US Army Corps of Engineers
BUILDING STRONG®
Ft Leonard Wood Area OfficeWater Tower Lift
18 September 2015Dale Bleckman
Resident EngineerNorth Resident Office
![Page 2: US Army Corps of Engineers BUILDING STRONG ® Ft Leonard Wood Area Office Ft Leonard Wood Area Office Water Tower Lift 18 September 2015 Dale Bleckman Resident](https://reader036.vdocuments.mx/reader036/viewer/2022062805/5697c0011a28abf838cc246f/html5/thumbnails/2.jpg)
2 BUILDING STRONG®
AgendaThe Water Tower Extension
• What happened• Options Considered• The Lift• Architect-Engineer Liability• Questions
![Page 3: US Army Corps of Engineers BUILDING STRONG ® Ft Leonard Wood Area Office Ft Leonard Wood Area Office Water Tower Lift 18 September 2015 Dale Bleckman Resident](https://reader036.vdocuments.mx/reader036/viewer/2022062805/5697c0011a28abf838cc246f/html5/thumbnails/3.jpg)
3 BUILDING STRONG®
What Happened• 500,000 gallon water tower near vet clinic finished in
late 2014
• After completion it was determined that water pressure was about 14 psi too low.
• Research indicated that the tower was designed 33.8 feet low
• Error was due to surveyor software glitch
• Architect-Engineer accepted responsibility for the design error
![Page 4: US Army Corps of Engineers BUILDING STRONG ® Ft Leonard Wood Area Office Ft Leonard Wood Area Office Water Tower Lift 18 September 2015 Dale Bleckman Resident](https://reader036.vdocuments.mx/reader036/viewer/2022062805/5697c0011a28abf838cc246f/html5/thumbnails/4.jpg)
4 BUILDING STRONG®
Options Considered• Use pump
Additional maintenance Additional cost
• Raise the tower 33.8 feet Use a jacking system Use cranes
![Page 5: US Army Corps of Engineers BUILDING STRONG ® Ft Leonard Wood Area Office Ft Leonard Wood Area Office Water Tower Lift 18 September 2015 Dale Bleckman Resident](https://reader036.vdocuments.mx/reader036/viewer/2022062805/5697c0011a28abf838cc246f/html5/thumbnails/5.jpg)
5 BUILDING STRONG®
The Lift• Water Tower weighed approx 225,000 pounds
• Three cranes used (550 ton, 450 ton, 210 ton) and 150’ man lift
• 13 tractor trailers required to move one of the big cranes – over 500,000 pounds of counterweights
• New 33.8 foot, 53,000 pound section added to extend tower from 122’ to 156’
• Prep for lift started at 0530 hrs, 18 Sep 2015; tank was standing on its own by 1730 hrs same day
• Weather was one of the main controlling factor
![Page 6: US Army Corps of Engineers BUILDING STRONG ® Ft Leonard Wood Area Office Ft Leonard Wood Area Office Water Tower Lift 18 September 2015 Dale Bleckman Resident](https://reader036.vdocuments.mx/reader036/viewer/2022062805/5697c0011a28abf838cc246f/html5/thumbnails/6.jpg)
6 BUILDING STRONG®
THE LIFT
![Page 7: US Army Corps of Engineers BUILDING STRONG ® Ft Leonard Wood Area Office Ft Leonard Wood Area Office Water Tower Lift 18 September 2015 Dale Bleckman Resident](https://reader036.vdocuments.mx/reader036/viewer/2022062805/5697c0011a28abf838cc246f/html5/thumbnails/7.jpg)
7 BUILDING STRONG®
Architect Engineer Liability
• Design error was due to software glitch with surveyor’s program
• Designer accepted responsibility and re-designed tower
• Designer is responsible for re-construction cost but is not responsible for the additional 33.8 foot section
• Re-construction costs paid from project $s; AE Liability $s, if any, will go to US Treasury
![Page 8: US Army Corps of Engineers BUILDING STRONG ® Ft Leonard Wood Area Office Ft Leonard Wood Area Office Water Tower Lift 18 September 2015 Dale Bleckman Resident](https://reader036.vdocuments.mx/reader036/viewer/2022062805/5697c0011a28abf838cc246f/html5/thumbnails/8.jpg)
8 BUILDING STRONG®
Questions