![Page 1: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/1.jpg)
2014 UTPOverview and Update ProcessJessica Butler, P.E.April 5, 2013
![Page 2: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/2.jpg)
Agenda
2
2014 UTP: Overview & Update Process
Describe 2014 UTP Update Resources & Toolkit
2014 UTP Programming Guidance
Project Ranking Tool
##
##
##
##
Summary & Action Items##
![Page 3: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/3.jpg)
2014 UTP UPDATE OVERVIEW
3
![Page 4: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/4.jpg)
Unified Transportation Program (UTP)
4
![Page 5: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/5.jpg)
UTP Annual Update Cycle
5
TPP Provides Category Allocations
to Districts/Local Partners
Districts/Local Partners Program
Known Projects for All UTP Years by
Category
Review/ Comment
Period
Adjustments
UTP Approved by
TTC (typically in
August)
2013 UTP 2014 UTP
Spring – Summer 2013
![Page 6: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/6.jpg)
2014 UTP Update: Big Picture
6
LegacySystems
New Generation
Tools & Approaches
We are here for the 2014 UTP Update
TxDOT Project Management & Programming
![Page 7: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/7.jpg)
2014 UTP – How is It Different from 2013?
MAP-21 Funding Assumptions Listing of Known Projects in all Categories
– Except Category 1 Preventive Maintenance & Rehab Listing Major Transportation projects Ability to program 10 Years + 11PA Reflect Total Project Cost Project Ranking Projects listed only once Organized by District vs. Category
7
![Page 8: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/8.jpg)
MAP-21 Funding Assumptions
8
MAP-21 Funding levels projected through FY 2014 Projection of MAP-21 beyond FY 2014 used to develop 11PA levels
MAP-21 SAFETEA-LU
National Highway Performance Program (NHPP) NHS, IM, & Bridge (portion)
Surface Transportation Program (STP) STP & Bridge (portion)
Congestion Mitigation & Air Quality Improvement Program (CMAQ)
CMAQ
Highway Safety Improvement Program (HSIP) HSIP (incl. High Risk Rural Roads)
Railway-Highway Grade Crossing(takedown from HSIP)
Railway Highway Grade Crossing
Transportation Alternatives TE, Recreational Trails, and Safe Routes to School
![Page 9: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/9.jpg)
Listing of Known Projects Across All Ten Years
Excludes Category 1 Improved information on planned projects Increased flexibility to program all 10 years + 11PA
9
Unified Transportation Planning Program
(Years 1-10)
Statewide Transportation Improvement Program
(Years 1-4)
TxDOT 2-year Letting Schedule
• TxDOT commitment to explore these projects further.
• Projects represent joint commitment by TxDOTand local partners.
• Projects are likely to occur, barring unforeseen complication
![Page 10: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/10.jpg)
Total Project Cost
Total Project Cost – the total cost of all phases associated with a project CSJ. Note: for the UTP, this is only future expenditures, not past expenditures.
Preliminary Engineering – Project development activities during which basic planning objectives are translated into specific, well-defined engineering criteria that transition a project into the final design process
ROW Purchase – Cost of any real property required to construct or implement a project
Construction Cost – Cost of the actual construction (labor and materials) Construction Engineering – Cost of the interpretation of plans and specifications
and formulation of engineering decisions Contingencies – Estimated amount of any unforeseen costs associated with a
project Indirect Cost – Expenses the provider or contractor incurs for operating its
business as a whole. Indirect cost rates for providers selected to enter into an engineering contract are obtainable from TxDOT’s Audit Office.
10
![Page 11: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/11.jpg)
Project Ranking
New requirement under Texas Administrative Code [43 TAC §16.105] For 2014 UTP
– FOR INFORMATIONAL PURPOSES ONLY– Referenced as a sorting tool in the document
After 2014 UTP approval, TxDOT may assess the project ranking process
11
![Page 12: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/12.jpg)
2014 UTP Development Resources
UTP Development Web Page – General Info 2014 UTP Development Timeline Draft Preliminary Funding Levels Instructions for Programming Other Helpful LinksUTP Programming Toolkit District/Division-Specific Project Programming Tool (Excel) Project Ranking Tool (SharePoint)Other Resources TxDOT UTP Staff TPP MPO Liaison Contact Info
12
![Page 13: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/13.jpg)
2014 UTPDEVELOPMENT WEB PAGE
13
![Page 14: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/14.jpg)
UTP Development Web Page – General Info
http://www.txdot.gov/inside-txdot/division/transportation-planning/utp-development.html
![Page 15: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/15.jpg)
UTP 2014 Development Timeline
15
August 2013
Months April May June
Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13
TPP Provides Preliminary Category Allocations to Districts/Local Partners
Districts/Local Partners Program Known Projects for All UTP Years by Category
Districts/Local Partners Rank Known Projects for All UTP Years
DCIS Fields Open
QCQA of Project Data
TxDOT Reports Preliminary Funding Levels to Commission
Project Selection Process Public Involvement & Approval
FINAL DRAFT 2014 UTP Public Involvement
Final 2014 UTP Approval by Commission
Milestone TxDOT/Local Partner Activity
August 2013
July 2013
Public Involvement
![Page 16: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/16.jpg)
Preliminary Funding Levels
16
Funding Category DRAFT 2014 UTP Funding1 - Preventative Maintenance and Rehabilitation 11,555,470,000
2 - Metro and Urban Area Corridor Projects 1,716,870,000
3 - Non-Traditional Funded Transportation Projects 6,840,130,000
4 - Statewide Connectivity Corridor Projects 0
5 - Congestion Mitigation and Air Quality Improvement 1,521,430,000
6 - Structures 2,500,000,000
7 - Metropolitan Mobility/Rehabilitation 2,835,860,000
8 - Safety 1,714,940,000
9 - Transportation Enhancements 567,030,000
10 - Supplemental Transportation Projects 747,220,000
11 - District Discretionary 624,560,000
12 - Strategic Priority 2,394,820,000
TOTAL UTP FUNDING: CATEGORIES 1-12 33,018,330,000Notes:
Category 8 total includes Prop 14 Safety Bond
Category 10 total includes Federal Earmark Match
![Page 17: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/17.jpg)
Programming General Instructions
17
PROGRAMMINGInstructions by Category
![Page 18: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/18.jpg)
2014 UTPPROGRAMMING TOOLKIT
18
![Page 19: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/19.jpg)
UTP Programming ToolkitSharePoint site
19
![Page 20: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/20.jpg)
Project Programming Toolkit Instructions
20
Project ProgrammingTOOLKIT
Instructions
![Page 21: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/21.jpg)
PROJECT PROGRAMMING TEMPLATE
21
![Page 22: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/22.jpg)
Project Programming
Data exported from DCIS All projects programmed in DCIS through 2023 were
included Program up to your allocations in Categories
– 10 years of work programs provided by FIN– 11PA for programming in addition to the Category allocations– Account for Inflation– Work with respective Divisions before moving Cat 6 or 8 projects – Program the projects known
If fully programmed and additional capacity in 11PA is needed, can request on project specific basis Move out projects that do not fit within 10 year plan or 11PA
allocation
22
![Page 23: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/23.jpg)
Project Programming Template (in Toolkit)
23
Data is organized into folders accessed through SharePoint Each District/Division has a separate folder Instructions posted online Download the files from SharePoint to work on Upload back to SharePoint Use the tabs to check your work as you go Suggest ranking after your finalize your project lists After May 10th we will extract the files from SharePoint Will have QCQA time to make adjustments
![Page 24: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/24.jpg)
Project Programming Template Instructions
24
TOOLKIT:Project Programming
TemplateInstructions
![Page 25: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/25.jpg)
PROJECT RANKING TOOL
25
![Page 26: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/26.jpg)
Project Ranking – A Legislative Requirement
43 TAC §16.105 amendments require TxDOT to develop criteria to rank the priority of each project listed in the UTP based on the transportation needs for the state and department goals. Projects must be ranked as Tier 1, 2 or 3 All major transportation projects will be Tier 1 and designated as highest
priority
Survey went out soliciting feedback on February 1, 2013. 39 responses total (13 MPO/20 District/6 Division) Ranking is not a replacement for current project selection processes The most important criteria for most categories were project need,
funding availability, meeting TxDOT’s goals, project readiness/phase of project, and addressing time‐sensitive critical needs.
26
![Page 27: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/27.jpg)
Project Ranking Tool - Scoring Criteria
Project Need– Safety – Congestion – Connect Texas Communities – Become Best-In-Class State Agency
Funding Availability Project Readiness/Phase of Project
27
![Page 28: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/28.jpg)
2014 UTP Ranking Process & Tool
28
Is Project Assigned a
Letting Date in the 2-Year
TxDOT Letting Schedule?
Rank =Tier 1
Yes
Has Project Been Identified
as a Major Transportation
Project?
Rank =Tier 1
Yes
No
2-Year Letting Schedule
Major Transportation
Project
No
Project Ranking Tool
Start Here
Project Need
Funding Availability
Project Readiness/
Phase
Score* (S1)
Score(S2)
Score(S3)
WSi = Total Score
Threshold Rank
> 75 Tier 151 - 75 Tier 2
< 50 Tier 3
![Page 29: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/29.jpg)
Project Ranking Tool (in Toolkit)
29
![Page 30: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/30.jpg)
Project Ranking Tool Instructions
30
TOOLKIT:Project Ranking
ToolInstructions
![Page 31: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/31.jpg)
2014 UTP UPDATE SUMMARY
31
![Page 32: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/32.jpg)
2014 UTP Programming Resources
UTP Development Web Page – General Info 2014 UTP Development Timeline Draft Preliminary Funding Levels Instructions for Programming Other Helpful LinksUTP Programming Toolkit District/Division-Specific Project Programming Tool (Excel) Project Ranking Tool (SharePoint)Other Resources TxDOT UTP Staff TPP MPO Liaison Contact Info
32
![Page 33: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/33.jpg)
UTP 2014 Development: Action Items
33
August 2013
Months April May June
Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13
TPP Provides Preliminary Category Allocations to Districts/Local Partners
Districts/Local Partners Program Known Projects for All UTP Years by Category
Districts/Local Partners Rank Known Projects for All UTP Years
DCIS Fields Open
QCQA of Project Data
TxDOT Reports Preliminary Funding Levels to Commission
Project Selection Process Public Involvement & Approval
FINAL DRAFT 2014 UTP Public Involvement
Final 2014 UTP Approval by Commission
Milestone TxDOT/Local Partner Activity
July 2013
Public Involvement
August 2013
![Page 34: UTP Presentation Slides DRAFT0405 final jb.pptx [Read-Only]ftp.dot.state.tx.us/.../tpp/utp/2014/040513_presentation.pdf · 2013-04-08 · Microsoft PowerPoint - UTP Presentation Slides_DRAFT0405_final_jb.pptx](https://reader033.vdocuments.mx/reader033/viewer/2022050211/5f5d63a88b24f126055f3fd0/html5/thumbnails/34.jpg)
34
THANK YOU