undulator vacuum system
DESCRIPTION
Undulator Vacuum System . Geoff Pile, Dean R. Walters, Soon-Hong Lee, James Bailey, James Morgan, Dana Capatina , Scott Doran, ANL. Undulator Vacuum System . Undulator Vacuum Chamber Support Status Production Schedule Bellows Module Testing: Combined Offset test and Surface Measurement - PowerPoint PPT PresentationTRANSCRIPT
October 30, 2007Undulator Breakout
1 Dean R. Walters
Undulator Vacuum System Vacuum System
Geoff Pile, Dean R. Walters, Soon-Hong Lee, James Bailey, James Morgan, Dana Capatina, Scott Doran, ANL
October 30, 2007Undulator Breakout
2 Dean R. Walters
Undulator Vacuum Chamber SupportStatusProduction Schedule
Bellows ModuleTesting: Combined Offset test and Surface MeasurementProduction Plan
Quadrupole SpoolDesignProduction Schedule
Long Break SpoolsStandard Spool DesignSpools with Sector ValveProduction Plan
Beam Finder WireStatus of ProductionModification to ChamberProduction Schedule
All Metal Chain Clamp Vacuum SealTesting Results
Undulator Vacuum System Vacuum System
October 30, 2007Undulator Breakout
3 Dean R. Walters
Undulator System LatticeL14-200000
SA-381-003-01
Undulator CELLL14-501000
SA-381-003-03
Girder AssemblyL143-010000
SA-381-003-04
Support Mover SystemL14-401000
SA-381-006-24
Girder WeldmentL1430401-100396
SA-381-002-76
Pedestal AssemblyL1430802-200000
SA-381-010-50
Girder WeldmentL1430401-100396
SA-381-002-76
UndulatorL143-112000
SA-381-001-35
BFW AssemblyL14506-110000SA-381-007-96
Quad AssemblyL1430501-100394
SA-381-012-74
RFBPM AssemblyL1450503-100000
SA-381-008-70
Vacuum ChamberL1440202-200000
SA-381-0XX-XX
WPM-WLSL-
MO-381-901-13
Control AssemblyL142-100060
SA-381-011-28
BFW SupportL14506-112000SA-381-013-25
Quad SpoolL14405-117000SA-381-013-97
RFBPM SupportL14505-104000SA-381-014-39
RFBPM ReceiverL1450501-310000
SA-381-011-80
Bellows ModuleL14403-110000SA-381-0XX-XX
Ion PumpL14405-104000SA-381-013-40
Long BreakVacuum Spool
L14406-111000SA-381-014-70
Long Break IsoVacuum Spool
L14406-112000SA-381-014-81
Long Break Diag.Vacuum Spool
L14406-116000SA-381-0XX-XX
October 30, 2007Undulator Breakout
4 Dean R. Walters
Sub-Assemblies in the Undulator Vacuum System
Beam Finder Wire
Ion Pump
RF Beam Position Monitor
Quadrupole Magnet
RF BPM Waveguide
Vacuum Chamber and Support
Wire Position Monitor
RF BPM Electronics
Bellows Module
Girder
Undulator Magnet
October 30, 2007Undulator Breakout
5 Dean R. Walters
Tubing Support Structure Production Status
Awarded to Walco Tool & Engineering (July, 2007).Tubing material was changed to Aluminum 6061-T6 from Steel due to a magnetic material risk. (August, 2007)Raw material was ordered in Sept. 2007 and was arrived at the vendor. (Oct. 18, 2007)A first article is being fabricated to reduce the risk. After rough machining, the tubing will be vibration stress relieved.Two weeks lead-time from the painter.One week for final machining and assembly.
October 30, 2007Undulator Breakout
6 Dean R. Walters
Production ScheduleFirst Article Inspection
Support tubing will be inspected before starting the machining of remaining 36 assemblies.Expect in the week of November 19th, 2007.Within 2 weeks after inspection, APS will allow the vendor to cut the remaining materials.
Production completionLead time: 8 weeks after the first article inspection.First Unit complete 12/10/2007Completion of remaining 36 assemblies: Week of Feb 4th, ’08.Will be directly sent to SLAC from the vendor.
Shipping CarriersCo-worked with Pak-Rite Ltd. to design
the “Sure-Lok” shipping carrier.10 carriers were delivered to Walco (Sept. 07)
October 30, 2007Undulator Breakout
7 Dean R. Walters
Bellows Module Design
Travel length Lateral offset Bellows length Angular
Extended +6.5 mm 5.08 mm 1.69 inch
Installed 0 mm 3.56 mm 1.43 inch
Compressed - 6.5 mm 2.03 mm 1.17 inch 35 without flange ends
Outer bellows assemblyEVAC flange with copper gasket and chain clampsRemovable tie rods for restraints to prevent damagesTravel Distance of a welded bellows (200-125-3-EE)
Internal pipe assembly Inner pipe assembly with ID 10 mm x OD 12 mm x ~ 68 mm long pipe/tubeNo finger assembly for electric conductivityGap in the Bellows will be of 7.8 mm +/- 6.5 mmPipe axis in the Bellows will be aligned to the Undulator within +/-100 m.
October 30, 2007Undulator Breakout
8 Dean R. Walters
Surface finish measurement - Internal pipe ID 10 mm pipes were honed for 2, 4, and 8 -inch Ra finish.Roughness data after 2nd degree LMS fitting (polynomial data fitting line to line) show that either 2 -inch Ra or 4 -inch Ra honing process works fine. RMS slope analysis shows that 2 -inch Ra is preferred and that 4 -inch Ra is marginal.
Sample 2Ra Sample 4Ra Sample 8Ra
Samples
October 30, 2007Undulator Breakout
9 Dean R. Walters
Bellows Tests and Results Original Tests (DCN 14403-0001).
Focused on internal sliding parts (RF and Spring Fingers).±2 mm X-Y offset with 0.5°angular offset x 2000 cycles.Tests were completed. Internal parts met specification.
Sliding internal parts no longer used. New tests focused on maximum possible rotational and X-Y offset.
Flange rotation of ±~ 0.8° is possible with < 75 in-lb of torque. 2000 cycles were run. Leak check showed no leaks.X-Y offset of ±10 mm is possible with ~ 10 lb of force. 2000 cycles were run. Leak check showed no leaks.
Further motion analysis showed rotational and X-Y offset may be simultaneously possible, but very unlikely.
Flange rotation of ~ 0.8° plus X-Y offset of ±9 mm is possible without permanently deforming the bellows. 50 cycles were run. Leak check showed no leaks.
October 30, 2007Undulator Breakout
10 Dean R. Walters
Production StatusOuter bellows assembly
Edge-welded Bellows were received from Standard Bellows Company.Welded flange (flange + adapter)
EVAC flange and its hardware were received from EVAC Inc.Weld shrinkage of the flange sealing diameter must be compensated.Drawings and SOW for production are complete.Lead time 6 weeks for the 1st articles (2 ea), 8 weeks for the remaining balance.
Flange with weld-neckExpect less shrinkage, but flange delivery for production will take 7 weeks ARO.4 custom-flanges with weld-neck will be weld tested.
Internal pipe assembly Drawings and SOW for production are complete.Internal surface finishing process is being tested.
Honing process was done. (honing oil - Perkins 284) Vacuum cleaning-baking-RGA process is on progress.
Lead time 3 weeks for the 1st articles (2 ea), then 3 weeks for the remaining balance.Production Schedule
First Articles complete on 1/31/200835 completed units on 3/25/2008
Weld Bead
October 30, 2007Undulator Breakout
11 Dean R. Walters
Short Break Sub-Assembly
BFWUndulator
Undulator
Beam
GirderGirder
RF BPMQuadrupole
Magnet
October 30, 2007Undulator Breakout
13 Dean R. Walters
Quad Spool Redesign and Production Schedule
New Requirements from Short Break Test“Driveshaft” design with a small bellows on each end.±0.15° angular offset possible at each end.0.03” compression possible at both ends.“Driveshaft” design allows X-Y offset > allowable from Quad.
Production ScheduleDesign complete. All parts and fabrication on order. Small bellows delivery is driving the schedule. Bellows delivery scheduled for 11/7.Ship bellows and flanges for first three units on 11/10 to AES for laser welding and post welding electro-polish.Ship bellows to Alumiplate for interior aluminum plating.First three units are scheduled for completion on 12/1.If no design/QA problems are encountered, two additional production runs of 17 pieces each should be completed by 1/31.
October 30, 2007Undulator Breakout
16 Dean R. Walters
Long Break SpoolWith Pump Down Valve
and Sector Valve
October 30, 2007Undulator Breakout
17 Dean R. Walters
BFW Assembly Mounted on Adjustable Support
Adjustable Mounting Support
Vacuum Pump Connector (2.75” Conflat Flange)
Card Position Monitor (Limit switches)
Air Supply Shut Off Valve
Pneumatic Solenoid Valve
Precision Screw
Electrical Connectors for Wire Signals
Vacuum Chamber Connection Flange
(NW-50 CeFix w/Clamp)
Beam Port
Pneumatic Cylinder
Alignment Fiducials
Frame
Compression Spring Positioner
Potentiometer
Housing
October 30, 2007Undulator Breakout
18 Dean R. Walters
StatusCatalog Items– Delivery CompleteMachined Parts– Delivery CompleteShaft Frame Weldment– First Article Delivered and Approved by ANLBFW Vacuum Chamber– Contract Awarded. Delivery of 1st Lot within 5 weeksStarted Assembly of First Article at ANLAssembly and Alignment Procedures— Completed DraftVacuum Test and Bake-out Procedures– Completed DraftIn Field Alignment Procedure– Conceptually PlannedDeliverables Drawing– Completed Draft
October 30, 2007Undulator Breakout
19 Dean R. Walters
Significant IssuesCurrently developing electrical interfaces with control groupNeed to develop pneumatic interfaceNeed to develop wire signal interfaceNeed to develop protection cover strategyComplete Assembly and Testing of the First ArticleModified beam tube to accommodate new BLM designModifed Ion Pump connection to allow space for BLM Wire Card Installation
Schedule for Completed BFW Assemblies w/ Supports to SLAC
Deliver 1st Lot (3) --- 12/12/07Deliver 2nd Lot (10) --- 1/14/08Deliver 3rd Lot (10) --- 2/11/08Deliver 4th Lot (14) --- 3/20/08
October 30, 2007Undulator Breakout
20 Dean R. Walters
All Metal Chain Clamp Vacuum Seal
October 30, 2007Undulator Breakout
21 Dean R. Walters
Short Break Test System System
1
2 3 4 5O-ring seal on hose to
leak detector
October 30, 2007Undulator Breakout
22 Dean R. Walters
Test ProcedureInitial tests (number #1-14) were conducted on individual seals to work out assembly technique.
Copper seals were used in tests #1-5Aluminum seals were used in tests #6-10
Step #1 installed gasket at 60 in-lbStep #2 Leak checkStep #3 increase torque 75 in-lbStep #4 Leak checkStep #5 If it still leaks replace gasket and repeat steps #1-4
Second round tests (number #15-27)In this set of test all five gaskets were replaced using 75 in-lb of torqueIn reporting the results only the leaks were noted.Background of the leak detector was equal or lower that 1 X 10-10 mbar-lit/sec of heliumLeaks were defined as any reproducible meter deflection on any scale.On test #18 the entire assembly was helium bagged for 10 minutes without any leak detector response. The results of the bagging of test #27 are shown in a later slide.
October 30, 2007Undulator Breakout
23 Dean R. Walters
Test ResultsTest Log Bood
Seal Mat'l No. No. Seal #1 Seal #2 Seal #3 Seal #4 Seal #5Friday Copper 1 Ok Ok Ok Leak OkFriday Copper 2 OK Cu - not rplc OK Cu - not rplc OK Cu - not rplc Leak new chain OK Cu - not rplcFriday Copper 3 OK Cu - not rplc Leak Leak OK OK Cu - not rplc Initial Failure RateFriday Copper 4 NA Leak Leak NA NA 46.2%Friday Copper 5 NA NA OK OK OK Cu - not rplc
Saturday Aluminum 6 1 NA NA Leak Leak OK Cu - not rplcSaturday Aluminum 7 2 NA NA Leak Leak OK Cu - not rplcSaturday Aluminum 8 3 NA NA Leak Leak OK Cu - not rplcSaturday Aluminum 9 4 NA NA Leak Leak OK Cu - not rplc
Monday Aluminum 10 NA NA Leak Leak OK Cu - not rplcMonday Aluminum 11 NA NA Leak Leak OK Cu - not rplcMonday Copper 12 NA NA OK OK OK Cu - not rplcMonday Aluminum 13 NA NA Leak OK - Cu OK Cu - not rplcMonday Copper 14 OK Cu - not rplc OK OK Lk OK Cu - not rplc
Tuesday Copper 15 1 B1 OK - New chainTuesday Copper 16 2 Lk - bellows B1 flgTuesday Copper 17 3 Lk - bellows B1 flgTuesday Copper 18 4 replc w/ B2Tuesday Copper 19 5 B2Tuesday Copper 20 6 B2Tuesday Copper 21 7 B2
Wednesday Copper 22 8 B2Wednesday Copper 23 9 B1Wednesday Copper 24 10 B1Wednesday Copper 25 11 Leak Leak B1 LeakWednesday Copper 26 12 Ok - new chain Ok - new chain B1 Ok - new chainWednesday Copper 27 13 B1
15 15 24 1 142 2 12
112
Failure rate in the formal test65 5
7.7%
No. of Times the Chains are used:
October 30, 2007Undulator Breakout
24 Dean R. Walters
Transportation TestMoved assembly onto hard wheel roller cartRolled around APS ringProbe leak check
No leaks at 5 X 10-11Bagged the assembly
After 7 minutes a rise was notedAt 10 minutes leak rate rose to 5 X 10-10Loose tape seal around bag could be evidence of permeability of vacuum hose o-ring.
October 30, 2007Undulator Breakout
25 Dean R. Walters
Induced Deflection Test & Aluminum GasketsSet-up
This is a test where a known leak tight assembly has a single component shifted 2 mm (.08”) and then re-leak checked.
Three test were performedEach with a new gaskets to the component which in this case is the RFBPMThe assembly was leak testedThe component was moved 2 mm
Test #1 it was moved 2 mm in X directionTest #2 it was moved 2 mm in Y directionTest #3 it was moved -2 mm in Y direction
The assembly was leak checked again after movingIn all cases the assembly was leak free.
Transportation TestAt the end of Test #1 the assembly was rolled around the APS ring, greater than 1 km, and then leak checked one more time, no leaks.
ALUMINUM GASKETSEVAC supplied replacement gaskets to replace the initial setTested 15 standard thickness gaskets, 2.17 mm, torqued to 39 in-lbs finding no leaksTested 5 extra thick gaskets, 2.36 mm, and were successful in 4 of 5.These tests were conducted with Dicronite dry lubricant on the chains.In further testing Armoloy XADC lubricated chains will be tried.