tso8i 5410.ppt [kompatibilitetstilstand] · lab1 umss sand tawa sema kapi beau keni kuda teno jamb...

16
FIG Working Week 2011 Bridging the Gap between Cultures Marrakech, Morocco, 1822 May 2011 1 GNSS HEIGHTING AND ITS POTENTIAL USE IN MALAYSIA DEPARTMENT OF SURVEY AND MAPPING MALAYSIA Hasan Jamil FIG WORKING WEEK Marrakech WW2011 PRESENTATION OUTLINE Vertical datum and Levelling Background Case Studies Conclusion GNSS Heighting Introduction

Upload: trinhhanh

Post on 11-Apr-2018

217 views

Category:

Documents


1 download

TRANSCRIPT

FIG Working Week 2011

Bridging the Gap between Cultures

Marrakech, Morocco, 18‐22 May 2011 1

GNSS HEIGHTING AND ITS

POTENTIAL USE IN MALAYSIA

DEPARTMENT OF SURVEY AND MAPPING

MALAYSIA

Hasan Jamil

FIG WORKING WEEKMarrakech WW2011

PRESENTATION OUTLINE

Vertical datum and Levelling Background

Case Studies

Conclusion

GNSS Heighting

Introduction

FIG Working Week 2011

Bridging the Gap between Cultures

Marrakech, Morocco, 18‐22 May 2011 2

BRIEF: Malaysia - Morocco

MAP OF MALAYSIA

FIG Working Week 2011

Bridging the Gap between Cultures

Marrakech, Morocco, 18‐22 May 2011 3

MALAYSIA

Land Area: 329,758 square km

Population: 28 million

Climate: Tropical, temperature

from 23 oC - 32 oC

Maritime Area: 603,210 square km

Location: South East Asia

BACKGROUND

Horizontal and verticalcontrol in Malaysia fallsunder Department of Surveyand Mapping

FIG Working Week 2011

Bridging the Gap between Cultures

Marrakech, Morocco, 18‐22 May 2011 4

VERTICAL DATUM AND

LEVELLING IN MALAYSIA

1908 : Earliest Vertical Datum at Port

Klang

1912 : First National Vertical Datum

(LSD)

1967 : First Order Levelling Network

(FOLN67)

1912 : First line levelled from Port Klang

to Kuala Lumpur

VERTICAL DATUM AND

LEVELLING IN MALAYSIA

1984-1993 : Peninsular Malaysia Geodetic

Vertical Datum (10-year tidalobservation)

1985-1999 : Precise Levelling Network

2000 onwards : Upgrading of Precise LevellingNetwork

FIG Working Week 2011

Bridging the Gap between Cultures

Marrakech, Morocco, 18‐22 May 2011 5

PRECISE LEVELLING NETWORK

THAILANDGETING

CHENDERING

TG.GELANG

PULAU

TIOMAN

SEDILI

JOHOR

BAHRU

TG.KELING

PORTKLANG

LUMUT

PULAU

PINANG

PULAU

LANGKAWI

KUALA

LUMPUR

SINGAPORE

KANGAR

NAKA

PADANG

BESARBUKIT

KAYU

HITAM

SIK

ALOR

SETAR

GURUN

BALING

BUTTERWORTH

KG.SUMPITA

N

GERIK

IPOH

BAGAN

SERAI

AYER

TAWAR

SITIAWAN

BEHRANG

SG.BESAR

BENTA

TRANUM

KUALA

KUBU

BENTONG

KARAK

JERANTUT

TEMERLOH

KG.AWAHGAMBANG

KUANTAN

KOTA

BHARU

BANDING

MUADZAM

KERATONG

LEBAN

CHONDON

G

SEGAMAT

AYER KEROH

MELAKA

PEDAS

LINGGI

SEREMBAN

BAHAU

SERTINGKELANG

AYER

HITAM

BATU PAHAT SKUDAI

PONTIAN

KECIL

JEMALUANG

GUA

MUSANG

TIDE GAUGE STATION

LEVELLING NETWORK

JUNCTION POINT

Extent of Precise Levelling Network in Peninsular Malaysia

Conventional Digital (bar coded)Motorised

Methods Of Survey

PRECISE LEVELLING NETWORK (contd.)

FIG Working Week 2011

Bridging the Gap between Cultures

Marrakech, Morocco, 18‐22 May 2011 6

Uses spirit levelling in determination

of orthometric height

Simple and effective but slow

PRECISE LEVELLING NETWORK (contd.)

MALAYSIA GEOID MODEL

Malaysia has established its geoid model

which is known as MyGEOID in 2004 and 2005

Peninsular Malaysia : WMGEOID04

Sarawak and Sabah : EMGEOID05

Peninsular Malaysia

Sabah

Sarawak

FIG Working Week 2011

Bridging the Gap between Cultures

Marrakech, Morocco, 18‐22 May 2011 7

The range of geoidal height value is between -16 m (northern area) to 10 m (southern area)

99 100 101 102 103 104 105

LONGITUDE

PENINSULAR MALAYSIA GEOID

1

2

3

4

5

6

7LATIT

UDE

-24

-22

-20

-18

-16

-14

-12

-10

-8

-6

-4

-2

0

2

4

6

8

10

12

SOUTH CHINA SEA

STRAIT

S O

F M

ALACCA

SCALE BAR ( METER )

PENINSULAR MALAYSIA :

WMGEOID04

MyRTKnet

99.50 100.00 100.50 101.00 101.50 102.00 102.50 103.00 103.50 104.00 104.50

Longitude

ARAU

BABH

BANT

BEHR

GETI

GMUS

GRIK

JHJY

JUML

KLAW

KUAL

KUKP

LGKW

MERS

MERU

PEKN

PUPK

SGPT

TGPG

TLOH

UPMS

USMP

UUMK

AYER

BAHA

BENT

CAME

CENE

GAJA

JRNT

KRAI

KROM

LASA

LIPI

MUAD

MUKH

PASP

PDIC

PRTS

PUSI

SBKB

SEG1

SETI

SIK1

SPGR

SRIJ

TERI

TGRH

TLKI

TOKA

Sabah and Sarawak - 28 stations

110 111 112 113 114 115 116 117 118 119

Longitude (E)

1

2

3

4

5

6

7

La

titu

de

(N

)

UMAS

AMAN

SIBU

BINT

MIRI

LAB1

UMSS

SAND

TAWA

SEMA

KAPI

BEAUKENI

KUDA

TENO

JAMB

TUNKLAHA

SEMP

RANA

KBEL

TEBE

MUKA BELA

MARU

LIMBLAWA

LSEM

MRDU

NIAH

SRTK

RANA

Malaysia has established Malaysia Real-time Kinematic

GNSS Network (MyRTKnet) in 2006 - 2009

Peninsular Malaysia - 50 stations

FIG Working Week 2011

Bridging the Gap between Cultures

Marrakech, Morocco, 18‐22 May 2011 8

GNSS HEIGHTING

Relationship between orthometric height, geoid and ellipsoid

H = h - N

H = Height above geoid (GPS derived orthometric height)

h = Height above ellipsoid (GPS height)

N = geoid-ellipsoid separation, geoid height from gravimetric geoid model (geoidal height)

where:

FLOWCHART OF GNSS HEIGHTING

FIG Working Week 2011

Bridging the Gap between Cultures

Marrakech, Morocco, 18‐22 May 2011 9

Field Procedure

No. Items Parameter

1. Observation

Technique

Static positioning

2. GNSS Control At least 3 stations

3. Observation

Sessions

At least 2 independent sessions

4. Station Connections At least 3 independent baselines

5. VDOP Less than 6 (90% of the

observation session)

6. Elevation Angle Above 10°

7. Satellite Tracking At least 5 satellites with GDOP of

less than 6

8. Equipment

Calibration

As regulated

9. MyRTKnet Usage As regulated

GNSS-DERIVED ORTHOMETRIC HEIGHT -

Recommended Guidelines

Office ProcedureNo. Items Parameter1. General Procedure Prescribed procedures as provided in

manufacturer manual must be followed.2. Datum GDM20003. Ephemerides Short baselines of less than 30 km: Broadcast.

Long baselines: precise.4. Baseline Processing

QualityRMS less than 2 cm.Maximum data rejection - less than 10 %.Ambiguity fixed solution.Aposteriori variance factor is unity.

5. Adjustment Only independent baselines (n-1) should be included in the adjustment.Least square adjustment should be used.

6. Minimally ConstrainedAdjustment

1 control station fixed in GDM2000 coordinates.

7. Quality Indicator Pass Chi-squares test at 95% confident region.All baselines must pass the local test.

8. Test on Control Stations

Relative precision must be less than 2 ppm (2D) and 3 ppm on the vertical component.

9. Over-constrainedAdjustment

At least 2 control stations must be fixed in the final adjustment.

Note: The office procedures are carried out using Trimble Geomatic Office (TGO) software

Recommended Guidelines (contd.)

FIG Working Week 2011

Bridging the Gap between Cultures

Marrakech, Morocco, 18‐22 May 2011 10

CASE STUDIES

Method - either RTK or static technique on BMs

GNSS observation in progress

Results - horizontal positions (lat & long) and verticalpositions (ellipsoidal height)

Compare to the levelling height

CASE STUDY 1

Penang Bridge

GNSS observations with static technique

involving a total number of 3 bench marks (BM)

FIG Working Week 2011

Bridging the Gap between Cultures

Marrakech, Morocco, 18‐22 May 2011 11

RESULTS - CASE STUDY 1

Difference Between GNSS Heighting & Levelling

(cm)

No. of Observation

< 1 3

Peninsular Malaysia

CASE STUDIY 2

GNSS observations with RTK technique involving

a total number of 77 bench marks (BM)

FIG Working Week 2011

Bridging the Gap between Cultures

Marrakech, Morocco, 18‐22 May 2011 12

RESULTS - CASE STUDY 2

Difference Between GNSS Heighting & Levelling

(cm)

No. of Observation &

(%)

< 10 59

(77 %)

10 – 18.8 18

(23%)

BMs observed in Pahang

BMs observed in Johor

BMs observed in Melaka

BMs observed in Selangor

SBMs

BMs observed in Kedah

BMs observed in Perak

BMs observed in Kelantan

BMs observed in Negeri Sembilan

BMs observed in Terenganu

BMs observed in Perlis

0.00 m

-0.3

-0.25

-0.2

-0.15

-0.1

-0.05

0

0.05

0.1

0.15

0.2

0.25

0.3

Total Points Observed

Dif

fere

nt

in m

ete

r

Scatter plot of the difference between Orthometric

Heights Derived GNSS and Levelling

RESULTS - CASE STUDY 2 (contd.)

FIG Working Week 2011

Bridging the Gap between Cultures

Marrakech, Morocco, 18‐22 May 2011 13

Tanjung Malim, Perak

CASE STUDY 3

GNSS observations with static technique involving a total number of 11 bench marks (BM)

RESULTS - CASE STUDY 3

Difference Between GNSS Heighting & Levelling

(cm)

No. of Observation &

(%)

< 10 7

(64 %)

10 – 16.2 4

(36%)

FIG Working Week 2011

Bridging the Gap between Cultures

Marrakech, Morocco, 18‐22 May 2011 14

RESULTS - CASE STUDY 3 (contd.)

Scatter plot of the difference between Orthometric Heights Derived GNSS and Levelling

CONCLUSION

The development of geodetic

infrastructures such as MyRTKnet and

MyGEOID has given great opportunity inenhancing the determination of heightingusing GNSS.

The conventional spirit levelling requires alot of time and is a costly operation as wellas involves a lot of manpower as

compared to GNSS heighting.

FIG Working Week 2011

Bridging the Gap between Cultures

Marrakech, Morocco, 18‐22 May 2011 15

CONCLUSION

Based on the initial studies that have been

carried out, the results indicate that the

accuracy achievable by GNSS heighting in

Malaysia can provide second order

levelling standard.

However, more case studies need to be

conducted regarding GNSS heighting.

Look Forward To Meeting You In

Kuala Lumpur In June 2011 and 2014

22 – 24 June 2011

PUTRA WORLD TRADE CENTRE

Kuala Lumpur, Malaysia

www.seasc2011.org

FIG Working Week 2011

Bridging the Gap between Cultures

Marrakech, Morocco, 18‐22 May 2011 16

Look Forward To Meeting You In

Kuala Lumpur In June 2011 and 2014

Thank you for your attention ....Thank you for your attention ....Thank you for your attention ....Thank you for your attention ....