using change management in primavera contract management

86
Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 1

Upload: p6academy

Post on 21-Feb-2017

710 views

Category:

Business


1 download

TRANSCRIPT

Page 1: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 1

Page 2: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 2

FYI: New Portal with same DocID

Archive

740964.1

Schedule

740966.1

Generic Advisor

Webcast Note

740966.1

before

now

Page 3: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 3

Using Change Management in Primavera Contract Management

Teleconference Access: US & Canada: 888-259-4812 Toll Number: 706-679-4880 Password: AdvisorPG Current Advisor Webcast Schedule and Archived Download – DOC#740966.1

Upcoming live webcasts and recent recordings:

April 25, 2013: PeopleSoft Payroll for North America and Benefits Release

9.2 – Empowering Employees with Employee Self Service

April 25, 2013: PeopleSoft: Your Upgrade: Preparing for Platform Changes

April 25, 2013: JDE E1: Change Assistant: Overview and Benefits

April 25, 2013: Database: Automation of patch conflict resolution and

deployment through EM 12c

April 25, 2013: EBS – MFG: ASCP-Rapid Planning Integration

April 30, 2013: FM: Diagnostics Enhancements in SOA Suite 11g PS6

(11.1.1.7)

April 30, 2013: Mutexes in Oracle Database

April 30, 2013: Demonstration of the benefits of PeopleSoft ePerformance

9.2

April 30, 2013: Primavera: Data Integrity When Performing Imports

May 1, 2013: What’s New in PeopleSoft Recruiting Solutions 9.2

May 2, 2013: Campus Solutions: Financial Aid Regulagtory 2013-2014

Release 3 (9.0 Bundle #29)

May 2, 2013: PeopleTools: Search Framework Introduction and Setup

May 7, 2013: Upgrading to PeopleTools 8.53

May 7, 2013: Oracle Systems: Best Practices for Migrating to Oracle

Solaris 11

May 7, 2013: Proactive Capabilities in MOS for JD Edwards EnterpriseOne

Page 4: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 4

The following is intended to outline our general

product direction. It is intended for information

purposes only, and may not be incorporated into

any contract. It is not a commitment to deliver any

material, code, or functionality, and should not be

relied upon in making purchasing decision. The

development, release, and timing of any features

or functionality described for Oracle’s products

remains at the sole discretion of Oracle.

Safe Harbor Statement

Page 5: Using Change Management in Primavera Contract Management

<Insert Picture Here>

Using Change Management in Primavera Contract Management

Sunny Bains

Janette Caceres

Senior Technical Support Engineers

Page 6: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 6

AGENDA

Change Management Process

Defining Reason Codes

Initiating Change Management from other Documents

Adding Change Documents / Proposals / Change Orders

Generating Change Documents from Change Management

Applying Markup

Collecting into Change Orders

Approving Change Orders

Costing

Entering Change Orders / Proposals without Using Change

Management

Page 7: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 7

Contracts and Purchase Orders often change

Change Management automates the Change Process

Change Management is a workflow process

Change Management

Page 8: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 8

Change Management is a Workflow Process

Page 9: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 9

Create customized workflow with Change Management

Helps simplify the Change process

One location to enter all necessary information

Change Management

Page 10: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 10

Change Management Document

Page 11: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 11

Project Settings

Page 12: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 12

Project Settings

Page 13: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 13

Project Settings

Page 14: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 14

Document Setup

Page 15: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 15

Adding a Custom Document Type

Page 16: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 16

Adding a Custom Document Type

Page 17: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 17

Adding a Custom Document Type

Page 18: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 18

New Custom Document Type Added

Page 19: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 19

Clearing Phases of Change Management

Page 20: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 20

Calculating Net Amount of Previous Change

Page 21: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 21

Calculating Net Amount of Previous Change

If calculating based on Change date:

Date is the primary sort with the change number as a secondary sort

for changes created on the same day.

Changes must be approved in sequence by date for the Net Amount of

Previous Change to be calculated accurately.

If calculating based on Change number:

The date of the Change documents will be ignored.

Changes must be approved in sequence by number for the Net

Amount of Change to be calculated accurately.

Note: Pending changes included in the calculation follow the same

rules

Page 22: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 22

Contract Management User Levels

Contract Management Administrator

- Full Access Rights to all projects

Project Administrator

- Full Access Rights to currently assigned projects

Regular User

- Administrator defined Access Rights

Page 23: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 23

Restricting Access to Change Management

Page 24: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 24

Project Access Dialog Box

Page 25: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 25

Project Access Dialog Box

Page 26: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 26

Defining Reason Codes

Add change reasons for Change Management

Use the reasons for filtering grouping and sorting

Page 27: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 27

Reason Codes

Page 28: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 28

Adding and Deleting Reason Codes

Page 29: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 29

Change Management Log Window

Page 30: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 30

Change Management Document

Page 31: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 31

Adding a Change Management Document

From Change Management module

From other document types:

- Daily reports

- Meeting minutes

- Notepads

- Noncompliance notices

- Notices

- Punch lists

- Request for information RFI

- Trends

- Contracts

Page 32: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 32

Initiating Change Management (CM)

Page 33: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 33

General Tab

Page 34: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 34

Status Tab

Page 35: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 35

Details Tab

Page 36: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 36

Remarks Tab

Page 37: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 37

Budgeted Tab

Page 38: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 38

Budgeted Tab

Page 39: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 39

Commitments Tab

Page 40: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 40

Documents by Phase

Page 41: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 41

Adding Commitments

Page 42: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 42

Adding Commitments

Page 43: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 43

Add Multiple Estimates

Page 44: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 44

Add Multiple Estimates Window

Page 45: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 45

Multiple Estimates Added

Page 46: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 46

Copy Commitments to Budgeted

Page 47: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 47

Copy Commitments to Budgeted Window

Page 48: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 48

Deleting Generated Proposal/Change

Documents

Documents created via Change Management can not be deleted

outside of Change Management

Document can not be deleted if later phases have been generated

from it.

Page 49: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 49

Deleting Change Management Document

Page 50: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 50

Costing information assigned to generated documents

Post to any portion of the Cost Worksheet

Costing Generated Documents

Page 51: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 51

Including Changes on the Cost Worksheet

Page 52: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 52

Proposed change orders (PCO)

Change order requests (COR)

Estimates (EST)

Request for proposal (RFP)

Proposals: Seek for a bid to perform a specific activity/change

Change Orders: Specify a redirection of plans or introduce new items to

show approved increases/decreases

Proposals & Change Orders

Page 53: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 53

What can we do with Markup?

Have different Markup values based on total labor, material, and

equipment costs

Set default values for overhead and profit, but you can also add

additional Markup values for each document

Assign Markup categories using a percentage rate or a flat amount

with both types

Set Markup values at the contract or purchase order level, similar to

requisitions

Specify the target cost code to which you want to apply the Markup

amount

Page 54: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 54

Markup from Collected Documents

Page 55: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 55

Cost Worksheet

Page 56: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 56

Cost Worksheet

Page 57: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 57

Markup for Changes

Page 58: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 58

Markup for Changes

Page 59: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 59

Adding a Change Order Outside of Change Management

Enable setting in Project Settings dialog box

Need to have collected at least one Change Order document

Page 60: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 60

Document Creation Outside of CM

Page 61: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 61

Change Order Document

Page 62: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 62

Change Order Document

Page 63: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 63

Change Order Document

Page 64: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 64

Change Order Summary Tab

Page 65: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 65

Markup for Changes

Page 66: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 66

Collected Changes

Page 67: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 67

Line Items Tab

Page 68: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 68

Line Items Tab

Page 69: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 69

Line Items Tab

Page 70: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 70

Details Tab

Page 71: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 71

Details Tab

Page 72: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 72

Details Tab

Page 73: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 73

Approval Process

Page 74: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 74

Approval Process

Page 75: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 75

Multiple Reviewer Process

Page 76: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 76

Approving Change Orders

Page 77: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 77

Getting Approved Change Order in to Requisition

Page 78: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 78

Getting Approved Change Order in to Requisition

Page 79: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 79

Collecting into Change Orders

Collect costs from pending Change Orders

Multiple Changes from one Contract into one Change Order

Page 80: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 80

Line Items Tab

Page 81: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 81

Collecting Change Orders

Page 82: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 82

Collecting Change Orders

Page 83: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 83

Collect from Changes option only available if created

outside of Change Management

Change Order must not have been collected before

Change Order should not have status of Approved,

Closed or Rejected

Status of Change Order collected in to another Change

Order gets set to Closed

Collecting into Change Orders

Page 84: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 84

Are You Ready To Get Proactive?

Avoid the unexpected

Don’t leave value on the table

Lower overall organizational costs through preventative

maintenance

Reduce risks and maximize uptime

Achieve resolution faster

Streamline and simplify your daily operations

Get even more through connection

Discover more about Get Proactive

https://support.oracle.com/CSP/main/article?cmd=show

&type=ATT&id=1385165.1:DISCOVER

ACT Get Proactive

Access proactive capabilities available for your products

by visiting the product pages at My Oracle Support;

Article ID 432.1

Contact the Get Proactive team

today for help getting started

[email protected]

Page 85: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 85

Page 86: Using Change Management in Primavera Contract Management

Copyright © 2013, Oracle and/or its affiliates. All rights reserved. 86

THANK YOU