Ujian Tengan Semester MPPL
Ujian Tengan Semester MPPL
Nama : Wirawan SatyadiNIM : 1311530230Mata kuliah : MPPLKampus Salemba
1. Rencana Kegiatan Proyek Perangkat Lunak Retail Web Site
NoKodeKegiatanAgustusSeptemberOktoberNovember
1234123412341234
1AProject Management
2BRequirment Gathering
3CDesaign and Analyst
4DSite Software Development
5ETesting and Production
6FHTML Desaign and Creation
7GGraphic and Interface
8HContent Creation
9IBackend Software
10JDatabase Implementation
11KMiddleware Development
12LSecurity Subsystem
13MCatalog Engine
14NTransaction Processing
2. - Project Management, lamanya waktu 1 minggu.- Requirment Gathering, lamanya 1 minggu, dilakukan setelah Project Management- Desaign and Analyst, lamanya 1 minggu, dilakukan setelah Requirment Gathering- Site Software Development, lamanya 10 minggu, dilakukan setelah Requirment Gathering- Testing and Production, lamanya 3 minggu, dilakukan setelah Site Software Development- HTML Desaign and Creation, lamanya 5 minggu, dilakukan saat Site Software Development- Graphic and Interface, lamanya 5 minggu, dilakukan saat Site Software Development- Content Creation, lamanya 5 minggu, dilakukan saat Site Software Development- Backend Software, lamanya 10 minggu, dilakukan saat Site Software Development- Database Implementation, lamanya 5 minggu, dilakukan saat Backend Software- Middleware Development, lamanya 5 minggu, dilakukan saat Backend Software- Security Subsystem, lamanya 5 minggu, dilakukan saat Backend Software- Catalog Engine, lamanya 5 minggu, dilakukan saat Backend Software- Transaction Processing, lamanya 5 minggu, dilakukan saat Backend Software
3. A. Work Breakdown Structure (WBS)
B. Diagram Gantt ChartNoKodeKegiatanAgustusSeptemberOktoberNovember
1234123412341234
1AProject Management
2BRequirment Gathering
3CDesaign and Analyst
4DSite Software Development
5ETesting and Production
6FHTML Desaign and Creation
7GGraphic and Interface
8HContent Creation
9IBackend Software
10JDatabase Implementation
11KMiddleware Development
12LSecurity Subsystem
13MCatalog Engine
14NTransaction Processing
C. Diagram Jaringan dengan ADM (Arrow Diagramming Method)
D. Diagram Jaringan dengan PDM (Precedence Diagramming Method)
E. B + D + F = 1 + 10 + 5 = 16C + E + G = 1 + 3 + 5 = 9I + K + M = 10 + 5 + 5 = 20J + L + N = 5 + 5 + 5 = 15Jadi Lintasan Kritisnya adalah 20
F. Waktu tercepat untuk menyelesaikan seluruh kegiatan proyek adalah 20 minggu