  • 8/14/2019 Using Serial Number Tracking at an Operation_SPD

    1/19

    System Process DocumentUsing Serial Number Tracking at an Operation

    Department

    Responsibility/Role

    File Name 27762880.docRevision

    Document Generation Date 18/01/2010 09:38:00

    Date Modified 1/18/2010 09:38:00 AM

    Last Changed by

    Status

    Using Serial Number Tracking at an Operation

    Trigger:

    Concept

    The Serialization Start Op Seq flag in the Routing Details page indicates that item tracking

    with serial numbers begins at this particular operation. This enables you to track items using

    serial numbers prior to the completed transaction. You must check this field to use serial number

    tracking for Oracle Work in Process transactions.

    Serialization Start Operation determines the job operation where serial number tracking begins.

    The serial start operation on the item routing is always copied to the job routing during jobcreation. If there is no serialization start operation on the item routing, and this parameter is

    enabled, the serialization start operation is defaulted to the first operation on the job routing. This

    value displays on the Discrete Jobs page. If this parameter is not enabled, the serialization startoperation on the job routing is blank, and serialization is disabled.

    In this topic, you will use serial number tracking at an operation.

    Required Field(s) Comments

    Output - Result(s) Comments

    Additional Information

    Last changed on: 1/18/2010 09:38:00 AM Page 1

  • 8/14/2019 Using Serial Number Tracking at an Operation_SPD

    2/19

    System Process DocumentUsing Serial Number Tracking at an Operation

    Procedure

    Step Action

    1. Begin by navigating to the Routings page.

    Click the vertical scrollbar.

    Page 2 Last changed on: 1/18/2010 09:38:00 AM

  • 8/14/2019 Using Serial Number Tracking at an Operation_SPD

    3/19

    System Process DocumentUsing Serial Number Tracking at an Operation

    Step Action

    2. Click the Manufacturing and Distribution Manager link.

    Last changed on: 1/18/2010 09:38:00 AM Page 3

  • 8/14/2019 Using Serial Number Tracking at an Operation_SPD

    4/19

    System Process DocumentUsing Serial Number Tracking at an Operation

    Step Action

    3. Click the vertical scrollbar.

    Step Action

    4. Click the Routings link.

    Page 4 Last changed on: 1/18/2010 09:38:00 AM

  • 8/14/2019 Using Serial Number Tracking at an Operation_SPD

    5/19

    System Process DocumentUsing Serial Number Tracking at an Operation

    Step Action

    5. Use the Organizations page to select your organization.

    Last changed on: 1/18/2010 09:38:00 AM Page 5

  • 8/14/2019 Using Serial Number Tracking at an Operation_SPD

    6/19

    System Process DocumentUsing Serial Number Tracking at an Operation

    Step Action

    6. Click the M1 Seattle Manufacturing list item.

    Step Action

    7. Click the OKbutton.

    orPress [Alt+O].

    Page 6 Last changed on: 1/18/2010 09:38:00 AM

  • 8/14/2019 Using Serial Number Tracking at an Operation_SPD

    7/19

    System Process DocumentUsing Serial Number Tracking at an Operation

    Step Action

    8. Use the Routings page to define the operations for a routing and the sequence to

    perform them.

    You can define a primary or an alternate routing.

    You can also navigate to the Routing Details and Routing Revisions pages from

    this page.

    Last changed on: 1/18/2010 09:38:00 AM Page 7

  • 8/14/2019 Using Serial Number Tracking at an Operation_SPD

    8/19

    System Process DocumentUsing Serial Number Tracking at an Operation

    Step Action

    9. Click in the Item field.

    Page 8 Last changed on: 1/18/2010 09:38:00 AM

  • 8/14/2019 Using Serial Number Tracking at an Operation_SPD

    9/19

    System Process DocumentUsing Serial Number Tracking at an Operation

    Step Action

    10. Press [F11].

    Step Action

    11. Enter the desired information into the Item field. Enter "RT1000".

    Last changed on: 1/18/2010 09:38:00 AM Page 9

  • 8/14/2019 Using Serial Number Tracking at an Operation_SPD

    10/19

    System Process DocumentUsing Serial Number Tracking at an Operation

    Step Action

    12. Press [Ctrl+F11].

    Step Action

    13. Click the Routing Details button.

    Page 10 Last changed on: 1/18/2010 09:38:00 AM

  • 8/14/2019 Using Serial Number Tracking at an Operation_SPD

    11/19

    System Process DocumentUsing Serial Number Tracking at an Operation

    Step Action

    14. Use the Routing Details page to enter the serialization start operation sequence and

    the details of where you store the finished assemblies upon completion.

    The Serialization Start Operation determines the job operation where serial

    number tracking begins. The serial start operation on the item routing is always

    copied to the job routing during job creation. If there is no serialization start

    operation on the item routing, and this parameter is enabled, the serialization startoperation is defaulted to the first operation on the job routing. If this parameter is

    not enabled, the serialization start operation on the job routing is blank, and

    serialization is disabled.

    Last changed on: 1/18/2010 09:38:00 AM Page 11

  • 8/14/2019 Using Serial Number Tracking at an Operation_SPD

    12/19

    System Process DocumentUsing Serial Number Tracking at an Operation

    Step Action

    15. Click in the Serialization Start Op Seq field.

    Page 12 Last changed on: 1/18/2010 09:38:00 AM

  • 8/14/2019 Using Serial Number Tracking at an Operation_SPD

    13/19

    System Process DocumentUsing Serial Number Tracking at an Operation

    Step Action

    16. Enter the desired information into the Serialization Start Op Seq field. Enter "10".

    Step Action

    17. Click in the Locator field.

    Last changed on: 1/18/2010 09:38:00 AM Page 13

  • 8/14/2019 Using Serial Number Tracking at an Operation_SPD

    14/19

    System Process DocumentUsing Serial Number Tracking at an Operation

    Step Action

    18. Use the Completion Locatorpage to enter the row and rack where you want the

    finished goods to be stored.

    Page 14 Last changed on: 1/18/2010 09:38:00 AM

  • 8/14/2019 Using Serial Number Tracking at an Operation_SPD

    15/19

    System Process DocumentUsing Serial Number Tracking at an Operation

    Step Action

    19. Click in the Row field.

    Step Action

    20. Enter the desired information into the Row field. Enter "A".

    Last changed on: 1/18/2010 09:38:00 AM Page 15

  • 8/14/2019 Using Serial Number Tracking at an Operation_SPD

    16/19

    System Process DocumentUsing Serial Number Tracking at an Operation

    Step Action

    21. Click in the Rackfield.

    Page 16 Last changed on: 1/18/2010 09:38:00 AM

  • 8/14/2019 Using Serial Number Tracking at an Operation_SPD

    17/19

    System Process DocumentUsing Serial Number Tracking at an Operation

    Step Action

    22. Enter the desired information into the Rackfield. Enter "1".

    Step Action

    23. Click the OKbutton.

    orPress [Alt+O].

    Last changed on: 1/18/2010 09:38:00 AM Page 17

  • 8/14/2019 Using Serial Number Tracking at an Operation_SPD

    18/19

    System Process DocumentUsing Serial Number Tracking at an Operation

    Step Action

    24. Click the Save button.

    Page 18 Last changed on: 1/18/2010 09:38:00 AM

  • 8/14/2019 Using Serial Number Tracking at an Operation_SPD

    19/19

    System Process DocumentUsing Serial Number Tracking at an Operation

    Step Action

    25. You have completed the Using Serial Number Tracking at an Operation procedure.