ts, length of yets 2015-2016 eyets 2016-2017 + liu & cons project

14
TS, Length of YETS 2015- 2016 EYETS 2016-2017 + LIU & CONS Project

Upload: millicent-blankenship

Post on 03-Jan-2016

220 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: TS, Length of YETS 2015-2016 EYETS 2016-2017 + LIU & CONS Project

TS, Length of YETS 2015-2016 EYETS 2016-2017 + LIU & CONS Project

Page 2: TS, Length of YETS 2015-2016 EYETS 2016-2017 + LIU & CONS Project

1. TS 2015

2. www.cern.ch/LS1toLS2

3. Length of YETS 2015-2016 / EYETS 2016-2017

1. YETS 2015-2016

2. EYETS 2016-2017

4. LIU project - Malika Meddahi

5. ACC-CONS project - Michael Benedikt

6. Long Shutdown 2 (LS2) Project

7. EN/MEF-OSS section

8. Training

Outline

David Hay & Simon Mataguez EDMS1509577

Page 3: TS, Length of YETS 2015-2016 EYETS 2016-2017 + LIU & CONS Project

TS 2015

https://espace.cern.ch/be-dep/BEDepartmentalDocuments/BE/Injector_Schedule_2015.pdf

David Hay & Simon Mataguez EDMS1509577

Page 4: TS, Length of YETS 2015-2016 EYETS 2016-2017 + LIU & CONS Project

www.cern.ch/LS1toLS2

David Hay & Simon Mataguez EDMS1509577

Page 5: TS, Length of YETS 2015-2016 EYETS 2016-2017 + LIU & CONS Project

Length of YETS 2015-2016

Status UNDER APPROVAL

ATS-PM-MS-0001 EDMS 1470895

David Hay & Simon Mataguez EDMS1509577

Page 6: TS, Length of YETS 2015-2016 EYETS 2016-2017 + LIU & CONS Project

Length of EYETS 2016-2017

David Hay & Simon Mataguez EDMS1509577

Page 7: TS, Length of YETS 2015-2016 EYETS 2016-2017 + LIU & CONS Project

https://indico.cern.ch/event/344461

LIU project - Malika Meddahi

David Hay & Simon Mataguez EDMS1509577

Page 8: TS, Length of YETS 2015-2016 EYETS 2016-2017 + LIU & CONS Project

The goal of this year, if the ECR of a certain activity cannot be prepared in 2015, then the relative SRR should be submitted before the end of 2015.

David Hay & Simon Mataguez EDMS1509577

Page 9: TS, Length of YETS 2015-2016 EYETS 2016-2017 + LIU & CONS Project

ACC-CONS project - Michael Benedikt STATUS

• Project was launched in 2003/2004 (AB consolidation) to guarantee long-term accelerator

complex operation in view of the LHC program.

• CERN’s Activity Planning Tool ((APT) application https://apt.cern.ch/apt/gui/) used as central tool

for handling and tracking all accelerator consolidation requests

• Two consolidation “reviews” each year, April (to update MTP) and October (carry-over & last minute actions)

• First review was completed end 2014:

• No changes to already approved and ongoing WUs

• Considered only requests STARTING in year 2015

David Hay & Simon Mataguez EDMS1509577

Page 10: TS, Length of YETS 2015-2016 EYETS 2016-2017 + LIU & CONS Project

ACC-CONS project - Michael Benedikt PROCEDURE

• All consolidation centralized in APT

• Soon Standardized EDMS (Consolidation Program WU Description) documentation

accompanying each consolidation request:Context and scope of the consolidation activity

Risk analysis description

Proposed technical solution

Description, alternatives, replacement vs. renewal, etc.

Impact of consolidation

Effect on future operation, maintenance needs & cost, lifetime, homogenization of equipment, safety …

Impact of implementation on other technical systems, projects and technical groups

Resource estimate

Budget estimate, personnel estimate,

Timeline with project planning and milestones

David Hay & Simon Mataguez EDMS1509577

Page 11: TS, Length of YETS 2015-2016 EYETS 2016-2017 + LIU & CONS Project

Long Shutdown 2 (LS2) ProjectLS2 coordinator Jose Miguel Jimenez

The preparation, coordination and follow-up till completion of all LS2 activities in the frame of the LIU, HL-LHC Projects and other CERN approved projects.

LS2 activities: Tool Plan (https://plan.cern.ch/plan/)

• Main milestones:

• LS1 Post Mortem: 1st trimester’15

• Start date: 1st July 2018;

• Duration: 18 months (end’19)

• Yearly “LS2 day” as of 2015

• Activities declared in Plan by end’15 both for injectors and LHC;

• Mid’16, definition of activities for EYETS 2016 and for LS2;

• Preliminary “final” validation: mid 2017.

LS1Post

Mortem

LS2Day

LS2Day

LS2Day

PLANis madeavailable

ConsolidatedList of tasks

to Director A&T

1st stepfinal

validation

Finalvalidation

LHC Performance Workshop (Chamonix 2014) https://indico.cern.ch/event/315665/

David Hay & Simon Mataguez EDMS1509577

Page 12: TS, Length of YETS 2015-2016 EYETS 2016-2017 + LIU & CONS Project

EN/MEF-OSS section

Organization, Technical Coordination and Scheduling

Organization, Technical

Coordination and

Scheduling

LIU-PLI, LIU-Ions, LIU-

Booster, LIU-PS, Linac4

coord.

Consolidation Project

Maintenance (Systems)

David Hay & Simon Mataguez EDMS1509577

Page 13: TS, Length of YETS 2015-2016 EYETS 2016-2017 + LIU & CONS Project

Training

• The first IMPACT training is now available to all people with a CERN login on the SIR platform.

“Intervention Management Planning and Coordination Tool (IMPACT) - Fundamentals”

• New safety courses and New conditions for access rights in Beam Facilities (Mostly to be enforced on May 11 !)

(Please have a look on the presentation from Marc Tavlet, at the IEFC on 24th April, about the new courses for access conditions. https://indico.cern.ch/event/389721/contribution/12/1/material/slides/1.pdf )

• CERN Beam Facilities• Machine-specific courses• Introduction of “ranks” in ADaMS

David Hay & Simon Mataguez EDMS1509577

Page 14: TS, Length of YETS 2015-2016 EYETS 2016-2017 + LIU & CONS Project