Transitional Operations: Guiding Owners Through Start-up Operations and Regulatory
Compliance
Debra C Sharpe, MPH CCHO RBP Director, Laboratory Services & Compliance, WorkingBuildings, LLC
Craig Reed, PhD, RBP Deputy Director, Laboratory Operations, WorkingBuildings, LLC
![Page 2: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/2.jpg)
Transitional Operations
Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of being operated and maintained to perform in conformity with the design intent…
- ASHRAE Guideline 1 - 1996
![Page 3: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/3.jpg)
Transitional Operations
Commissioning Process A quality-based method that is adopted by an Owner to achieve successful construction projects.
- ASHRAE Guideline 0 - 2005
![Page 4: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/4.jpg)
Delivering Buildings That Work - Worldwide
• Better documentation of the Owner’s needs
• Fewer unidentified deficiencies at takeover
• Systems operate at maximum energy efficiency
• Better trained operators
• Saves Money!
Benefits to Owners
The economic benefits
of commissioning lie in
avoiding the added
costs associated with
non-commissioned
facilities.
Benefits to Designers • Clearer understanding of Owner’s needs reduces re-
design work
• Independent design reviews reduce RFIs
• Feedback on actual systems operability – lessons
learned to take to the next project.
![Page 5: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/5.jpg)
Delivering Buildings That Work - Worldwide
• Better design documents
• Early identification of issues
reduces re-work
• Clear documentation of system
functionality at turnover
• Reduced warranty call-backs
Benefits to Contractors
![Page 6: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/6.jpg)
Delivering Buildings That Work - Worldwide
• Technically complicated facilities like
laboratories, or health care facilities
• Typical Project Size
– $3,000,000+
• Engaged early by the owner is best
– Pre-design (preferably)
– Assist in programming
– OPR Workshop
• Specific tasks defined for each phase
When to Use Commissioning
![Page 7: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/7.jpg)
Delivering Buildings That Work - Worldwide
• Typical Project Scope
– Mechanical (chillers, boilers, VAVs)
– Controls (BAS, power monitoring)
– Electrical (switchboards, transformers,
generators)
– Life Safety (Fire Alarm, emergency
lighting)
– Security (card readers, door alarms,
CCTV)
– Building Envelope
When to Use Commissioning
![Page 8: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/8.jpg)
Delivering Buildings That Work - Worldwide
• History of the firm
• Evidence that commissioning is a principal
enterprise of the firm
• Experience with the type of facility being built
• Commissioning expertise and capability
• Local experience over the last five (5) years
on projects of similar size and scope
Commissioning Firm Qualifications
![Page 9: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/9.jpg)
Delivering Buildings That Work - Worldwide
• Prior commissioning reference
contacts
• Resumes of key (commissioning)
management personnel and their
positions
• Professional liability insurance
Commissioning Firm Qualifications
![Page 10: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/10.jpg)
Delivering Buildings That Work - Worldwide
• Minimum 5 years commissioning experience
• Certification by a nationally recognized
authority
– Building Commissioning Association
(BCA)
– University of Wisconsin (Department of
Engineering Professional Development)
– AABC Commissioning Group (ACG)
Commissioning Authority
Qualifications
![Page 11: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/11.jpg)
Delivering Buildings That Work - Worldwide
• 0.5% - 1.5% of the total
construction
• 2% - 3% of mechanical
construction
• 1% - 2% of electrical construction
• Avg $1.00 per square feet
Cost of Commissioning
![Page 12: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/12.jpg)
Transitional Operations
Program Phase
• Owner’s Program of Requirements
• Documentation of the Design Intent Preliminary Commissioning Plan
![Page 13: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/13.jpg)
Delivering Buildings That Work - Worldwide
Integrate The Process
![Page 14: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/14.jpg)
Delivering Buildings That Work - Worldwide
Pre-Design
Phase
![Page 15: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/15.jpg)
Design
Construction
Occupancy
Pre- Design
![Page 16: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/16.jpg)
Research
EVIDENCE /
ACCESSIONING
COURIER /
NON COC /
SECURITY
STORAGE
Existing LAB
RESEARCH LAB
Same requirements as other groups for PCR process
STORAGE / EQUIPMENT – (1)-20C, (1) 4C (Lockable) BATCH
DATA FOR
REVIEW @
DESKS
•Bone Sand Hood
•Chem Hood
•(2) Freezers
•UV Box
•LN2 for Freezer
Mill
PCR /
AMPLIFICATION
POST PCR /
ANALYSIS
EXTRACTION
(Currently share
with Automation)
PCR /
AMPLIFICATION
POST PCR /
ANALYSIS
ANALYSIS SEQUENCING
RX
•Corbet Liquid
Handling
•(2)BSC A1
•DI H2O (Type1)
•(2)BT Centrifuge
PRE PCR / EXTRACTION
•(1)
Freezer
•(1) Dry
•(4)
Permanent
Storage
Freezers
Can be single
space for up to
6 people & 8
kneespaces
Process Flows & SOPs
![Page 17: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/17.jpg)
Transitional Operations
• Mission, Goals & Meeting Minutes
• Service/Research Definition
• Regulatory Compliance
• Standard Operating Procedures (SOPs)
• Equipment Cut Sheets & Coordination
• Waste Handling
• Materials Receiving
• Inventory Control
• Security
• Staffing & Scheduling
• Service Contracts
• Community Outreach Initiatives
• Existing Utilities & Providers
• Internal Design Standards
Design Phase Narrative
![Page 18: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/18.jpg)
Transitional Operations
Designer Compliance Discussions
• Complexity of the Design
• Can the institution maintain the intended design concept
• Cost of operation the facility
• Ways to reduce cost of overhead and maintenance
![Page 19: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/19.jpg)
Transitional Operations
Design Phase • Protocols/PPE
• Security paradigm
• O&M
• First responder coordination
• Inventory and equipment analysis
• Contract services providers
• Equipment coordination
![Page 20: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/20.jpg)
Transitional Operations
Owner Compliance Discussions
• What agents will be used? In vivo/In vitro
• Volumes & concentrations
• Volumes & types of chemicals
• Work or process flow
• Is this an organization with “Institutional Control”?
![Page 21: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/21.jpg)
Transitional Operations
Owner Compliance Discussions
• Review existing state regulations & identify if they go beyond federal regulations (i.e., waste disposal)
• Review copies of existing policies and procedures
• Review existing operational documents
• Identifying appropriate SOPs, PPE and protocols based on risk assessments
![Page 22: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/22.jpg)
Transitional Operations
Construction Phase Owner
• O&M protocols/PPE
• Community outreach
• First responder coordination
• Contract services providers
• Facilities inspections
• Move management
• Maintaining existing facility
![Page 23: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/23.jpg)
Transitional Operations
Final Acceptance • As-built documentation
• Complete commissioning and facility validation
• Complete systems (O&M) manual
• Training documents
• Specified materials inventory
• Off-season testing TBD
![Page 24: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/24.jpg)
Transitional Operations
Transitional Phase • Maintenance & documentation
• RFPs for service contracts
• Move coordination
• Instrument/equipment validation
• User walk-through tours
• Regulatory compliance documents
• Training
![Page 25: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/25.jpg)
Transitional Operations
Transitional Operations
• Laboratory Commissioning
• Design Review for Compliance
• Protocol Development/Revisions
• Final Stage Operations Oversight
• Building O&M Staff
• Regulatory Compliance Enforcement/ Pre-Inspections
• Move Coordination
• Facility Wide/Multi-Science Protocols
![Page 26: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/26.jpg)
Transitional Operations
Compliance Coordination • Biosecurity Plan
• Emergency Response Plan
• Biosafety Manual
• Community Outreach Initiatives
• Protocols
• PPE
• Security
• Maintenance Safety
![Page 27: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/27.jpg)
Transitional Operations
Compliance Coordination • Providing Supportive Facility Cx
Documentation to the Regulatory Authorities (i.e., CDC SA Registration)
• Assisting with the Development of Regulatory Documents Policies and Procedures
• Developing and Providing Training to Laboratory and Maintenance Staff
• Meeting with the Regulatory Agencies the community and first responders
![Page 28: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/28.jpg)
Transitional Operations
New Jersey Public Health, Environmental and Agricultural Laboratory
![Page 29: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/29.jpg)
New Jersey Public Health, Environmental and Agricultural Laboratory
NJPHEAL
![Page 30: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/30.jpg)
Transitional Operations
New Jersey Public Health, Environmental and Agricultural Laboratory
NJPHEAL Vision • Mission Based Objective – 15 Years
• Response to Deteriorating State PH Labs
• Anthrax Incidents after 9/11
• Increased Funding Opportunities
• Available Property – Secure Location
![Page 31: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/31.jpg)
Transitional Operations
New Jersey Public Health, Environmental and Agricultural Laboratory
Consolidated Lab Services
• Clinical Public Health
• Environmental Health
• Animal Health
• Plant Health
• Laboratory Response Network
![Page 32: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/32.jpg)
New Jersey Public Health, Environmental and Agricultural Laboratory
Contractual Structure
New Jersey Building Authority
(NJBA)
Department of Health and Senior
Services
Department of Environmental
Protection
Department of Agriculture
Design Team
Construction Manager
Contractor
Transitional Operations Team
Consultants
![Page 33: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/33.jpg)
Site Location & Security
New Jersey State Police Headquarters Campus
![Page 34: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/34.jpg)
Transitional Operations
New Jersey Public Health, Environmental and Agricultural Laboratory
Unique Design Challenges
• Space Types
• Facility Wide Protocols
• 24/7 Operations
• Regulatory Requirements
• Community Relations
• Katrina, China & Inflation
• Move Managment
• Six Years and Counting…
![Page 35: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/35.jpg)
Transitional Operations
New Jersey Public Health, Environmental and Agricultural Laboratory
Murphy’s Law • DI Water Leak X 12 (and counting…)
• Condensation flood (AHU Down)
• Sanitary Blockage Flood
• No BSL-3 exhaust fan redundancy
• Installation of separate BSL-3 exhaust fans to maintain static pressure
• Lack of supply and exhaust airflow tracking
• Static dissipating tile shrinkage
• VAV reprogramming
• Long horizontal runs perchloric acid hoods
![Page 36: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/36.jpg)
Transitional Operations
Lessons Learned
• Users were not adequately involved in the design process
• Centralized leadership was lacking for decision making
• Poor value engineering choices
• Cx agent initially reported to the architect then the owner
![Page 37: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/37.jpg)
Transitional Operations
Lessons Learned
• Did not adequately review existing compliance structure and documentation
• Ensure all groups understand compliance expectations
• Sharing a facility with different state entities very, very challenging
![Page 38: Transitional Operations · 2017. 9. 3. · Transitional Operations Commissioning The process of ensuring that systems are designed, installed, functionally tested, and capable of](https://reader035.vdocuments.mx/reader035/viewer/2022071103/5fdd0434d6c8fe724f2da978/html5/thumbnails/38.jpg)
Transitional Operations
Conclusions
• Complex & time intensive process
• Expertise is essential
• Involve Cx agent early and report to the owner
• Communication/documentation
• Consolidated leadership with involved stakeholders
• Shared responsibilities
• Informed decision making is key
• Final year is the most difficult