txwtr cm at risk presentation manager at... · coy m veach, p.e., ccm vice president freese and...
TRANSCRIPT
CM‐AT RISK VS. DESIGN BID BUILDA T C S O PA TEXAS CASE STUDY ON PROCUREMENT AND
IMPLEMENTATION
September 28, 2010
Acknowledgement
Mike Adams, P.EExecutive Director of Engineering and Utilities
City of Midlothian
Coy M Veach, P.E., CCMVice President
Freese and Nichols, Inc.
David W. Sloan, P.E., BCEESenior Process EngineerFreese and Nichols, Inc.
Bryant Caswell, P.EAssociate
Schrickel Rollins and AssociatesSchrickel Rollins and Associates
Outline
• City of Midlothian, Texas
• Project Delivery Systems (PDS)
• Legislation History in Texas
• CM‐At Risk – Structure, Schedule and Services,– Solicitation and Procurement Process
• CMAR vs.DBB
• Take Away Points
• Questions and AnswersQ
City of Midlothian• Ellis County, Texas
• Population ‐ 16,000 residents
• Strategically located equal distance from Dallas and Fort Worth• Strategically located equal distance from Dallas and Fort Worth –25 miles southwest of Dallas and southeast of Fort Worth
• 2006 Long Range Water Supply and Master Plan – projects population to steadily increase over the next 20 years
• Existing Tayman WTP production capacity of 13.0 MGD
d d• Current water demand is 10.0 MGD
• Projected water demand is 36.5 MGD
Midlothian WTP Project Profile
• The Tayman WTP is completely build‐out
• New WTP to meet future demands and provide redundancy
• Membrane Filtration facility
• FundingTWDB Drinking Water SRF + City Funds = $30 0 M– TWDB Drinking Water SRF + City Funds = $30.0 M
– Engineering = $4.2 M
– Funding Available for Construction = $25.6 M
• Owner Preferences– Maximize local construction participation
– Operators involved in design/pre‐construction phaseOperators involved in design/pre construction phase
– Desire for qualified contractor with experience
• Projected water demand may exceed available capacity in summer fof 2012
Selected Water Treatment Process
Raw WWater Influent
Rapid Mix
Flocculators Sedimentation Basins
TRWD
Basins
Ground Storage Tanks
High Service Pump Station Membranes
UV/Ox
Phase I – 9 MGDPhase II – 18 MGDPhase III 36 MGDPhase III – 36 MGD
Project Delivery Systems
• In‐house design and construction
• Traditional – Design / Bid / Build (DBB)Traditional Design / Bid / Build (DBB)
• Construction Manager Agency (CMA)
• Construction Manager At Risk (CMAR)• Construction Manager At Risk (CMAR)
• Design Build (DB)
• Design / Build / Operate / Transfer (DBOT)• Design / Build / Operate / Transfer (DBOT)
Legislation History In Texas
• 1995 SB‐1 – Largely an education reform bill
• 1997 SB‐583 and 1999 SB‐669 ‐ Provided Guidance1997 SB 583 and 1999 SB 669 Provided Guidance
• 2001 SB‐510 – Counties, Cities and River Authorities but not for “horizontal” constructionnot for horizontal construction
• 2003 HB‐3028 ‐ Revisions
• 2007 HB‐1886 – Authorization for all types of projects2007 HB‐1886 Authorization for all types of projects
Structure and Schedule
OWNER
CMAR
ARCHITECT/ENGINEER
CMAR PRE‐CONSTRUCTIONCMAR PRE‐CONSTRUCTIONG
CM/GCCONSTRUCTION
CMAR CONSTRUCTION
SUBCONSULTANTS
SUBCONTRACTORSSUBCONTRACTORS
Project Schedule
GMPDesignPDR Normal Construction$
$Contractor Selected
Fast Track Construction
Typical CMAR Services
• CMAR assumes the risk of construction
• Providing suggestions on constructability, risk management, and materials during preconstruction.
• Preparing bid packages for the procurement of Subcontractors and Suppliers, including the Membrane Filtration System
• Preparing overall project schedule and updates.
• Preparing Opinion of Probable Construction Costs (OPCC)
• Guaranteeing the construction cost.
Profile of a CMAR Project
• Complex project, difficult to define or subject to change.
• Tight/limited budget or sensitive financial controls
• Tight schedule, fast tracking desired.
• Better risk management desired.g
• Builder selection flexibility
The Midlothian WTP #2 fits this profile
CMAR Project Flow ChartDBB Project Flow Chart
Prepare CMAR RFP. Evaluate andPrepare CMAR
RFP. Evaluate andContract with Architect/
Prepare Preliminary RFP. Evaluate and
Select CMARRFP. Evaluate and
Select CMARArchitect/Engineer
Preliminary Design
Advertising and Bidding
CMAR Bids Project
Components
Complete Final Design
Contract with CMAR for Pre‐Construction
Contract with CMAR for Pre‐Construction
ComponentsServicesServices
Award Contract to Low BidderNegotiate GMP
Enter into Construction Phase Contract
Complete Construction
Solicitation of a CMAR
• Request for Proposal– Scope: Project should be reasonably well defined.
– Selection/scoring criteria
– Experience
h d l– Schedule
– Budget
Other information to support selection of CMAR– Other information to support selection of CMAR
• One or two step selection process required. Midlothian selected the one step processselected the one step process.
One Step/Two Step Process
• One Step Process– All qualification and fees are requested
– Fees include preconstruction, general conditions, bonds, and contingencies
Evaluation based on qualifications and pricing simultaneously– Evaluation based on qualifications and pricing simultaneously
• Two Step ProcessFirst step: Select maximum 5 proposers on the basis of– First step: Select maximum 5 proposers on the basis of qualifications (non‐monetary criteria) only.
– Second step: Request full proposal only from shortlisted proposers.
– Evaluation based on qualifications first, then pricing
Scoring Processff h d f l• One effective method for evaluation is using a scoring
matrix based on weighted criteria and point scale
I iti l i d i d d tl d ith t• Initial scoring done independently and without knowledge of the preconstruction fees
• Owner/Architect/Engineer Due Diligence• Owner/Architect/Engineer Due Diligence– Reviews: Financials stability, personnel and reference checks
• Set up a workshop:• Set up a workshop:– Compile scores
– Open fees and score the last criteriaOpen fees and score the last criteria
– Reevaluate scores based on financials
• Determine if interviews are necessaryetermine if interviews are necessary– Revisit scores based on interviews.
Midlothian CMAR Scores
Guidelines for Interviews
• Short list to top contenders, release the rest.
• Establish a set of standard questions
• For the benefit of the CMAR– Provide adequate time for CMAR to prepare.
ifi b i f h i i– Be specific about expectations for the interview.
– Make the sessions informal and relaxed.
• Set aside time to discuss the collective results after eachSet aside time to discuss the collective results after each interview.
• Document reasons for scoring changes ‐ be able to defend g gscores.
Selection and Contract
• At the completion of interviews– Review and revise scores as necessary
– Make final decision on CMAR for recommendation to Board or City Council
P bli h lt f l ti ithi 45 d• Publish results of selection process within 45 days
• Notify TWDB (funding agency) of recommendation
f h l d f d b• Notify the selected CMAR firm and begin contract execution process
P t ti i b i t t ti• Preconstruction services begins on contract execution date and ends after GMP is established
Proposal Evaluation Flow Chart
CMAR = DBB
• Owner retains design professional as their advocate and trusted advisor.
• Advertisement and solicitation process allows everyone to compete on “Best Value”.
• Includes safeguards of accountability and transparency.
• Price is known before construction begins.
• Single point of responsibility for construction.
• Contractor/Builder is at risk for cost overruns and errors.
CMAR ≠ DBB• Collaborative team with Owner, A/E and CMAR – vested interest
• More control in the selection of Builder/Contractor. Allows negotiations with top ranked firms.
• Costing is “open book” and allows owner to participate in setting price.
• Ability to effectively “fast track” construction.
• Contingency is owned and managed by Owner
CMAR Myths
• No Construction Inspection required
• Less qualified Construction Inspector is acceptableq p p
• No change orders during construction
G t t t i t th O• Greatest cost savings to the Owner
• CMAR projects have shorter schedules
Take Away Points
• Assess the project and determine if alternate delivery is beneficial
• Solicit and procure CMAR in accordance to state rules and regulations
• Owner must provide inspections materials testing and• Owner must provide inspections, materials testing and verification inspections independently of CM
• Bonds are requiredBonds are required
• Specify the point at which the Guaranteed Maximum Price will be set in the RFP.
• CM recommends, Owner selects subcontractors and suppliers.
Questions and Answers