ukraine-israel.comukraine-israel.com/.../uploads/2019/04/dna-march-2019.docx · web viewservices of...
TRANSCRIPT
Monthly report March 2019Building of a residential complex with built-in trading office premises on 100-A Vasylkivska street, in the Holosiivskyi district of Kyiv
Building of the multifunctional complex on 100-A Vasylkivska street, in the
Holosiivskyi district of Kyiv.
Section BMonthly report march 2019
"29 th» March 2019
Director LLC "DNA VIP __________ David Maor
Ukraine01034. Kyiv1-D Skovoroda st.LLC "DNA VIP"Tel: +38 (044) 257-30-59Fax: +38 (044) 257-30-27e-mail: [email protected]
Monthly report March 2019p. 1 of 15
Monthly report March 2019Building of a residential complex with built-in trading office premises on 100-A Vasylkivska street, in the Holosiivskyi district of Kyiv
Contents
1 Introduction Рage 32 Provided service Page 33 P. 2.1.1 and 2.1.5. Control over violation of the requirements of the agreed and
approved project documentation. Technical supervision of a construction.Page 4-10
4 P.2.1.7. Verification of the presence of documents which confirm qualitative characteristics of a structure, products, materials and equipment.
Page 7
5 P.2.1.10. Control over the maintenance of the general log of the construction works
Page 7
6 P.2.1.4. Control over the compliance of safety regulations during the construction. Page 87 P.2.1.2. The degree of the construction's facility readiness. Page 8-12
Monthly report March 2019p. 2 of 15
Monthly report March 2019Building of a residential complex with built-in trading office premises on 100-A Vasylkivska street, in the Holosiivskyi district of Kyiv
1. Introduction
Services of the technical supervision of the construction of a residential complex with built-in
trading and office premises, situated on the 100-A Vasylkivska street, in the Holosiyivsky district of
Kyiv according to the contract "About the provision of technical supervision services, respectively" to
the requirements of the current legislation of Ukraine.
2. Provided service
The process of execution of work on the construction site was planned on the basis of the schedule of
execution of works (Appendix No. 1 to the contract of the general contract, developed in аugust 2017).
2.1.1. Control of quality. Control over violation of the requirements of the agreed and approved
project documentation, construction norms, rules, standards and specifications, approved project, the use
of substandard building materials, structures, products.
2.1.2. The Construction readiness degree and determination of degree of backlog of the planned deadlines
for the completion of the relevant construction stage specified in the project documentation and
construction schedule, by providing the Customer with conclusions.
2.1.4. Control over the compliance of safety regulations during the construction, provided by the State
construction regulations and rules of Ukraine.
2.1.5. Technical supervision of the construction in accordance with the requirements of the approved
design documentation;
2.1.7. Verification of the availability of documents which confirm qualitative characteristics of structures,
products, materials and equipment used during the construction - technical passports, certificates,
documents that reflect the results of laboratory tests, devices and technologies in accordance with the
design documentation, legislation and boundary indicators of works cost.
2.1.9. Controlling measurements, carried out at the time of inspection by the state supervisory bodies and
departmental inspections, as well as the independent conduct of control measurements of performed
work;
2.1.10. Control over the maintenance of the general log of the construction works of the standard sample
Monthly report March 2019p. 3 of 15
Monthly report March 2019Building of a residential complex with built-in trading office premises on 100-A Vasylkivska street, in the Holosiivskyi district of Kyiv
P. 2.1.1. and 2.1.5. Control of quality. Control over violation of the requirements of the agreed and
approved project documentation, construction norms, rules, standards and specifications,
approved project, the use of substandard building materials, structures, products. Technical
supervision of the construction in accordance with the requirements of the approved project
documentation.
Ventilation and heating networks.
According to sections WS and HW from 03.01.1 9 till 03.28.1 9 .
1. Quality control of air conditioner and boiler drainage networks in bathrooms on 3rd, 17th, 20th,
21st and 22ndfloors of block “B”.
Works are completed according to the project.No remarks.
2. Quality control bathroom floors base hydro isolation on 17th, 20th, 21st and 22nd floors of block
“B”.
Works are completed according to the project.No remarks.
3. Quality control of water supply networks in bathroomson3rd, 12th, 17th, 20thand 21st floors of
block “B”.
Works are completed according to the project.No remarks.
4. Quality control of air conditioners drainage networks in apartments on 3rd, 4th, 11th, 14th, 15th
and 23rd floors of block “B”.
Works are completed according to the project.No remarks.
5. Quality control of air conditioners drainage networks connection to sewage in apartments on
8th, 9th, 11th, 13th, 14th, 15th, 16th, 18th and 29th floors of block “B”.
Works are completed according to the project.No remarks.
Monthly report March 2019p. 4 of 15
Monthly report March 2019Building of a residential complex with built-in trading office premises on 100-A Vasylkivska street, in the Holosiivskyi district of Kyiv
Finishing work.
Quality control of floor creed.
Work is completed at marks:
+12.050; +15.050; +21.050; +24.050; +30.050; +33.050; +36.050; +39.050; +42.050; +45.050; +48.050;
+51.050; +54.050; +57.050; +60.050; +63.050; +66.050; +69.050; +72.050
Works are completed according to the project.
No remarks.
Quality control of plastering works (apartments + places for common use).
Work is completed at marks:
+12.050; +15.150; +18.150; +21.150; +24.150; +30.150; +33.150; +36.150; +39.150; +42.150; +45.150;
+48.150; +51.150; +54.150; +57.150; +60.150; +63.050; +66.050; +69.050; +72.050;
Works are completed according to the project.
No remarks.
Quality control overlaying plates, putty.
The work is carried out by the marks:
+15.150; +18.150; +21.150;+24.150; +27.150;+30.150; +33.150; +36.150; +39.150; +42.150;
+45.150+48.150; +51.150; +54.150; +57.150; +60.150; +63.050; +66.050; +69.050; +72.050;
Works are completed according to the project.
No remarks.
Works on the device of warming and decorative finishing of a facade are carried out.
Quality control. Works are carried out at the following markings:
+12.050; +15.150; +18.150; +21.150; +24.150; +30.150; +33.150; +36.150; +39.150; +42.150; +45.150;
+48.150; +51.150; +54.150; +57.150; +60.150; +63.050; +66.050; +69.050; +72.050;
Installation of entrance doors to the apartments.
Quality control. Work is completed at marks:
+15.150; +18.150; +21.150;+24.150; +27.150;+30.150; +33.150; +36.150; +39.150; +42.150; +45.150;
+48.150; +51.150; +54.150; +57.150; +60.150; +63.050; +66.050; +69,050; +72,050.
Works are completed according to the project.
Monthly report March 2019p. 5 of 15
Monthly report March 2019Building of a residential complex with built-in trading office premises on 100-A Vasylkivska street, in the Holosiivskyi district of Kyiv
No remarks.
Installation of doors at the exits to the balcony cold transition
Quality control. Work is completed at marks:
+12.050; +15.150; +18.150; +21.150; +24.150; +30.150; +33.150; +36.150; +39.150; +42.150; +45.150;
+48.150; +51.150; +54.150; +57.150; +60.150; +63.050; +66.050; +69.050; +72.050;
Works are completed according to the project.
No remarks
Works on the installation of fencing balconies
Quality control. Work is completed at marks:
+12.050; +15.150; +18.150; +21.150; +24.150; +30.150; +33.150; +36.150; +39.150; +42.150; +45.150;
+48.150; +51.150; +54.150; +57.150; +60.150; +63.050; +66.050; +69.050; +72.050;
Works are completed according to the project.
No remarks.
Installation work on low-voltage systems.
Quality control. Work is completed at marks:
+12.050; +15.150; +18.150; +21.150; +24.150; +30.150; +33.150; +36.150; +39.150; +42.150; +45.150;
+48.150; +51.150; +54.150; +57.150; +60.150; +63.050; +66.050; +69.050; +72.050;
Works are completed according to the project.
No remarks.
Electric networks and lightning protection
Quality control. Work is completed at marks:
+12.050; +15.150; +18.150; +21.150; +24.150; +30.150; +33.150; +36.150; +39.150; +42.150; +45.150;
+48.150; +51.150; +54.150; +57.150; +60.150; +63.050; +66.050; +69.050; +72.050;
Works are completed according to the project.
No remarks.
Installation of elevators
Quality control
Completed installation of all elevators (two KONE elevators and one Doppler elevator). Preparation of
elevators for commissioning, experimental operation.
Works are completed according to the project.
No remarks.
Monthly report March 2019p. 6 of 15
Monthly report March 2019Building of a residential complex with built-in trading office premises on 100-A Vasylkivska street, in the Holosiivskyi district of Kyiv
Apartments are completed with furniture, interior items, lamps, washbasins, toilet bowls, mixers
tap /
Monthly report March 2019p. 7 of 15
Monthly report March 2019Building of a residential complex with built-in trading office premises on 100-A Vasylkivska street, in the Holosiivskyi district of Kyiv
Monthly report March 2019p. 8 of 15
Monthly report March 2019Building of a residential complex with built-in trading office premises on 100-A Vasylkivska street, in the Holosiivskyi district of Kyiv
Finishing works and furnishing of the lobby are carrier out.
Monthly report March 2019p. 9 of 15
Monthly report March 2019Building of a residential complex with built-in trading office premises on 100-A Vasylkivska street, in the Holosiivskyi district of Kyiv
P.2.1.7. Verification of the presence of documents which confirm qualitative characteristics of a
structure, products, materials and equipment, which are used during building of the facility, such
as technical passports, certificates, documents that reflect the results of laboratory tests, devices
and technologies in accordance with the design documentation, legislation and boundary indicators
of works cost. The quality of reinforcing products and concrete mix is controlled constantly as well as
laboratory analyses of materials. The quality of materials and products meets all necessary regulatory
acts, state standards passports, certificates.
P.2.1.10. Control over the maintenance of the general log of the construction works of the standard
sample. Verification of the necessary records in works logs, author's supervision monitoring ,
availability of necessary licenses;
The logs of author's supervision,production works, concrete, welding and joint works are being
conducted, there are no remarks.
P.2.1.4. Control over the compliance of safety regulations during the construction, provided by the
State construction regulations and rules of Ukraine.
The perimeter of the building's site, the area of production (floors), the work of the tower crane and
the assembly area of the reinforcement frame are fenced. The passages of the elevator's shafts are closed,
the overlap is installed in the mines.
Monthly report March 2019p. 10 of 15
Monthly report March 2019Building of a residential complex with built-in trading office premises on 100-A Vasylkivska street, in the Holosiivskyi district of Kyiv
All builders work in protective helmets, vests, belts and overalls. All floors are cleaned, staircases
are fenced, the construction site is in good condition. Toilets are installed in the construction camp and on
the upper floors of building; containers for household and solid construction waste are provided as well as
their regular export.
Logs of operational control over the state of occupational safety, registration of instructions on the
safety of work in the workplace, instructions for the right of movement of goods by a base and a screw
crane, the issuance of safety devices and personal protective equipment, periodic inspection of removable
load grip devices and containers, are kept. Logs of operational control over the state of occupational
safety, registration of instructions on the safety of work in the workplace, instructions for the right of
movement of goods by a tower crane, the issuance of safety devices and personal protective equipment,
periodic inspection of removable devices and containers
are conducted. There is no remarks.
Fire safety of the construction camp. The register of instructions about fire safety is conducted.
Warehouses are equipped with extinguishers, fire-prevention shields are completed, "Instructions about
fire safety in office and household premises" are present. The condition of electrical networks in premises
which were mentioned earlier is normal. All house hold premises are grounded.
Conclusions of the section: In general, the quality of performed works corresponds to the
working project and operating norms, measures for the protection of labor and industrial
sanitation on the construction site in proper condition.
P.2.1.2. The construction readiness degree and determination of degree of back log of the
planned deadlines for the completion of the relevant construction stage, specified in the project
documentation and constructions chedule, providing the customer with conclusions.
General condition of the construction works of a residential complex with built-in trading-office premises on the 100-A Vasylkivska street, in the Holosiivskyi district of
Kyiv, Section B.01.04.2019
№ п.п Stage Maximum Cost
of a stage
Execution for reporting
period:
Execution of a stage on:
Percentage of execution on:
Marh 2019 01.04.2019 01.04.2019
1Preparatory work, temporary
buildings, permits, risk insurance. Gas boiler,
77 944 079,66 0,00 77 944 079,65 100,00
Monthly report March 2019p. 11 of 15
Monthly report March 2019Building of a residential complex with built-in trading office premises on 100-A Vasylkivska street, in the Holosiivskyi district of Kyiv
technical conditions.2 Soil development 250 000,00 0,00 250 000,00 100,00
3 Arrangement of the pile foundation of the house 6 310 500,00 0,00 6 310 500,00 100,00
4 Concrete pile caps and force plate of the building 6 065 280,00 0,00 6 065 280,00 100,00
5 Damp proofing of walls 92 400,00 0,00 92 080,56 99,656 Monolithic frame 33 761 812,50 0,00 33 795 045,25 100,10
7Installation of reinforced
concrete structures (ventilation channels)
3 199 200,00 0,00 3 199 200,00 100,00
8Installation of reinforced
concrete structures (passages of staircases)
550 000,00 0,00 550 000,00 100,00
9 Brick masonry (internal) 5 086 800,00 0,00 5 086 800,00 100,0010 Facade masonry 5 878 125,00 0,00 5 878 125,00 100,0011 Brick masonry of partitions 2 205 000,00 0,00 2 205 000,00 100,00
12 Installation of windows and balcony doors 4 411 875,00 0,00 4 411 875,00 100,00
13 Installation of aluminum stained glass windows 3 630 000,00 0,00 3 630 000,00 100,00
14Plaster works
(apartments+places for common use)
7 361 280,00 0,00 7 361 280,00 100,00
15 The arrangement of a wet facade 5 362 500,00 0,00 4 826 250,00 90,00
16 Arrangement of balcony partitions 1 959 750,00 0,00 1 371 825,00 70,00
17 Networks of heating and ventilation of the house 11 000 000,00 0,00 11 000 000,00 100,00
18Networks of the water supply and sewerage system of the
house10 500 000,00 0,00 9 850 000,00 93,81
19 Floors 3 384 850,00 0,00 3 384 850,00 100,0020 Installation of apartment doors 2 345 000,00 0,00 2 345 000,00 100,00
21 Installation of fire-prevention doors 275 000,00 0,00 275 000,00 100,00
22 Decorating works (apartments) 54 530 712,50 650 000,00 37 594 962,64 68,94
23Decorating works (places for
common using technical buildings elevator halls)
3 818 880,00 572 832,00 1 908 496,00 49,98
24 Roof 831 060,00 0,00 831 060,00 100,0025 Fire alarm system 1 700 000,00 0,00 1 445 000,00 85,0026 Fire alert system 450 000,00 0,00 382 500,00 85,0027 Smoke protection system 3 000 000,00 0,00 3 000 000,00 100,0028 Gas fire extinguishing system 180 000,00 0,00 144 000,00 80,0029 Water fire extinguishing 600 000,00 84 000,00 599 000,00 99,8330 Pump station 1 200 000,00 0,00 1 200 000,00 100,00
Monthly report March 2019p. 12 of 15
Monthly report March 2019Building of a residential complex with built-in trading office premises on 100-A Vasylkivska street, in the Holosiivskyi district of Kyiv
31 Low current networks 3 750 000,00 0,00 2 625 000,00 70,00
32 Electric networks and lightning protection 5 500 000,00 550 000,00 5 225 000,00 95,00
33 Individual heating point 1 and 2 5 000 000,00 0,00 5 000 000,00 100,00
34 Installation of elevator equipment 4 068 414,00 65 000,00 4 064 993,30 99,92
35 Illumination of facades and territory 600 000,00 0,00 0,00 0,00
36 Video monitoring, access, control 1 500 000,00 0,00 0,00 0,00
37 Dispatcher system 250 000,00 0,00 0,00 0,0038 Entrance groups and lobby 4 500 000,00 225 000,00 4 050 000,00 90,00
39 Premises for bicycles and carriages 153 360,00 0,00 0,00 0,00
40 Planting 315 000,00 0,00 0,00 0,0041 Sport ground 121 600,00 0,00 0,00 0,0042 Playground 305 220,00 0,00 0,00 0,0043 Paving shaped elements 530 750,00 0,00 0,00 0,0044 Asphalt 1 155 000,00 0,00 0,00 0,0045 Total 285 633 448,66 2 146 832,00 257 902 202,40 90,29
Conclusions on the section: on the 01 of April 2019, the degree of readiness of the Construction
Facility is 90,29 %, there is no lagging behind the planned deadlines for the completion of the relevant
construction stage specified in the project documentation and construction schedule.
Composed by: _____________ S.Zholtikov
Permit documentation
Monthly report March 2019p. 13 of 15
Monthly report March 2019Building of a residential complex with built-in trading office premises on 100-A Vasylkivska street, in the Holosiivskyi district of Kyiv
Permit for construction work
License for construction work of the contracting entity LLC KDD ENGINEERING http://kdd.ua/uk/#company
Monthly report March 2019p. 14 of 15
Monthly report March 2019Building of a residential complex with built-in trading office premises on 100-A Vasylkivska street, in the Holosiivskyi district of Kyiv
Expert opinion
Monthly report March 2019p. 15 of 15