update on electronics integration m.morel ph-ese-fe 03 june 2014

9
Update on electronics integration M.Morel PH-ESE-FE 03 June 2014

Upload: cianna

Post on 06-Jan-2016

23 views

Category:

Documents


3 download

DESCRIPTION

Update on electronics integration M.Morel PH-ESE-FE 03 June 2014. RX and TX cards Schedule integration Summary. RX and TX cards Schedule integration Summary. RX and TX cards. We received one RX and TX card made in Fr4 from CERN workshop - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Update on electronics integration M.Morel PH-ESE-FE 03 June 2014

Update on electronics integration

M.MorelPH-ESE-FE

03 June 2014

Page 2: Update on electronics integration M.Morel PH-ESE-FE 03 June 2014

Update on Electronics integration M.Morel 26/3/2014

• RX and TX cards• Schedule integration• Summary

Page 3: Update on electronics integration M.Morel PH-ESE-FE 03 June 2014

Update on Electronics integration M.Morel 36/3/2014

• RX and TX cards• Schedule integration• Summary

Page 4: Update on electronics integration M.Morel PH-ESE-FE 03 June 2014

Update on Electronics integration M.Morel 4

• We received one RX and TX card made in Fr4 from CERN workshop• Short circuit discovered in the internal layers of the RX card. Other bad soldering

contacts and wrong side soldering (have been repaired).• Four other RX and TX cards in Nelco material are following (next week)• The test of the RX and TX cards could start soon.

6/3/2014

RX and TX cards

Page 5: Update on electronics integration M.Morel PH-ESE-FE 03 June 2014

Update on Electronics integration M.Morel 56/3/2014

RX

TX

RX and TX cards

Page 6: Update on electronics integration M.Morel PH-ESE-FE 03 June 2014

Update on Electronics integration M.Morel 66/3/2014

• RX and TX cards• Schedule integration• Summary

Page 7: Update on electronics integration M.Morel PH-ESE-FE 03 June 2014

Update on Electronics integration M.Morel 7

SMD assemblies

First electronic

tests without sensor

assembly

Gluing FlangesSensor

AssembliesForecasting

Integration of the cooling plate equipped

with the sensor assembly

Functional tests in the

Lab

Integration in the Vessel

GTK_carrier1 16/06 – 20/06 23/06 – 23/06 21/07 – 28/07 01/07 29/07 - 31/07 18/08 - 22/08 01/9 – 05/09

GTK_carrier2 16/06 – 20/06 30/06 – 04/07 21/07 – 28/07 18/08 20/08 - 21/08 08/09 – 12/09 22/09 – 26/09

GTK_carrier3 16/06 – 20/06 07/07 – 11/07 21/07 – 28/07 18/08 28/08 - 29/08 16/09 – 19/09 01/10 – 10/10

Schedule Integration

6/3/2014

Full schedule details: https://indico.cern.ch/event/318934/

• According to ELTOS company the delivery time of the GTK_carriers is respected and will be the 16 of June.

Page 8: Update on electronics integration M.Morel PH-ESE-FE 03 June 2014

Update on Electronics integration M.Morel 86/3/2014

• RX and TX cards• Schedule integration• Summary

Page 9: Update on electronics integration M.Morel PH-ESE-FE 03 June 2014

Update on Electronics integration M.Morel 96/3/2014

• One RX and TX card are ready for the tests• GTK_carrier boards production continues normally

They will be delivered on June 16.