UPPER HUMBER ENC TRIAL Nov 2012 – Oct 2013
Andy Hinton – Geographic Manager England East and South.
• Introduction and Background – why the Trial was conducted.
• Description of our new Hydrographic database system.
• Trial itself – how the product and service evolved over time
• Conclusions/ key lessons learnt
• Further work and applications
Upper Humber ENC cell presentation.
• Humber Bridge to Goole on River Ouse and Keadby on River Trent
• Goole – UK’s most inland port - 894th in world
•1600 commercial vessels - 80% ECDIS fitted
• Accommodates vessels of 5.5m draught
INTRODUCTION: AREA IN QUESTION
Dynamic hydrographic environment.
Tortuous navigation
Surveyed by ABP Humber on very frequent basis :
2 weeks
6 weeks
8 weeks
ABP HUMBER SURVEY SCHEDULE.
ABP Humber output
• Survey – 2 weeks
(Tuesday)
• New Ships course
• Autocad and pdf sheets
• Buoy moves (Friday)
• Chart - 2 months
• Paper chart 3497 – 1:50,000
• ‘Unchartable’.
• Traditional system - cannot cope with speed of change.
•Paper chart NMs - 12/15 days, New Edition - 5 to 7 weeks
• ENC updates - tied into paper chart NM timeframes.
UKHO CURRENT CHARTING.
REASONS FOR THE TRIAL.
• Introduction of the Hydrographic Database • Berth to Berth ENC service top 1000 ports.
• 80% vessels using river have ECDIS fitted.
• MAIB report – Sea Mithril 2007.
Hydrographic Database (HDB)
Incoming data
Source
Database
Paper Chart Editor
Product Editor
Paper Chart NMs NEs
AMLs
ARCS
ENC Updates NEs
HPD
CARIS HPD – Database approach.
Source database (S57) – updated real time.
Breaks link between paper charts and ENCs
Humber area rolled into HDB in 2010/ 2011.
THE TRIAL : PRODUCT CREATION. APRIL TO NOV 2012
Agreed to conduct Trial – February 2012
Two targets – Update ENC in two working days
Had to enhance navigation.
Product creation - Scale 1:25,000.
Critical features - Ship’s course, buoyage, coast, wrecks,
Topography – enhanced
Hydrography – General backdrop.
Ship’s Course/ Buoyage updated -14 days
Emailed out to ABP Humber 9th November
HUMBER ENC VERSION 1
9th November 2012.
Ship’s course
Buoyage
General Hydrography
No depths
HUMBER ENC VERSION 2
10th Jan 2013
All soundings
Unsurveyed outside
Update 2 working days.
Presentation issues
HUMBER ENC VERSION 3
February 2013
Contours only – 15
Ships course/ Buoys
Depth reassurance issue
HUMBER ENC VERSION 4 (FINAL)
April 2013
Basic depth into.
Contours
Decimetre
0.5 dry to 1m.
Ships course/ buoy
UKHO: Conclusions/ Lessons learnt .
• Production and Maintenance System.
• Automation.
• System performance.
• Port Authority/ survey contractor – technical capability.
Further work. • Non technical aspects • Commercially viable ?• Licensing/ distribution ?.
Future applications• Unchartable areas. • ENC Berthing cells.
Upper Humber ENC Cell.
Andrew Hinton.
ABP Humber Survey Team
Conduct survey
Survey processing and analysis.
Decide new buoyageand ships course
Create updated chart with new course and buoyage.
Conduct Buoy moves.
Day 1
Day 2
Day 3
Day 4
UKHO
Alerted survey imminent from NM
Two day target Import data, create surface, auto contouring & sounding selection. Delete existing features and replace.
Verification and validation checking of cell.
ABP Pilots
Issue NM
shoals
xyz and dxf file
Issue updated chart
New edition of ENC.
New edition of ENC
(Email)
PROCESSING CYCLE - FORTNIGHT