US Organization

05 April 2013 U.S. ATLAS Electronics Meeting at BNL 1

Page 2: US Organization 05 April 2013U.S. ATLAS Electronics Meeting at BNL1

US nSW Upgrade – Path to Approval

Review Process – path to Lehman Review & CD1 approval December 19-20, 2012 at BNL

o First review of program, scope and budget with US ATLAS Managerso Recommendation to concentrate on Electronics & Alignment

January 17-18, 2013 at Stony Brooko Mini-Lehman Review for practice – external reviewerso Presented budgets in detail, including cost books and risk analysiso Scope and budget settled

January 30-31, 2013 at BNLo Directors Review of Operations & Upgrade – external reviewerso Recommended more details of milestones, contingencies

March 4-7, 2013 DOE/NSF Operations Review at San Diegoo Interface between M&O and Upgrade (Kotcher & Hobbs)

July 11-12, 2013 BNL Directors Review of Upgrade Project at BNLo Will be a ‘Lehman-like’ Review

August 26-29, 2013 Lehman Review for CD1 approval at FNALo Key that we ‘pass’ this review for $ flow

05 April 2013 U.S. ATLAS Electronics Meeting at BNL 2

Page 3: US Organization 05 April 2013U.S. ATLAS Electronics Meeting at BNL1

Muon New Small Wheels: approved at Oct 2012 CB; now following up on milestones, e.g. full size Micromegas (2x1 m2), sTGC trigger demonstrator, etc. TDR in May

FTK: approved at March 2012 CB; vertical slice tested parasitically in 2012-2013 run;simulation for TDR (physics case) on critical path

Consolidating a (coherent) physics case for above projects is one of most crucial/urgentaspects in view of TDRs; presently hampered by severe lack of effort, in all of software developments, validation, performance/physics studies, as well as by computing resources more involvement also from the upgrade community is needed efforts being organized to increase synergies with Physics/CP groups

LAr (higher-granularity readout for trigger): IDR and kick-off in January; approved by EB for endorsement at Friday CB

TDAQ (LVL1, HLT/DAQ, trigger/online software, etc.): IDR and kick-off in January; approved by EB for endorsement at Friday CB

AFP: IDR and kick-off in Sept 2012 following up on milestones (e.g. project organization, consolidation of physics case) CB approval in 2014

Upgrade: Phase-1 projects

Page 4: US Organization 05 April 2013U.S. ATLAS Electronics Meeting at BNL1

U.S. ATLAS Electronics Meeting at BNL 4

Project Development

Developed draft BOEs and cost book – nSW will be DOE Schedule for drafts of Bases of Estimate

05 April 2013

1.2 - nSW (Polychronakos,Taylor)1 1.2.1.1 F/E Chip Johns 29-Mar 3-Apr2 1.2.1.2 F/E Board Johns 29-Mar 3-Apr3 1.2.1.3.1-3 Data Driver Cards Johns 10-Apr4 1.2.1.3.4-6 AMC Modules & Carrier Bds Johns 10-Apr5 1.2.1.4 MM RODs Johns 3-Apr6 1.2.2.1 Precision Alignment Bars Bensinger 22-Mar 29-Mar7 1.2.2.2 Prox Monitors Bensinger 3-Apr8 1.2.2.3 Alignment DAQ Bensinger 29-Mar 3-Apr9 1.2.3.1 Trigger Data Serializer Zhu 3-Apr

10 1.2.3.2 Router Boards Zhu 3-Apr