tuvalu outer-islands electrification programme -...
TRANSCRIPT
Tuvalu Outer-Islands Electrification Programme
Mafalu Lotolua
Maritime and Energy Official’s Meeting
Port Vila, Vanuatu, 7-14 December 2016
Good standard of living
Drive some economic activities
Affordable, secure, and reliable
2
13 Major Themes for the TE KAKEEGA III Theme (5) – Falekaupule and Island Development
- “Provide quality service and create more opportunities for development”
Outer-Islands Electrification Programme
Are we making a difference?
3
Extension of Power Supply
In 2000, 3 x diesel generators and LVdistribution network were installed oneach island with 18hrs power supply;and
TEC, fully state owned Enterprise(SOE)responsible for managing and operatingdiesel power stations
3xdiesel generators of totsl176kW
3xdiesel generators of total 176kW
3xdiesel generators of total 176kW
3xdiesel generators of total 176kW
3xdiesel generators of total 176kW
3xdiesel generators of total 208kW
3xdiesel generators of total 1800kW
3xdiesel generators of total144kW
Battery lighting
4
RE Target for Power Generation – 100% by 2020
2-Stated Goals• To generate electricity with 100% renewable energy by 2020 (revised 2015 to 2025), and• To increase energy efficiency on Funafuti (main island) by 30% 5
100% Target
Guided by the RE&EE Master Plan and isdirectly linked to the:
- Tuvalu National SustainableDevelopment Plan (Te Kakeega III),
- Tuvalu National Energy Policy 2009,
- Climate Change Policy (Te Kaniva)
Master Plan has identified the mostpossible proven technologies for Tuvalu tomeet its 100% target.
6
MP Implementation Strategy
60 – 95% - Solar
0 – 40% - Wind
5% - Biodiesel
30% - Energy Efficiency
Cannot achieve 100% renewable energy with ONE Renewable Energy source and needto include other potential PROVEN and MATURED technology, and
Energy Efficiency is also important to avoid additional renewable energy generation.
IS
7
RE Space in Tuvalu
195kW PV mini-grid – 90% (2015) +132kW standby genset
230kW PV mini-grid – 90% (2015) + 132kW standby genset 205kW PV mini-grid – 90%
(2015) + 132kW standby genset
400kW PV mini-grid - 90% (2015) + 132kW standby genseint
70kW PV mini-grid – 50% (2015) + 131kW standby genset
87kW PV mini-grid – 50%(2015) + 131kW standby genset
45kW PV mini-grid –50% (2015) +91kW standby genset
170kW PV grid-connected (2015)
Standalone Home Solar (SHS) System (2017) 925kW PV/200kW wind/1MWh battery
storage (2017/2018)
Amatuku – 8kW PV mini-grid – 2% (2016)
1. e8/Japan Funded
2. Italy Funded
3. NZ Funded
4. EU Funded
5. UAE Funded
6. Finland Funded
7. World Bank Funded
Funafala - Standalone Home Solar (SHS)System (2017)
MSS – 46kW PV mi-grid –40% (2009)
500kW PV grid-connected (2015)
20/66kW PV grid-connected (2008/2014)
Main Island
8
RE Space in Tuvalu (con’t)No Islands Technology PV Capacity
(kW)Batt(AH)
Standby Gen.(kW)
% RE Status
1 Nanumea Solar PV mini-grid 195 30,000 132 90 Operational
2 Nanumaga Solar PV mini-grid 205 33,000 132 90 Operational
3 Niutao Solar PV mini-grid 230 36,000 132 90 Operational
4 Vaitupu Solar-PV mini-grid 400 60,000 132 90 Operational
>MotufouaSS
Solar PV mni-grid 46 12,000 Feed from village power
40 Operational
5 Nui Solar PV mini-grid 70 15,360 131 50 Operational
6 Nukufetau Solar PV mini-grid 87 18,432 131 50 Operational
7 Nukulaelae Solar PV mini-grid 46 12,228 91 50 Operational
8 Niulakita Standalone Home Solar (SHS) System
0.280 200 Nil 100 1st Quarter 2017
9 Funafuti PV grid-connected 756 Nil 1,800 17 Operational
>Amatuku Solar PV mini-grid 8 2,000 180 4 Operational
>Funafala Standalone Home Solar (SHS) System
0.280 200 Nil 100 1st Quarter 2017 9
Solar Growth in Tuvalu
0
500
1000
1500
2000
2500
3000
3500
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
kW Deployed
Source – TEC
10
Overall Share of Renewable Energy
IMPLEMENTATION STRATEGIES
MASTER PLAN END2014
END 2015/2016
END2017/2018
Solar PV : 60 – 95% 4% 29% 43%
Wind : 0-40% 0 0 2%
Biodiesel : 5% 0 0 0
Energy Efficiency : 30% 0 0 0
11
BAU Vs RE&EE
-
500,000
1,000,000
1,500,000
2,000,000
2,500,000
3,000,000
2012 2014 2016 2018 2020 2022
BAU
REEE Master Plan
• BAU is steadily increasing and with the installation of RE, the dieselconsumption tend to decrease.
• Diesel Saved from January – September, 2016 (9 months period) –~9% ascompared to the same period of 2015.
Lit
ers
12
Challenges
Limited land space available for the development of solar PV
Lack of Natural Resources – predominately solar
Unreliable telecommunication outer islands – for monitoring purposes
Unfrequented service of Government ferry to the outer islands
Capacity Gap
Rely on the donor community and partners for implementation of RE
Lack of finance for replacement of parts
13
Moving Forward
14
Floating PV
Requesting Government to assist with the replacement cost of themajor components of PV equipment
Continue capacity development
Looking for options to improve telecommunication
Tariff review
Where we are now?
98% access rate to quality electricity and 100% by 1st quarter 2017
24/7 power supply
More economic activities
Using electricity wisely
15
Some Innovative ways we install PV modules
Power stationSite for PV
Outer-Island of Nukufetau Reef channel
16
Some Innovative ways to install PV modules (con’t)
In front of the Power Station
Funafuti Island Natural bond - potential for floating PV’s system.
Space can be used for parking/recreation
17
Thank You
18