UPDATE ON THE N2 WILD

COAST ROAD

25 January 2016

Photo – Msikaba Gorge

At Msikaba bridge site

1

Page 2: UPDATE ON THE N2 WILD COAST ROAD - SLR … · UPDATE ON THE N2 WILD COAST ROAD ... (balanced cantilever construction) & box girder ... Slide 1 Author: Tshivhangwaho Mudau

Progress since November 2016

2

• Construction

• Contracts for training of SMMEs and construction of local access

roads started

• Contracts for the construction of 4 Haul Roads to bridge sites

started (Nov 2016 to May 2017).

• Associated Search and Rescue of TOPS completed for

construction camp sites and first km of haul road routes

• Relocation of affected houses and graves started (66

structures/18 homesteads)

• Advertising for exhumation of graves without family

contratcs to be done shortly

• Repairs and maintenance to provincial and municipal roads

leading to the sites to be accelerated

Page 3: UPDATE ON THE N2 WILD COAST ROAD - SLR … · UPDATE ON THE N2 WILD COAST ROAD ... (balanced cantilever construction) & box girder ... Slide 1 Author: Tshivhangwaho Mudau

Progress since November 2016

3

• Closing date for both bridge tenders extended to January 2016

• Mtentu Bridge tenders closed 23 January 2017

• R1.510 billion was lowest tender received

• Msikaba Bridge tenders to close 30 January 2017

• Land acquisition for remaining sections of route continuing

• Detailed Design for remaining sections of roads

• 2 packages advertised and closed in December

• 2 packages currently out to Tender

• 3 packages still to be advertised

• Geotechnical

• Application submitted for Mining Permit and Environmental

Authorisation for Quarry Site SQ1 located between Msikaba and

Mtentu Bridges south of Holy Cross.

• Investigative drilling for other potential quarry sites and borrow

pits undertaken

Page 4: UPDATE ON THE N2 WILD COAST ROAD - SLR … · UPDATE ON THE N2 WILD COAST ROAD ... (balanced cantilever construction) & box girder ... Slide 1 Author: Tshivhangwaho Mudau

Progress since last meeting in November

2016

4

• Geotechnical cont/

• Drilling Investigative drilling for water sources (boreholes) and

geotechnical investigation purposes ongoing

• Compliance with Environmental requirements

• Search and Rescue and horticultural services by 2 service

providers started on Haul road sites

• ECO services by 2 service providers started

Page 5: UPDATE ON THE N2 WILD COAST ROAD - SLR … · UPDATE ON THE N2 WILD COAST ROAD ... (balanced cantilever construction) & box girder ... Slide 1 Author: Tshivhangwaho Mudau

N2 Wild Coast Road

Msikaba Bridge

5

Msikaba

bridge site

Page 6: UPDATE ON THE N2 WILD COAST ROAD - SLR … · UPDATE ON THE N2 WILD COAST ROAD ... (balanced cantilever construction) & box girder ... Slide 1 Author: Tshivhangwaho Mudau

General

Arrangement

6

Page 7: UPDATE ON THE N2 WILD COAST ROAD - SLR … · UPDATE ON THE N2 WILD COAST ROAD ... (balanced cantilever construction) & box girder ... Slide 1 Author: Tshivhangwaho Mudau

N2 Wild Coast Road

Msikaba Bridge

7

Page 8: UPDATE ON THE N2 WILD COAST ROAD - SLR … · UPDATE ON THE N2 WILD COAST ROAD ... (balanced cantilever construction) & box girder ... Slide 1 Author: Tshivhangwaho Mudau

N2 Wild Coast Road

Mtentu Bridge

8

Mtentu

bridge site

Page 9: UPDATE ON THE N2 WILD COAST ROAD - SLR … · UPDATE ON THE N2 WILD COAST ROAD ... (balanced cantilever construction) & box girder ... Slide 1 Author: Tshivhangwaho Mudau

N2 Wild Coast Road

Mtentu Bridge

9

Combination rigid frame

(balanced cantilever

construction) & box girder

(incrementally launched) bridge

Page 10: UPDATE ON THE N2 WILD COAST ROAD - SLR … · UPDATE ON THE N2 WILD COAST ROAD ... (balanced cantilever construction) & box girder ... Slide 1 Author: Tshivhangwaho Mudau

BRIDGE DETAILS

• National Route 2, Section 25, km 4.6

• 5 span post tensioned T-beam deck (longest span of 20m)

• Built in 1979

• Existing minimum clearance of 5.030m

• SANRAL minimum is 6.0m for new, for existing discuss with Bridge

Network Manager but not <5.6m

N2 Wild Coast Road

Mtentu Bridge

Page 11: UPDATE ON THE N2 WILD COAST ROAD - SLR … · UPDATE ON THE N2 WILD COAST ROAD ... (balanced cantilever construction) & box girder ... Slide 1 Author: Tshivhangwaho Mudau

N2 Wild Coast Road

Time Frames

11

2017 • Construction of Haul roads to 2 bridge sites (6 months)

• Start of construction of two Bridges (3-4 year construction period)

• Land acquisition for entire route to be completed

• Detailed design of remaining packages

• SMME focused Tenders

• Tenders for Relocation of structures

• Tenders for construction of Access roads

• Stakeholder engagement

• Regular meetings with DMs, LMs, Traditional Leaders and

business forums to be formalised

• Ongoing community consultation

• Specific community engagement as part of detailed design

development

• SANRAL to set up a Pondoland local office

Page 12: UPDATE ON THE N2 WILD COAST ROAD - SLR … · UPDATE ON THE N2 WILD COAST ROAD ... (balanced cantilever construction) & box girder ... Slide 1 Author: Tshivhangwaho Mudau

N2 Wild Coast Road

Time Frames

12

2018 • Construction for relocations and Access roads by SMMEs to be

completed

• Tender processes for construction of remaining sections of roads

and bridges

2019 -2021 • Construction of all greenfields roads and bridges (~ 3 year

construction periods)

• Construction of all community legacy projects (SMME focused)

• Rehabilitation

Page 13: UPDATE ON THE N2 WILD COAST ROAD - SLR … · UPDATE ON THE N2 WILD COAST ROAD ... (balanced cantilever construction) & box girder ... Slide 1 Author: Tshivhangwaho Mudau

N2 Wild Coast Road

Funding

13

• Funding for the bridges has been allocated from

SANRALs non-toll budget allocation

• Hybrid Funding Model to be used to fund the

remaining road portions:

• Combination of state funding (Fiscus) and

borrowing (Bonds)

• However the exact details are currently being

resolved with Treasury

• Funding for biodiversity offset agreement

• Awaiting Treasury procedures

Page 14: UPDATE ON THE N2 WILD COAST ROAD - SLR … · UPDATE ON THE N2 WILD COAST ROAD ... (balanced cantilever construction) & box girder ... Slide 1 Author: Tshivhangwaho Mudau

N2 Wild Coast Road

Impact

14

The project will have a huge positive impact on the Eastern

Cape and particularly the Pondoland area • The N2 WCR will be a Sustainable Development Corridor that will

form the Spine for the EC and Pondoland Development

• Greenfields portion will provide access to one of the most beautiful

but currently inaccessible and impoverished areas in SA

• The Mtentu and Msikaba bridges will be tourist attractions in their

own right complimenting the tourism attractions of the Wild Coast

• Will improve economic and logistic linkages in the region

• The project will have major socio- economic benefits

• Will open up the tourism and agriculture potential of the region

• Will significantly benefit the environment through the environmental

off-set agreement

• Will transform the EC construction industry landscape

Page 15: UPDATE ON THE N2 WILD COAST ROAD - SLR … · UPDATE ON THE N2 WILD COAST ROAD ... (balanced cantilever construction) & box girder ... Slide 1 Author: Tshivhangwaho Mudau

Thank You

Website: www.sanral.co.za

Fraud Hotline: Toll-Free Phone No: 0800 204 558

Toll-Free Fax No: 0800 007 788 E-mail: [email protected]

15

Page 16: UPDATE ON THE N2 WILD COAST ROAD - SLR … · UPDATE ON THE N2 WILD COAST ROAD ... (balanced cantilever construction) & box girder ... Slide 1 Author: Tshivhangwaho Mudau

N2 WIld Coast Toll Highway - Southern Portion of the Greenfields Sections

EMC Meeting ECO Findings Presentation

Date: 25 January 2017

Page 17: UPDATE ON THE N2 WILD COAST ROAD - SLR … · UPDATE ON THE N2 WILD COAST ROAD ... (balanced cantilever construction) & box girder ... Slide 1 Author: Tshivhangwaho Mudau

Introduction

Compliance Monitoring

Construction Progress

Msikaba North

Msikaba South

Public Involvement

Non-Compliances & Incidents

Areas of Good Compliance

Areas of Concern

Page 18: UPDATE ON THE N2 WILD COAST ROAD - SLR … · UPDATE ON THE N2 WILD COAST ROAD ... (balanced cantilever construction) & box girder ... Slide 1 Author: Tshivhangwaho Mudau

Greenfields sections of the project comprise new road

construction

(1) Ndwalane to Ntafufu

(2) Lusikisiki to Mthamvuna River Eastern Cape

EIMS appointed as ECO for Southern Sections:

Ndwalane to Msikaba

Page 19: UPDATE ON THE N2 WILD COAST ROAD - SLR … · UPDATE ON THE N2 WILD COAST ROAD ... (balanced cantilever construction) & box girder ... Slide 1 Author: Tshivhangwaho Mudau
Page 20: UPDATE ON THE N2 WILD COAST ROAD - SLR … · UPDATE ON THE N2 WILD COAST ROAD ... (balanced cantilever construction) & box girder ... Slide 1 Author: Tshivhangwaho Mudau
Page 21: UPDATE ON THE N2 WILD COAST ROAD - SLR … · UPDATE ON THE N2 WILD COAST ROAD ... (balanced cantilever construction) & box girder ... Slide 1 Author: Tshivhangwaho Mudau
Page 22: UPDATE ON THE N2 WILD COAST ROAD - SLR … · UPDATE ON THE N2 WILD COAST ROAD ... (balanced cantilever construction) & box girder ... Slide 1 Author: Tshivhangwaho Mudau

Reporting Period:

November to December 2016

Compliance Documentation:

Record of Decision (ROD)

Environmental Management Programme (EMPR)

Final Environmental Impact Assessment Report (EIAR)

Plant Permit

Water Use Licences (WUL)

Forestry Licence

Page 23: UPDATE ON THE N2 WILD COAST ROAD - SLR … · UPDATE ON THE N2 WILD COAST ROAD ... (balanced cantilever construction) & box girder ... Slide 1 Author: Tshivhangwaho Mudau

Search and Rescue Activities - Simply Enviro JV

Site establishment:

Fencing and clearing of site camp area

Lay down of storage containers and offices in progress

Conservancy tank had been installed at the site camp

Chemical toilets were delivered

A self-bund fuel storage tank & power generator

installed

Security house being constructed

Some construction vehicles (TLB and excavators) had

been delivered

Page 24: UPDATE ON THE N2 WILD COAST ROAD - SLR … · UPDATE ON THE N2 WILD COAST ROAD ... (balanced cantilever construction) & box girder ... Slide 1 Author: Tshivhangwaho Mudau
Page 25: UPDATE ON THE N2 WILD COAST ROAD - SLR … · UPDATE ON THE N2 WILD COAST ROAD ... (balanced cantilever construction) & box girder ... Slide 1 Author: Tshivhangwaho Mudau

Search and Rescue Activities - Simply Enviro JV

Site establishment:

Fencing and clearing of site camp area

Lay down of storage containers and offices in progress

Chemical toilets were delivered

Some construction vehicles (TLB and excavators) had

been delivered

Page 26: UPDATE ON THE N2 WILD COAST ROAD - SLR … · UPDATE ON THE N2 WILD COAST ROAD ... (balanced cantilever construction) & box girder ... Slide 1 Author: Tshivhangwaho Mudau
Page 27: UPDATE ON THE N2 WILD COAST ROAD - SLR … · UPDATE ON THE N2 WILD COAST ROAD ... (balanced cantilever construction) & box girder ... Slide 1 Author: Tshivhangwaho Mudau

No public complaints have been received

No Non-Conformances have been raised for this project

to date

No major incidents have been recorded

Page 28: UPDATE ON THE N2 WILD COAST ROAD - SLR … · UPDATE ON THE N2 WILD COAST ROAD ... (balanced cantilever construction) & box girder ... Slide 1 Author: Tshivhangwaho Mudau

Search and Rescue for protected species commenced,

and collected in nurseries at both site camps

Topsoil that was removed from the site camps was

being monitored and kept weed free

Environmental Awareness training was conducted

Page 29: UPDATE ON THE N2 WILD COAST ROAD - SLR … · UPDATE ON THE N2 WILD COAST ROAD ... (balanced cantilever construction) & box girder ... Slide 1 Author: Tshivhangwaho Mudau

Taking of water from a water resource

The approved water abstraction points in the NWA

General Authorisation are not accessible and the

Contractors cannot abstract water for construction

purposes

Site and Construction Camp Clearing: Method

Statements

Method statements had been developed, but not

subjected to final approval at the time of the site visits

Page 30: UPDATE ON THE N2 WILD COAST ROAD - SLR … · UPDATE ON THE N2 WILD COAST ROAD ... (balanced cantilever construction) & box girder ... Slide 1 Author: Tshivhangwaho Mudau

Water Pollution Control

Monitoring of aquatic ecosystems shall be undertaken

in accordance with the requirements of the

Supplementary EMP for Aquatic

Baseline Ecological Assessments

Baseline ecological data needs to be collected for

sensitive sites as per the requirements of the Aquatic

EMP

Page 31: UPDATE ON THE N2 WILD COAST ROAD - SLR … · UPDATE ON THE N2 WILD COAST ROAD ... (balanced cantilever construction) & box girder ... Slide 1 Author: Tshivhangwaho Mudau

Access Requirements

The contractor has indicated that construction of an

access road may be required for Msikaba South, these

roads may be outside of the haul road alignment.