value engineering the termination of the blue river flood conveyance channel
DESCRIPTION
Robert Prager, PE Strategic Value Solutions, Inc Independence, Missouri . Value Engineering the Termination of the Blue River Flood Conveyance Channel. Alan Schlindwein, PE US Army Corps of Engineers Kansas City, Missouri June 14, 2012. Battle of Westport. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Value Engineering the Termination of the Blue River Flood Conveyance Channel](https://reader036.vdocuments.mx/reader036/viewer/2022062501/5681638c550346895dd47c6b/html5/thumbnails/1.jpg)
US Army Corps of EngineersBUILDING STRONG®
Value Engineering the Termination of the Blue River Flood Conveyance Channel
Alan Schlindwein, PEUS Army Corps of Engineers
Kansas City, Missouri
June 14, 2012
Robert Prager, PEStrategic Value Solutions, Inc
Independence, Missouri
![Page 2: Value Engineering the Termination of the Blue River Flood Conveyance Channel](https://reader036.vdocuments.mx/reader036/viewer/2022062501/5681638c550346895dd47c6b/html5/thumbnails/2.jpg)
BUILDING STRONG®
Battle of Westport
AKA: The Gettysburg of the West
![Page 3: Value Engineering the Termination of the Blue River Flood Conveyance Channel](https://reader036.vdocuments.mx/reader036/viewer/2022062501/5681638c550346895dd47c6b/html5/thumbnails/3.jpg)
BUILDING STRONG®
The Real Brush Creek(after USACE project)
![Page 4: Value Engineering the Termination of the Blue River Flood Conveyance Channel](https://reader036.vdocuments.mx/reader036/viewer/2022062501/5681638c550346895dd47c6b/html5/thumbnails/4.jpg)
BUILDING STRONG®
1st & 2nd Battles of the Big Blue at Byram’s Ford
![Page 5: Value Engineering the Termination of the Blue River Flood Conveyance Channel](https://reader036.vdocuments.mx/reader036/viewer/2022062501/5681638c550346895dd47c6b/html5/thumbnails/5.jpg)
BUILDING STRONG®
Byram’s Ford
![Page 6: Value Engineering the Termination of the Blue River Flood Conveyance Channel](https://reader036.vdocuments.mx/reader036/viewer/2022062501/5681638c550346895dd47c6b/html5/thumbnails/6.jpg)
BUILDING STRONG®
Blue River Flood Conveyance Channel
35,000 cfs Flood Control Channel
New Bridges Remapping of
Floodplain
![Page 7: Value Engineering the Termination of the Blue River Flood Conveyance Channel](https://reader036.vdocuments.mx/reader036/viewer/2022062501/5681638c550346895dd47c6b/html5/thumbnails/7.jpg)
BUILDING STRONG®
3rd Battle of Byram’s Ford
Concrete Grade Control Structure
![Page 8: Value Engineering the Termination of the Blue River Flood Conveyance Channel](https://reader036.vdocuments.mx/reader036/viewer/2022062501/5681638c550346895dd47c6b/html5/thumbnails/8.jpg)
BUILDING STRONG®
Proposed Grade Control Structure
![Page 9: Value Engineering the Termination of the Blue River Flood Conveyance Channel](https://reader036.vdocuments.mx/reader036/viewer/2022062501/5681638c550346895dd47c6b/html5/thumbnails/9.jpg)
BUILDING STRONG®
Byram’s Ford Industrial Park
![Page 10: Value Engineering the Termination of the Blue River Flood Conveyance Channel](https://reader036.vdocuments.mx/reader036/viewer/2022062501/5681638c550346895dd47c6b/html5/thumbnails/10.jpg)
BUILDING STRONG®
Stated Goals
Prevent the headcutting at the battlefield location
Limit maximum flood elevation to pre-project conditions
Control velocity upstream to manage scour along the riverbanks
![Page 11: Value Engineering the Termination of the Blue River Flood Conveyance Channel](https://reader036.vdocuments.mx/reader036/viewer/2022062501/5681638c550346895dd47c6b/html5/thumbnails/11.jpg)
BUILDING STRONG®
Design
The structure was designed to stop head-cutting and control flood elevations upstream to pre-project conditions which in turn aided in managing scour at the battlefield location and along the riverbanks by controlling velocity.
![Page 12: Value Engineering the Termination of the Blue River Flood Conveyance Channel](https://reader036.vdocuments.mx/reader036/viewer/2022062501/5681638c550346895dd47c6b/html5/thumbnails/12.jpg)
BUILDING STRONG®
Externalities Construction of the grade control structure would
affect the channel upstream of this project and create pre-project conditions, i.e., flooding in areas that had not experienced flooding since the channel project began would now be flooded again.
![Page 13: Value Engineering the Termination of the Blue River Flood Conveyance Channel](https://reader036.vdocuments.mx/reader036/viewer/2022062501/5681638c550346895dd47c6b/html5/thumbnails/13.jpg)
BUILDING STRONG®
![Page 14: Value Engineering the Termination of the Blue River Flood Conveyance Channel](https://reader036.vdocuments.mx/reader036/viewer/2022062501/5681638c550346895dd47c6b/html5/thumbnails/14.jpg)
BUILDING STRONG®
![Page 15: Value Engineering the Termination of the Blue River Flood Conveyance Channel](https://reader036.vdocuments.mx/reader036/viewer/2022062501/5681638c550346895dd47c6b/html5/thumbnails/15.jpg)
BUILDING STRONG®
The Value Ah Ha! The current flood levels
can be maintained to limit maximum flood elevation to below pre-project conditions
Grade controls can be distributed along the river rather than at a concrete waterfall
Perfection
CostFu
nctio
ns0%
100%
Poor Value
Best Value
![Page 16: Value Engineering the Termination of the Blue River Flood Conveyance Channel](https://reader036.vdocuments.mx/reader036/viewer/2022062501/5681638c550346895dd47c6b/html5/thumbnails/16.jpg)
BUILDING STRONG®
![Page 17: Value Engineering the Termination of the Blue River Flood Conveyance Channel](https://reader036.vdocuments.mx/reader036/viewer/2022062501/5681638c550346895dd47c6b/html5/thumbnails/17.jpg)
BUILDING STRONG®
Stated Goals PROTECT THE
CHANNEL PRESERVE THE
BATTLEFIELD
By Mimicking Natural Processes
![Page 18: Value Engineering the Termination of the Blue River Flood Conveyance Channel](https://reader036.vdocuments.mx/reader036/viewer/2022062501/5681638c550346895dd47c6b/html5/thumbnails/18.jpg)
BUILDING STRONG®
Work with River
Continuum
Riffle PoolSequence
Place at end of Bend
![Page 19: Value Engineering the Termination of the Blue River Flood Conveyance Channel](https://reader036.vdocuments.mx/reader036/viewer/2022062501/5681638c550346895dd47c6b/html5/thumbnails/19.jpg)
BUILDING STRONG®
54000 59000 64000 69000 74000 79000680
700
720
740
760
780
800
820
840
Ground100yrbridgeslow flow
River Profile - Newbury & Proposed GCS
![Page 20: Value Engineering the Termination of the Blue River Flood Conveyance Channel](https://reader036.vdocuments.mx/reader036/viewer/2022062501/5681638c550346895dd47c6b/html5/thumbnails/20.jpg)
BUILDING STRONG®
Grade Control at KC Zoo
![Page 21: Value Engineering the Termination of the Blue River Flood Conveyance Channel](https://reader036.vdocuments.mx/reader036/viewer/2022062501/5681638c550346895dd47c6b/html5/thumbnails/21.jpg)
BUILDING STRONG®
Rock Grade Control Structure
![Page 22: Value Engineering the Termination of the Blue River Flood Conveyance Channel](https://reader036.vdocuments.mx/reader036/viewer/2022062501/5681638c550346895dd47c6b/html5/thumbnails/22.jpg)
BUILDING STRONG®
2000 cfs flow
![Page 23: Value Engineering the Termination of the Blue River Flood Conveyance Channel](https://reader036.vdocuments.mx/reader036/viewer/2022062501/5681638c550346895dd47c6b/html5/thumbnails/23.jpg)
BUILDING STRONG®