update on electronics integration m.morel ph-ese-fe 03 june 2014
DESCRIPTION
Update on electronics integration M.Morel PH-ESE-FE 03 June 2014. RX and TX cards Schedule integration Summary. RX and TX cards Schedule integration Summary. RX and TX cards. We received one RX and TX card made in Fr4 from CERN workshop - PowerPoint PPT PresentationTRANSCRIPT
Update on electronics integration
M.MorelPH-ESE-FE
03 June 2014
Update on Electronics integration M.Morel 26/3/2014
• RX and TX cards• Schedule integration• Summary
Update on Electronics integration M.Morel 36/3/2014
• RX and TX cards• Schedule integration• Summary
Update on Electronics integration M.Morel 4
• We received one RX and TX card made in Fr4 from CERN workshop• Short circuit discovered in the internal layers of the RX card. Other bad soldering
contacts and wrong side soldering (have been repaired).• Four other RX and TX cards in Nelco material are following (next week)• The test of the RX and TX cards could start soon.
6/3/2014
RX and TX cards
Update on Electronics integration M.Morel 56/3/2014
RX
TX
RX and TX cards
Update on Electronics integration M.Morel 66/3/2014
• RX and TX cards• Schedule integration• Summary
Update on Electronics integration M.Morel 7
SMD assemblies
First electronic
tests without sensor
assembly
Gluing FlangesSensor
AssembliesForecasting
Integration of the cooling plate equipped
with the sensor assembly
Functional tests in the
Lab
Integration in the Vessel
GTK_carrier1 16/06 – 20/06 23/06 – 23/06 21/07 – 28/07 01/07 29/07 - 31/07 18/08 - 22/08 01/9 – 05/09
GTK_carrier2 16/06 – 20/06 30/06 – 04/07 21/07 – 28/07 18/08 20/08 - 21/08 08/09 – 12/09 22/09 – 26/09
GTK_carrier3 16/06 – 20/06 07/07 – 11/07 21/07 – 28/07 18/08 28/08 - 29/08 16/09 – 19/09 01/10 – 10/10
Schedule Integration
6/3/2014
Full schedule details: https://indico.cern.ch/event/318934/
• According to ELTOS company the delivery time of the GTK_carriers is respected and will be the 16 of June.
Update on Electronics integration M.Morel 86/3/2014
• RX and TX cards• Schedule integration• Summary
Update on Electronics integration M.Morel 96/3/2014
• One RX and TX card are ready for the tests• GTK_carrier boards production continues normally
They will be delivered on June 16.