Conference on St. Thomas, Energy Development in Island Nations.TRANSCRIPT
USVI Energy Roadmap
Adam Warren, PhD (NREL)
Credit: Warren Gretz, NREL Credit: Don Buchanan, VI Energy Office Credit: Don Buchanan, VI Energy Office
EDIN-USVI Energy WorkshopApril 7-8, 2011Univ. of the Virgin Islands, St. Thomas
USVI Energy Roadmap
04/08/2023 2
Our motivation
Electricity Cost = Fixed Cost (Poles, Wires, Equipment) + LEAC
USVI Energy Roadmap
04/08/2023 3
Our motivationEIA: annual average price of low sulfur crude oil real 2009 dollars per barrel
Factors not considered:
USVI Energy Roadmap
EDIN is an international partnership between USA, New Zealand, and Iceland started in 2008.
Why Islands? Islands are often highly dependent on fossil fuels for
electricity and transportation and often have very high retail electricity rates
Islands often have abundant renewable resources and small populations, so are ideal places to showcase the future of high renewable energy penetration.
What is EDIN?
USVI Energy Roadmap
EDIN-USVI Background
Oct 2009 – First meeting
of Energy Action Team
Feb 2010 – MOU Signing
(DOE, DOI, USVI)
June 2010 – First official meeting
of Energy Working Groups
in St. Thomas
Nov 2010 – Working Groups meet in St. Croix to continue
Roadmap development
USVI Energy Roadmap
6
Feb 2010 – Declaration of our mission
At the MOU signing ceremony with DOE and DOI, Gov. deJongh, Jr. announced his goal to reduce USVI’s dependence of fossil fuel by 60% by 2025.
“There is no reason why the Virgin Islands cannot be the leaders in clean energy deployment in the Caribbean,” deJongh said.
USVI Energy Roadmap
7
June 2010 – Formation of Working Groups
EDIN - USVI Directors
Renewable Energy
Energy Efficiency Transportation
Policy & Analysis
Education & Workforce
Development
USVI Energy Roadmap
November 2010 –“How do we get to 60x25?”
ActionsWho? What? When? How?
StrategyRenewable Energy Energy Efficiency
Goal60% by 2025
USVI Energy Roadmap
Diverse set of stakeholders working together to ask the right questions and find the answers
USVI Energy Roadmap
Bostonia, ESG, ...
Act 7075 & Senate
NREL, DOE, &
DOI
VIEO & WAPA
Working Groups
USVI Energy Roadmap
April 2011 Workshop
• Critique draft Energy Roadmap– What can be done? What can’t?– What have we missed?
• Identify and eliminate Barriers.
• Working Groups– Mission– Values– Goal
USVI Energy Roadmap
Agenda
Discussions, not presentations.
USVI Energy Roadmap
EDIN-USVI Background
Organize
Plan
Assess
Implement
USVI Energy Roadmap
13
EDIN-USVI Process
“60x25”
USVI Energy Roadmap
14
USVI Energy Roadmap
USVI Energy Roadmap
Methodology: Relate everything to barrels of oil
Water
Electricity
Waste heat
= LEAC
Electricity Cost = Fixed Cost (Poles, Wires, Equipment) + LEAC
USVI Energy Roadmap
Determine Business as Usual (BAU)- What will happen if we don’t do anything
USVI Energy Roadmap
Determine Business as Usual (BAU)- Mix of EE & RE to achieve 60% by 2025
60% by 2025
USVI Energy Roadmap
Analyze roadmaps to 60% by 2025A different view
60% by 2025
USVI Energy Roadmap
Multiple paths are possibleEmphasize energy efficiency Emphasize renewable energy
USVI Energy Roadmap
04/08/2023 20
Key Findings
• It can be done, but only with all stakeholders pulling together, in the same direction.
• The kitchen sink – it’s going to take everything to get to 60% by 2025.
• WAPA must lead. All scenarios include waste-to-energy and increased generation/water efficiency.
USVI Energy Roadmap
04/08/2023 21
A few details
60 x 2025 RE / Fossil Fuel Mix
USVI Energy Roadmap
04/08/2023 22
Renewable Energy Technologies
USVI Energy Roadmap
04/08/2023 23
Energy Efficiency
USVI Energy Roadmap
04/08/2023 24
60% Goal
Cost
effe
ctive
ness
more
less
Energy Efficiency & Renewable Energy
USVI Energy Roadmap
25
Progress to Date
USVI Energy Roadmap
Progress to date
Renewable Energy• 448 kW Solar PV at STT Airport
• 450 Solar Water Heaters
End-Use Energy Efficiency• LED Street Lighting Project
• ESCO work for Department of Education (11 schools)
Generation Efficiency• Heat Recover Steam Generators in
STX
• Reverse Osmosis at STX
USVI Energy Roadmap Renewable Energy
448 kW Solar PV at Cyril E. King Airport
450 Solar Hot Water systemsinstalled
USVI Energy Roadmap Energy Efficiency
11 Schools Retrofitted to save Water and Energy
972 LED Street Lights in St. John
USVI Energy Roadmap Generation Efficiency at WAPA
Heat Recovery Steam Generators (HRSGs) - 19 MW from waste heat
Reverse Osmosis replacesDistillation for half of St. Croix’sWater Supply
USVI Energy Roadmap Joining us by Video Conference
Kari Burman
Vahan Gevorgian, PhD
Caleb Rockenbaugh
USVI Energy Roadmap
31