UJIAN TENGAN SEMESTER – MPPL Nama : Wirawan Satyadi NIM : 1311530230 Mata kuliah : MPPL Kampus Salemba 1. Rencana Kegiatan Proyek Perangkat Lunak “Retail Web Site” No Kode Kegiatan Agustus Septembe r Oktober November 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 A Project Management 2 B Requirment Gathering 3 C Desaign and Analyst 4 D Site Software Development 5 E Testing and Production 6 F HTML Desaign and Creation 7 G Graphic and Interface 8 H Content Creation 9 I Backend Software 10 J Database Implementat ion 11 K Middleware Development 12 L Security Subsystem 13 M Catalog Engine 14 N Transaction Processing

Upload: muslim-prabowo

Post on 13-Sep-2015

230 views

Category:

Documents


3 download

DESCRIPTION

budiluhur

TRANSCRIPT

Ujian Tengan Semester MPPL

Ujian Tengan Semester MPPL

Nama : Wirawan SatyadiNIM : 1311530230Mata kuliah : MPPLKampus Salemba

1. Rencana Kegiatan Proyek Perangkat Lunak Retail Web Site

NoKodeKegiatanAgustusSeptemberOktoberNovember

1234123412341234

1AProject Management

2BRequirment Gathering

3CDesaign and Analyst

4DSite Software Development

5ETesting and Production

6FHTML Desaign and Creation

7GGraphic and Interface

8HContent Creation

9IBackend Software

10JDatabase Implementation

11KMiddleware Development

12LSecurity Subsystem

13MCatalog Engine

14NTransaction Processing

2. - Project Management, lamanya waktu 1 minggu.- Requirment Gathering, lamanya 1 minggu, dilakukan setelah Project Management- Desaign and Analyst, lamanya 1 minggu, dilakukan setelah Requirment Gathering- Site Software Development, lamanya 10 minggu, dilakukan setelah Requirment Gathering- Testing and Production, lamanya 3 minggu, dilakukan setelah Site Software Development- HTML Desaign and Creation, lamanya 5 minggu, dilakukan saat Site Software Development- Graphic and Interface, lamanya 5 minggu, dilakukan saat Site Software Development- Content Creation, lamanya 5 minggu, dilakukan saat Site Software Development- Backend Software, lamanya 10 minggu, dilakukan saat Site Software Development- Database Implementation, lamanya 5 minggu, dilakukan saat Backend Software- Middleware Development, lamanya 5 minggu, dilakukan saat Backend Software- Security Subsystem, lamanya 5 minggu, dilakukan saat Backend Software- Catalog Engine, lamanya 5 minggu, dilakukan saat Backend Software- Transaction Processing, lamanya 5 minggu, dilakukan saat Backend Software

3. A. Work Breakdown Structure (WBS)

B. Diagram Gantt ChartNoKodeKegiatanAgustusSeptemberOktoberNovember

1234123412341234

1AProject Management

2BRequirment Gathering

3CDesaign and Analyst

4DSite Software Development

5ETesting and Production

6FHTML Desaign and Creation

7GGraphic and Interface

8HContent Creation

9IBackend Software

10JDatabase Implementation

11KMiddleware Development

12LSecurity Subsystem

13MCatalog Engine

14NTransaction Processing

C. Diagram Jaringan dengan ADM (Arrow Diagramming Method)

D. Diagram Jaringan dengan PDM (Precedence Diagramming Method)

E. B + D + F = 1 + 10 + 5 = 16C + E + G = 1 + 3 + 5 = 9I + K + M = 10 + 5 + 5 = 20J + L + N = 5 + 5 + 5 = 15Jadi Lintasan Kritisnya adalah 20

F. Waktu tercepat untuk menyelesaikan seluruh kegiatan proyek adalah 20 minggu