MADY MOHAMED
USING RATING SYSTEMS AS A GUIDE TOOL FOR
CONSULTANCY IN MAINTENANCE WORK
2
USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY IN MAINTENANCE WORK
Introduction1
Research Aim2
Proposed Methodology3
Presentation Content
3
Introduction:
This paper is focusing on employing rating systems to guide the
process of the operation and maintenance for buildings. The LEED
fundamental commissioning is discussed briefly while a detailed
explanation for the processes, tasks and responsibilities of each
stakeholder in building projects is presented.
USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY IN MAINTENANCE WORK
4
USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY IN MAINTENANCE WORK
Figure : the credits weighting of the
environmental categories of the LEED [29]
Introduction:
Rating systems are groups of
requirements for projects. Each
group is geared towards the unique
needs of a project. Projects earn
points to satisfy green building
requirements. Within each of the
LEED credit categories, projects
must satisfy prerequisites and earn
points
5
USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY IN MAINTENANCE WORK
Figure 2: EA LEED V4 category including the Fundamental and Enhanced commissioning [30]
6
Commissioning:
While the focus of the commissioning includes individual equipment
or systems, it is considered a holistic approach emphasizing the
connections between components and the overall building energy
efficiency .
Commissioning assure having a good level of maintenance,
USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY IN MAINTENANCE WORK
7
Figure 3: Relationships between commissioning and energy-efficiency
8
Figure 4: Commissioning Phases
9
USING RATING SYSTEMS AS A GUIDE TOOL FOR CONSULTANCY IN MAINTENANCE WORK
Table 2: Commissioning Plan Contents
10
Legend:
R= Responsible
C=Consult
A = Approval
I = Inform
Pro
ject
Man
ag
er /
Dev
elop
men
t
Con
sult
an
t
Op
era
tion
s P
erso
nn
el
Ow
ner
Rep
/BC
Hou
sin
g
Tec
hn
ica
l E
xp
erts
/Des
ign
Tea
m
Con
stru
ctio
n
Ma
na
ger
(C
M)/
Gen
eral
Con
tra
cto
r C
om
mis
sion
in
g A
gen
t
Arc
hit
ect
Pre-Design Phase
Develop Owner’s Project Requirements R C A C C
Develop preliminary commissioning scope R C A C C
Develop preliminary Commissioning Plan C I C I R I
Design Phase
Hold design stage Cx meetings I I I I I R I
Identify project specific responsibilities R I I I C C
Review Owner’s Project Requirements
documentation for completeness and clarity
C C I I I R I
Develop Basis of Design C C A C/A I C R
Develop Commissioning Plan C I C C R C
Perform focused Cx reviews of design drawings and
specifications
I I I C C R C
Create Cx specifications including testing protocols for
all commissioned equipment/systems
I I I C C R C
Integrate Cx activities into project schedule A I I I R C I
Construction Phase
Review submittals applicable to equipment/system
being commissioned
I I C C R A
Develop Construction Checklists for
equipment/systems to be commissioned
A C I R C
Review changes of systems A A I/C C C R
Complete (fill in) Construction Checklists as the
work is accomplished
I I R C I
Continuously maintain record drawings (as-built) and
submit as detailed in the contract documents
I I R C C
Coordinate functional testing for all commissioned
systems and assemblies
I I I C C R C
Perform quality control inspections I I R C R C
Maintain record of functional testing I I/C I/C I/C C R C
Prepare Cx progress reports I I I I I R C
Hold construction phase Cx meetings C C C C C R C
Maintain Master Issues Log I I I C C R C
Implement training program for operating
personnel
I C C I/C R C C
Post-Construction and Operations Phase
Coordinate and supervise deficiency corrections A I/C I/C I/C C C R
Coordinate and supervise deferred and seasonal
testing
A I/C I/C I/C C R C
Review current building operations at warranty
review meetings
I I/C I/C I/C I/C R C
Complete Final Commissioning Report A I I I I R I
This table summarize the main tasks during
the different project commissioning phases
and provide relates each task with the
responsibilities of the commissioning team.
Table 3: Commissioning MajorResponsibilities Matrix, after ASHRAE
11
Fin
al
Co
mm
is
sio
nin
g
Re
po
rt
Cx Authority
review the OPR Develop
Commissioning
Plan
Simulation
/Modelling
results
Update
Project
Drawings
as BuiltCoordinate
Functional
Testing
Maintain Records of
Functional TestsIssue Log
Commissioning
Documentation
Create Cx specification
for equipment
Commissioning
Processes
Construction Checklist
Seasonal
Testing
Com
pu
ter
stu
dy
Con
stru
ctio
np
ha
seO
per
ati
on
al
ph
ase
Quality
control
inspections
Develop - Issues LogOPR /BoD
AnalysisPerform
deficiency
corrections
Review
Building
Operation
Target
Identification
(LEED Fundamental
Commissioning)
Des
ign
ph
ase