: Introduce flexibility=> a even different and better design

• Note: Excel simulation techniques taught in ESD.70

Page 11: Value of Flexibility an introduction using a spreadsheet analysis of a multi-story parking garage

Parking Garage Case• Garage in area where population expands• Actual demand is necessarily uncertain

• Design Opportunity: Strengthened structure – enables future addition of floor(s) (flexibility)– costs more (flexibility costs)

• Design issue: is extra cost worthwhile?

Page 12: Value of Flexibility an introduction using a spreadsheet analysis of a multi-story parking garage

Parking Garage Case details• Demand

– At start is for 750 spaces– Over next 10 years is expected to rise exponentially by

another 750 spaces– After year 10 may be 250 more spaces– could be 50% off the projections, either way;– Annual volatility for growth is 10%

• Average annual revenue/space used = $10,000

• The discount rate is taken to be 12%

Page 13: Value of Flexibility an introduction using a spreadsheet analysis of a multi-story parking garage

Parking Garage details (Cont)• Costs

– annual operating costs (staff, cleaning, etc.) = $2,000 /year/space available

(note: spaces used is often < spaces available)– Annual lease of the land = $3.6 Million – construction cost = $16,000/space + 10% for each

level above the ground level

• Site can accommodate 200 cars per level

Page 14: Value of Flexibility an introduction using a spreadsheet analysis of a multi-story parking garage

Step 1: Set up base case

0 1 2 3 19 20Demand 750 893 1,015 1,688 1,696Capacity 1,200 1,200 1,200 1,200 1,200Revenue $7,500,000 $8,930,000 $10,150,000 $12,000,000 $12,000,000Recurring Costs

Operating cost $2,400,000 $2,400,000 $2,400,000 $2,400,000 $2,400,000Land leasing cost $3,600,000 $3,600,000 $3,600,000 $3,600,000 $3,600,000 $3,600,000

Cash flow $1,500,000 $2,930,000 $4,150,000 $6,000,000 $6,000,000Discounted Cash Flow $1,339,286 $2,335,778 $2,953,888 $696,641 $622,001Present value of cash flow $32,574,736Capacity costs for up to two levels $6,400,000Capacity costs for levels above 2 $16,336,320Net present value $6,238,416

Year

Demand growth as predicted, no variability

Page 15: Value of Flexibility an introduction using a spreadsheet analysis of a multi-story parking garage

Optimal design for base case (no uncertainty) is 6 floors

-15

-10

-5

0

5

10

2 3 4 5 6 7 8 9

Number of Floors

Exp

ecte

d N

PV

($, M

illio

ns)

Traditional NPV Recognizing uncertainty

Page 16: Value of Flexibility an introduction using a spreadsheet analysis of a multi-story parking garage

Step 2: Simulate uncertainty

0

100

200

300

400

500

600

-17.8 -15.6 -13.5 -11.3 -9.2 -7.0 -4.9 -2.7 -0.6 1.6 3.7 5.9 8.0

Freq

uenc

y

5-floor design Simulated Mean

6-floor design Determ inistic

Result

Lower demand => Loss

Higher demand => Gain limited by garage size

Page 17: Value of Flexibility an introduction using a spreadsheet analysis of a multi-story parking garage

NPV Cumulative Distributions

0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1

-20 -15 -10 -5 0 5 10

Prob

abili

ty

CDF for Result of Simulation Analysis (5-

floor) Implied CDF for Result of

Deterministic NPV Analysis (6-floor)

Compare Actual (5 Fl) with unrealistic fixed 6 Fl design

Page 18: Value of Flexibility an introduction using a spreadsheet analysis of a multi-story parking garage

Recognizing uncertainty => different design (5 floors)

-15

-10

-5

0

5

10

2 3 4 5 6 7 8 9

Number of Floors

Exp

ecte

d N

PV

($, M

illio

ns)

Traditional NPV Recognizing uncertainty

Page 19: Value of Flexibility an introduction using a spreadsheet analysis of a multi-story parking garage

Step 3: Introduce flexibility into design (expand when needed)

0 1 2 3 19 20Demand 820 924 1,044 1,519 1,647Capacity 800 800 1,200 1,600 1,600

Decision on expansion expandExtra capacity 400

Revenue $8,000,000 $8,000,000 $10,440,000 $15,190,000 $16,000,000Recurring Costs

Operating cost $1,600,000 $1,600,000 $2,400,000 $3,200,000 $3,200,000Land leasing cost $3,600,000 $3,600,000 $3,600,000 $3,600,000 $3,600,000 $3,600,000Expansion cost $8,944,320

Cash flow $2,800,000 -$6,144,320 $4,440,000 $8,390,000 $9,200,000Discounted Cash Flow $2,500,000 -$4,898,214 $3,160,304 $974,136 $953,734Present value of cash flow $30,270,287Capacity cost for up to two levels $6,400,000Capacity costs for levels above 2 $7,392,000Price for the option $689,600Net present value $12,878,287

Year

Including Flexibility => Another, better design:

4 Floors with strengthened structure enabling expansion

Page 20: Value of Flexibility an introduction using a spreadsheet analysis of a multi-story parking garage

Summary of design results from different perspectives

Why is the optimal design much better when we design with flexibility?

Perspective Simulation Option Embedded Design Estimated Expected NPVDeterministic No No 6 levels $6,238,416

Recognizing Uncertainty Yes No 5 levels $3,536,474

Incorporating Flexibilty Yes Yes4 levels with strengthened

structure$10,517,140

Page 21: Value of Flexibility an introduction using a spreadsheet analysis of a multi-story parking garage

Sources of value for flexibility:1) Minimize exposure to downside risk

0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1

-20 -15 -10 -5 0 5 10

Pro

babi

lity

5-Floor Design 4-Floor Design

Page 22: Value of Flexibility an introduction using a spreadsheet analysis of a multi-story parking garage

Sources of value for flexibility: 2) Maximize potential for upside gain

0.0%

10.0%

20.0%

30.0%

40.0%

50.0%

60.0%

70.0%

80.0%

90.0%

100.0%

-20 -15 -10 -5 0 5 10 15 20 25 30 35

Prob

abili

ty

CDF for NPV with Flexibility

CDF for NPV without Flexibility

Mean for NPV without Flexibility

Mean for NPV with Flexibility

Page 23: Value of Flexibility an introduction using a spreadsheet analysis of a multi-story parking garage

Comparison of designswith and without flexibility

Wow! Everything is better! How did it happen?

Root cause: change the framing of the problem

• recognize uncertainty ; add in flexibility thinking

Design Design with Flexibility Thinking Design without Flexibility thinking Comparison(4 levels, strengthened structure) (5 levels)

Initial Investment $18,081,600 $21,651,200 Better with optionsExpected NPV $10,517,140 $3,536,474 Better with optionsMinimum Value -$13,138,168 -$18,024,062 Better with optionsMaximum Value $29,790,838 $8,316,602 Better with options

Page 24: Value of Flexibility an introduction using a spreadsheet analysis of a multi-story parking garage

Cash Flow SimulationOption to Abandon in MiningFor a Marginally Profitable Underground

Mining OperationVassilios Kazakidis, Associate ProfessorMining Engineering, Laurentian University

Text refers to spreadsheet analysis used for demonstration

Draft Presentation: Do not quote or circulate without permission

Page 25: Value of Flexibility an introduction using a spreadsheet analysis of a multi-story parking garage

Outline• Cash flow simulation model created in Excel to model an

abandonment decision in a marginally profitable underground nickel mine.

• The model was created using actual cost and production data from a currently operating mine.

• Nickel is a historically volatile metal (~35%/yr).• Abandonment occurs when metal prices fall low enough to make

the project unprofitable (the trigger).• When metal prices fall low enough, this causes the operating

costs to exceed the revenues generated. • If this occurs during any period, an “IF statement” in the model

triggers the abandonment, and an associated abandonment cost is incurred.

By Vassilios Kazakidis (Do not quote or circulate without permission)

Page 26: Value of Flexibility an introduction using a spreadsheet analysis of a multi-story parking garage

Revenue and Cost Simulation• The Revenue generated during each period is

determined by simulating the metal price based on an inputted initial value ($2.8/lb) and volatility (40%) and using the Brownian motion. The metal price is then multiplied by the number of lbs mined per period to give the revenue generated.

• The Operating cost is simulated for each period based on an inputted initial value ($1.412 M) and cost volatility (9.6%), again using Brownian motion. Cost volatility is caused by uncertainties due to ground problems or equipment failures which are common occurrences in underground mines, and which affect costs.

• The mine has the option to abandon at the start of any of the simulated periods if operating cost > revenue.

By Vassilios Kazakidis (Do not quote or circulate without permission)

Page 27: Value of Flexibility an introduction using a spreadsheet analysis of a multi-story parking garage

Model Layout• The model is divided into 3 spreadsheet tabs:

– Input Parameters– No Option to Abandon– Option to Abandon

• In the “No Option” tab, no abandonment can occur.• In the “Option to Abandon” tab, shutdown may occur.• Simulating NPV values for both of these spreadsheets will

show that the NPV in the “option to abandon” is consistently higher then with “no option”.

• With the “option to abandon”, the very low (even negative) tail-end NPV values are essentially cut-off.

• The difference between the simulated NPV’s in both spreadsheets is the value of flexibility.

By Vassilios Kazakidis (Do not quote or circulate without permission)

Page 28: Value of Flexibility an introduction using a spreadsheet analysis of a multi-story parking garage

Summary

• Sources of value for flexibility– Cut downside risk– Expand upside potential

• VAR chart is a neat way to represent the sources of value for flexibility

• Spreadsheet with simulation is a powerful tool for estimating value of flexibility