Tower Renewal – Not yet passive but actively pursuing improvement Eleanor McAteer November 29, 2012. Toronto Towers. over 1,000 concrete slab, multi-residential apartment buildings Built between 1950’s and 1980’s 8 stories or more. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Tower Renewal – Not yet passive but actively pursuing improvement Eleanor McAteer](https://reader035.vdocuments.mx/reader035/viewer/2022062810/56815e6a550346895dcce637/html5/thumbnails/1.jpg)
1
Tower Renewal –Not yet passive but actively pursuing improvement
Eleanor McAteerNovember 29, 2012
![Page 2: Tower Renewal – Not yet passive but actively pursuing improvement Eleanor McAteer](https://reader035.vdocuments.mx/reader035/viewer/2022062810/56815e6a550346895dcce637/html5/thumbnails/2.jpg)
2
Toronto Towers
• over 1,000 concrete slab, multi-residential apartment buildings
•Built between 1950’s and 1980’s
•8 stories or more
![Page 3: Tower Renewal – Not yet passive but actively pursuing improvement Eleanor McAteer](https://reader035.vdocuments.mx/reader035/viewer/2022062810/56815e6a550346895dcce637/html5/thumbnails/3.jpg)
3
A program to drive broad environmental, social, economic, and cultural change by improving Toronto’s concrete apartment towers and the
neighbourhoods that surround them.
And in so doing, secure a resilient source of housing.
Tower Renewal
![Page 4: Tower Renewal – Not yet passive but actively pursuing improvement Eleanor McAteer](https://reader035.vdocuments.mx/reader035/viewer/2022062810/56815e6a550346895dcce637/html5/thumbnails/4.jpg)
4
![Page 5: Tower Renewal – Not yet passive but actively pursuing improvement Eleanor McAteer](https://reader035.vdocuments.mx/reader035/viewer/2022062810/56815e6a550346895dcce637/html5/thumbnails/5.jpg)
5
![Page 6: Tower Renewal – Not yet passive but actively pursuing improvement Eleanor McAteer](https://reader035.vdocuments.mx/reader035/viewer/2022062810/56815e6a550346895dcce637/html5/thumbnails/6.jpg)
6
Temperature 1971-2000 2050
# days > 30 C 15 40
# days > 35 C 0.5 4
New ClimateExample:
Should buildings not be upgraded to have better performance for occupant comfort, the building may become stigmatized as ‘unliveable’ making it functionally obsolete before it is physically obsolete
![Page 7: Tower Renewal – Not yet passive but actively pursuing improvement Eleanor McAteer](https://reader035.vdocuments.mx/reader035/viewer/2022062810/56815e6a550346895dcce637/html5/thumbnails/7.jpg)
7
27 climatic design values included in the National Building Code are relevant to the design and performance of a building
Case Study – Climate Change Vulnerability Assessment
![Page 8: Tower Renewal – Not yet passive but actively pursuing improvement Eleanor McAteer](https://reader035.vdocuments.mx/reader035/viewer/2022062810/56815e6a550346895dcce637/html5/thumbnails/8.jpg)
8
We must consider the Buildings and People
Community Impact
“2006, nearly 40% of all the families in high-rise buildings in the City of Toronto were poor”
http://www.unitedwaytoronto.com/whatWeDo/reports/verticalPovertyReport.php
![Page 9: Tower Renewal – Not yet passive but actively pursuing improvement Eleanor McAteer](https://reader035.vdocuments.mx/reader035/viewer/2022062810/56815e6a550346895dcce637/html5/thumbnails/9.jpg)
9
Tower Renewal Guidelines
A “how to” guide for owners, managers, engineers and architects.
http://www.daniels.utoronto.ca/trg
![Page 10: Tower Renewal – Not yet passive but actively pursuing improvement Eleanor McAteer](https://reader035.vdocuments.mx/reader035/viewer/2022062810/56815e6a550346895dcce637/html5/thumbnails/10.jpg)
10
Huge Opportunities
Image: Boldstar Infrared Services Inc.
![Page 11: Tower Renewal – Not yet passive but actively pursuing improvement Eleanor McAteer](https://reader035.vdocuments.mx/reader035/viewer/2022062810/56815e6a550346895dcce637/html5/thumbnails/11.jpg)
11
Physical Improvements
Figure A.17. Cutaway rendering of the completed EIFS wall overcladding and window replacement.
http://www.daniels.utoronto.ca/trg Ted Kesik
•In-suite Measures
•Mechanical Systems
•Building Surfaces
•Energy Generation
![Page 12: Tower Renewal – Not yet passive but actively pursuing improvement Eleanor McAteer](https://reader035.vdocuments.mx/reader035/viewer/2022062810/56815e6a550346895dcce637/html5/thumbnails/12.jpg)
12
Case Study - Green Phoenix
greenphoenix.ca
![Page 13: Tower Renewal – Not yet passive but actively pursuing improvement Eleanor McAteer](https://reader035.vdocuments.mx/reader035/viewer/2022062810/56815e6a550346895dcce637/html5/thumbnails/13.jpg)
13
Tenant Engagement
Teamwork saves energy, funds bike club and helps neighbours get to know one another
The positive outcomes are in contrast to the assumptions that conservation was of minimal interest to residents in a place where many have low incomes, and with utility costs included in the rent, they'd see no direct payback. Brahms Energy Saving Team
![Page 14: Tower Renewal – Not yet passive but actively pursuing improvement Eleanor McAteer](https://reader035.vdocuments.mx/reader035/viewer/2022062810/56815e6a550346895dcce637/html5/thumbnails/14.jpg)
14
Tower Renewal STEP Program
Five step process, intended to incrementally build capacity
Foundation Stage
Step One: Learning and Planning
Step Two: Action
Step Three: Maximizing Outcomes
Step Four: Leadership
![Page 15: Tower Renewal – Not yet passive but actively pursuing improvement Eleanor McAteer](https://reader035.vdocuments.mx/reader035/viewer/2022062810/56815e6a550346895dcce637/html5/thumbnails/15.jpg)
15
STEP Assessment
• Checklist to determine current state
• Compare to other apartment buildings
• Directs improvement plans, monitors and recognizes actions
• All apartment buildings can participate
3
![Page 16: Tower Renewal – Not yet passive but actively pursuing improvement Eleanor McAteer](https://reader035.vdocuments.mx/reader035/viewer/2022062810/56815e6a550346895dcce637/html5/thumbnails/16.jpg)
16
Economic Impact
Undertaking Tower Renewal Retrofit throughout Toronto is projected to create:
• 10,000+ person years of employment
• $Billion+ in net wages paid locallyhttp://www.toronto.ca/city_manager/pdf/tr_jobs.pdf
![Page 17: Tower Renewal – Not yet passive but actively pursuing improvement Eleanor McAteer](https://reader035.vdocuments.mx/reader035/viewer/2022062810/56815e6a550346895dcce637/html5/thumbnails/17.jpg)
17
Implementation Outcomes
• Comprehensive projects drive green industry growth and create substantial number of jobs
• Improvements create better living conditions
• Better environmental performance reduces GHG emissions
• Resilience to climate impacts, providing more secure provision of rental housing stock
![Page 18: Tower Renewal – Not yet passive but actively pursuing improvement Eleanor McAteer](https://reader035.vdocuments.mx/reader035/viewer/2022062810/56815e6a550346895dcce637/html5/thumbnails/18.jpg)
18
2009700,000+ Tonnes CO2
2020+230,000 Tonnes CO2
![Page 19: Tower Renewal – Not yet passive but actively pursuing improvement Eleanor McAteer](https://reader035.vdocuments.mx/reader035/viewer/2022062810/56815e6a550346895dcce637/html5/thumbnails/19.jpg)
19
Eleanor McAteer, Project Director for Tower Renewal, [email protected]