Sound Transit Board Meeting August 22, 2013
University Link Project Briefing
• 3.15-mile extension of Central Link – twin bored tunnels – Capitol Hill Station – UW Station and crossover
• Schedule: – Final Design: 2007-2010 – Construction: 2009-2016 – System testing: 6 months – Open for service: Fall 2016
• Project budget: $1.948 billion (including finance cost)
2 2
Project Snapshot
2
Financials as of July 2013
• Awarded construction contracts exceed $909 million • Active work on two heavy civil contracts, two station finishes
contracts (UWS and CHS), the rail/systems contract ,and a fiber retrofit contract
• Estimated Final Cost (EFC) trending approximately $107M under Project Budget
Financial Snapshot Millions
Project Budget $1,948
Committed $1,569
Incurred $1,191
3
Financial Snapshot
3
• Presently, Project is approximately 75% complete overall • Sound Transit’s Revenue Service Milestone remains
September 24, 2016 • Project schedule contains 169 days of project-wide float
4
Schedule Snapshot
4
• Four major heavy civil contracts – I-5 Undercrossing Pits – UW to Capitol Hill – Capitol Hill to Pine Street – Yard Expansion
• Two major station finishes contracts – UW Station (GC/CM) – Capitol Hill Station (GC/CM)
• Three major systems/track contracts – U-Link Systems and Track (GC/CM) – Network – EMI/Vibration/Wheel Flat Monitoring
• Maintenance of Way Building • Procurement of light rail vehicles
Complete Active Pending
5
Implementation
5
MOW Bldg
AIRPORT WAY
Maintenance of Way Building
STOR
AGE
6
7
Capitol Hill Station to Pine Street Stub Tunnel
7
Permanent Track Installation
8
9
49’-5”
55’-0”
9
JOH
N
N
BROADWAY Capitol Hill Station
9
10
Capitol Hill Station
10
11
Capitol Hill Station
11
University of Washington Station to Capitol Hill Station
12
Rail Installation
13
14
University of Washington Station
University of Washington Station
15
University of Washington Station
16
Pedestrian bridge and bike path
17
Montlake Triangle Project
University of Washington Station
18
Top Five Risks • Civil to Civil Contract Interface • Civil to Systems Contract Interface • Systems Long Lead Item • Software Development • Systems Final Design, Installation, Testing and Rail
Activation (Systemwide)
19