Page 1: USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY …exicon.website/uploads/editor/Omaintec2017... · MADY MOHAMED USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY IN MAINTENANCE

15th INTERNATIONAL OPERATIONS & MAINTENANCE CONFERENCE IN THE ARAB

COUNTRIESUNDER THE THEME: “SMART MAINTENANCE” CONICIDE WITH THE 15TH ARAB MAINTENANCE

EXHIBITION

MADY MOHAMED

USING RATING SYSTEMS AS A GUIDE TOOL FOR

CONSULTANCY IN MAINTENANCE WORK

Page 2: USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY …exicon.website/uploads/editor/Omaintec2017... · MADY MOHAMED USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY IN MAINTENANCE

2

USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY IN MAINTENANCE WORK

Introduction1

Research Aim2

Proposed Methodology3

Presentation Content

Page 3: USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY …exicon.website/uploads/editor/Omaintec2017... · MADY MOHAMED USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY IN MAINTENANCE

3

Introduction:

This paper is focusing on employing rating systems to guide the

process of the operation and maintenance for buildings. The LEED

fundamental commissioning is discussed briefly while a detailed

explanation for the processes, tasks and responsibilities of each

stakeholder in building projects is presented.

USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY IN MAINTENANCE WORK

Page 4: USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY …exicon.website/uploads/editor/Omaintec2017... · MADY MOHAMED USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY IN MAINTENANCE

4

USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY IN MAINTENANCE WORK

Figure : the credits weighting of the

environmental categories of the LEED [29]

Introduction:

Rating systems are groups of

requirements for projects. Each

group is geared towards the unique

needs of a project. Projects earn

points to satisfy green building

requirements. Within each of the

LEED credit categories, projects

must satisfy prerequisites and earn

points

Page 5: USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY …exicon.website/uploads/editor/Omaintec2017... · MADY MOHAMED USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY IN MAINTENANCE

5

USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY IN MAINTENANCE WORK

Figure 2: EA LEED V4 category including the Fundamental and Enhanced commissioning [30]

Page 6: USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY …exicon.website/uploads/editor/Omaintec2017... · MADY MOHAMED USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY IN MAINTENANCE

6

Commissioning:

While the focus of the commissioning includes individual equipment

or systems, it is considered a holistic approach emphasizing the

connections between components and the overall building energy

efficiency .

Commissioning assure having a good level of maintenance,

USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY IN MAINTENANCE WORK

Page 7: USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY …exicon.website/uploads/editor/Omaintec2017... · MADY MOHAMED USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY IN MAINTENANCE

7

Figure 3: Relationships between commissioning and energy-efficiency

Page 8: USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY …exicon.website/uploads/editor/Omaintec2017... · MADY MOHAMED USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY IN MAINTENANCE

8

Figure 4: Commissioning Phases

Page 9: USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY …exicon.website/uploads/editor/Omaintec2017... · MADY MOHAMED USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY IN MAINTENANCE

9

USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY IN MAINTENANCE WORK

Table 2: Commissioning Plan Contents

Page 10: USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY …exicon.website/uploads/editor/Omaintec2017... · MADY MOHAMED USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY IN MAINTENANCE

10

Legend:

R= Responsible

C=Consult

A = Approval

I = Inform

Pro

ject

Man

ag

er /

Dev

elop

men

t

Con

sult

an

t

Op

era

tion

s P

erso

nn

el

Ow

ner

Rep

/BC

Hou

sin

g

Tec

hn

ica

l E

xp

erts

/Des

ign

Tea

m

Con

stru

ctio

n

Ma

na

ger

(C

M)/

Gen

eral

Con

tra

cto

r C

om

mis

sion

in

g A

gen

t

Arc

hit

ect

Pre-Design Phase

Develop Owner’s Project Requirements R C A C C

Develop preliminary commissioning scope R C A C C

Develop preliminary Commissioning Plan C I C I R I

Design Phase

Hold design stage Cx meetings I I I I I R I

Identify project specific responsibilities R I I I C C

Review Owner’s Project Requirements

documentation for completeness and clarity

C C I I I R I

Develop Basis of Design C C A C/A I C R

Develop Commissioning Plan C I C C R C

Perform focused Cx reviews of design drawings and

specifications

I I I C C R C

Create Cx specifications including testing protocols for

all commissioned equipment/systems

I I I C C R C

Integrate Cx activities into project schedule A I I I R C I

Construction Phase

Review submittals applicable to equipment/system

being commissioned

I I C C R A

Develop Construction Checklists for

equipment/systems to be commissioned

A C I R C

Review changes of systems A A I/C C C R

Complete (fill in) Construction Checklists as the

work is accomplished

I I R C I

Continuously maintain record drawings (as-built) and

submit as detailed in the contract documents

I I R C C

Coordinate functional testing for all commissioned

systems and assemblies

I I I C C R C

Perform quality control inspections I I R C R C

Maintain record of functional testing I I/C I/C I/C C R C

Prepare Cx progress reports I I I I I R C

Hold construction phase Cx meetings C C C C C R C

Maintain Master Issues Log I I I C C R C

Implement training program for operating

personnel

I C C I/C R C C

Post-Construction and Operations Phase

Coordinate and supervise deficiency corrections A I/C I/C I/C C C R

Coordinate and supervise deferred and seasonal

testing

A I/C I/C I/C C R C

Review current building operations at warranty

review meetings

I I/C I/C I/C I/C R C

Complete Final Commissioning Report A I I I I R I

This table summarize the main tasks during

the different project commissioning phases

and provide relates each task with the

responsibilities of the commissioning team.

Table 3: Commissioning MajorResponsibilities Matrix, after ASHRAE

Page 11: USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY …exicon.website/uploads/editor/Omaintec2017... · MADY MOHAMED USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY IN MAINTENANCE

11

Fin

al

Co

mm

is

sio

nin

g

Re

po

rt

Cx Authority

review the OPR Develop

Commissioning

Plan

Simulation

/Modelling

results

Update

Project

Drawings

as BuiltCoordinate

Functional

Testing

Maintain Records of

Functional TestsIssue Log

Commissioning

Documentation

Create Cx specification

for equipment

Commissioning

Processes

Construction Checklist

Seasonal

Testing

Com

pu

ter

stu

dy

Con

stru

ctio

np

ha

seO

per

ati

on

al

ph

ase

Quality

control

inspections

Develop - Issues LogOPR /BoD

AnalysisPerform

deficiency

corrections

Review

Building

Operation

Target

Identification

(LEED Fundamental

Commissioning)

Des

ign

ph

ase

USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY IN MAINTENANCE WORK