UCH POWER PROJECT. Electric Service. Colonies, jobs. 586 MW. Scope Of The Project. Financers. Dutch and German banks ABN Amro Deutsche Bank NDFC World Bank IFC Bank of China. MARKET SUMMARY. MARKET SUMMARY(80’S &90’s). 81-91 : 9% & 10.9%. 31,500 GWH . 7100 MV:Cpty. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: UCH POWER PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022081514/568164e8550346895dd7527f/html5/thumbnails/1.jpg)
UCH POWER PROJECT
![Page 2: UCH POWER PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022081514/568164e8550346895dd7527f/html5/thumbnails/2.jpg)
Project beginnin
g
Costing $690 M
586 MW
Dera Murad Jamali
OGDC
low-Btu gas
![Page 3: UCH POWER PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022081514/568164e8550346895dd7527f/html5/thumbnails/3.jpg)
586 MW
Electric Service
Colonies,jobs
Scope Of The
Project
![Page 4: UCH POWER PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022081514/568164e8550346895dd7527f/html5/thumbnails/4.jpg)
Financers
Dutch and German banks
ABN Amro
Deutsche Bank
NDFC
World Bank
IFC
Bank of China
![Page 5: UCH POWER PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022081514/568164e8550346895dd7527f/html5/thumbnails/5.jpg)
![Page 6: UCH POWER PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022081514/568164e8550346895dd7527f/html5/thumbnails/6.jpg)
MARKET SUMMARY
![Page 7: UCH POWER PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022081514/568164e8550346895dd7527f/html5/thumbnails/7.jpg)
MARKET SUMMARY(80’S &90’s)
81-91 : 9% & 10.9%
7100 MV:Cpty
31,500 GWH
600 & 800 MV
Forecasted incr demand :
16,323MV
![Page 8: UCH POWER PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022081514/568164e8550346895dd7527f/html5/thumbnails/8.jpg)
NEED ANALYSIS
Resources indigenous to
Pakistan
Avoiding import of foreign fuel:$2
billion
Agriculture sector nominal consumer electricity(18.2%) :15.8% in 1987 to
1991
![Page 9: UCH POWER PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022081514/568164e8550346895dd7527f/html5/thumbnails/9.jpg)
NEED ANALYSISDemand growth:
9.4%
GDP growth of
6.4%: 1991-92
June 1991: 32% of villages
(electricity)
Higher propensity of
electricity consumption
Demographic and economic
changes
![Page 10: UCH POWER PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022081514/568164e8550346895dd7527f/html5/thumbnails/10.jpg)
![Page 11: UCH POWER PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022081514/568164e8550346895dd7527f/html5/thumbnails/11.jpg)
Imported 34% of energy requirements
![Page 12: UCH POWER PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022081514/568164e8550346895dd7527f/html5/thumbnails/12.jpg)
![Page 13: UCH POWER PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022081514/568164e8550346895dd7527f/html5/thumbnails/13.jpg)
PROJECT Partners
![Page 14: UCH POWER PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022081514/568164e8550346895dd7527f/html5/thumbnails/14.jpg)
PARTICIPANTS
California Energy Company Inc Hawkins Oil & Gas Inc. Hasan Group Kiewit Energy Company Tenaska Inc.
![Page 15: UCH POWER PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022081514/568164e8550346895dd7527f/html5/thumbnails/15.jpg)
LOCATION• Dera Murad Jamali, District
Nasirabad, Balochistan
![Page 16: UCH POWER PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022081514/568164e8550346895dd7527f/html5/thumbnails/16.jpg)
![Page 17: UCH POWER PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022081514/568164e8550346895dd7527f/html5/thumbnails/17.jpg)
ADVANTAGES OF SELECTED SITE
Close to
water
WAPDA’s transmission system
Major
road
system
![Page 18: UCH POWER PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022081514/568164e8550346895dd7527f/html5/thumbnails/18.jpg)
FUEL SUPPLYLow btu gas from UCH
gas field
US.$1.20
• OGDC is the lease operator of Uch gas field
• Per unit price charged by the UCH is
![Page 19: UCH POWER PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022081514/568164e8550346895dd7527f/html5/thumbnails/19.jpg)
FUEL SUPPLY
GAS FROM OGDC
STORED AT PLANT:FIEL
D GATE
GAS PIPELINE IS 66KM
LONG
![Page 20: UCH POWER PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022081514/568164e8550346895dd7527f/html5/thumbnails/20.jpg)
![Page 21: UCH POWER PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022081514/568164e8550346895dd7527f/html5/thumbnails/21.jpg)
FUEL FOR THE START UP & SHUTDOWN
1500,000 GALLONS
Fuel will be trucked to location
![Page 22: UCH POWER PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022081514/568164e8550346895dd7527f/html5/thumbnails/22.jpg)
INTERCONNECTION WITH NATIONAL GRID
Near the 220 KV national grid QUETTA LOAD CENTER LINKED OTHER LOAD
CENTER
![Page 23: UCH POWER PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022081514/568164e8550346895dd7527f/html5/thumbnails/23.jpg)
BENEFITS OF LOW BTU GAS
DISPLACES EQUIVALENT VOLUME OF OIL
FREE FOREIGN ECXHANGE
FAR LOWER IMPACT ON ENVIRONMENT
CONBUSTION RESULT IN LEAST EMISSION OF
POLLUTION
![Page 24: UCH POWER PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022081514/568164e8550346895dd7527f/html5/thumbnails/24.jpg)
MACHINES USED
Gas turbines
Generators
(steam & gas)
Steam turbines
![Page 25: UCH POWER PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022081514/568164e8550346895dd7527f/html5/thumbnails/25.jpg)
![Page 26: UCH POWER PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022081514/568164e8550346895dd7527f/html5/thumbnails/26.jpg)
GENERAL BENEFITS
High therm
al efficie
ncy
Low capital costs
Low environmental impacts
Indigenous fuel
![Page 27: UCH POWER PROJECT](https://reader035.vdocuments.mx/reader035/viewer/2022081514/568164e8550346895dd7527f/html5/thumbnails/27.jpg)
CRITICAL ANALYSIS
& CONCLUSI