totalsolution for sustainability - wika rekon...mechanical, electrical dan steel structure...

38
COMPANY PROFILE for Sustainability Solution Total

Upload: others

Post on 01-Aug-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

COMPANY PROFILE

for SustainabilitySolutionTotal

Page 2: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

PT WIJAYA KARYA REKAYASA KONSTRUKSI, which is commonly called WIKA REKON, is a company engaged in construction services, engineering procurement and construction services, fabrication services, operation and maintenance services as well as investment.

WIKA REKON is primarily engaged in MEP (Mechanical Electrical, Piping), EPCC (Engineering, Procurement, Construction, Commissioning), O&M (Operation & Maintenance) and Investment.

As a Company that already has full of experience, WIKA REKON provides the best service and work for every stakeholder, so that what is produced from each project can be beneficial for all parties

PT WIJAYA KARYA REKAYASA KONSTRUKSI, yang biasa disebut WIKA REKON adalah Perusahaan yang bergerak dibidang Jasa Konstruksi, jasa Engineering Procurement dan Construction, jasa Fabrikasi, jasa Peng-operasian dan Pemeliharaan serta Investasi.

WIKA REKON yang utama melakukan pekerjaan -pekerjaan di bidang MEP (Mechanical Electrical Piping), EPCC (Engineering Procurement Construction Commisioning), O&M (Operation & Maintenance) dan Investasi.

Sebagai perusahaan yang sudah mempunyai banyak pengalaman, WIKA REKON menyajikan pelayanan serta pekerjaan yang terbaik bagi setiap pemangku kepentingan, sehingga apa yang dihasilkan dari setiap pekerjaan dapat bermanfaat bagi semua pihak

Page 3: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

Sambutan dari CEO

Pertama-tama, PT Wijaya Karya Rekayasa Konstruksi (WIKA REKON) adalah anak perusahaan PT Wijaya Karya (Persero), Tbk. (WIKA) yang dirancang menjadi perusahaan yang terintegrasi, agresif, inovatif dan professional pada bidang MEP (Mechanical, Electrical, Piping), EPCC (Engineering, Procure-ment, Construction, Commissioning) dan O&M (Operation & Maintenance) serta Investasi di sektor industrial dan powerplant serta fasilitas infrakstruktur.

Kedepannya, dengan visi menjadi perusahaan “Total Solution Bidang Energi yang Terintegrasi dan Terkemuka di Asia Tenggara” WIKA REKON akan terus maju dan tumbuh mempertahankan profitabilitas operasi menjawab tantangan dengan memberikan solusi yang terintegrasi pada ketersediaan energi di Indonesia serta Asia Tenggara.

Saat ini, kami menangani beberapa proyek MEP dan EPCC seperti pabrik biodiesel pertama di wilayah Kalimantan Selatan serta mengoperasikan dan melakukan pemeliharaan rutin di 7 lokasi unit pembangkit listrik dari Sumatera hingga Papua.

Kami yakin bahwa Perusahaan telah bergerak sesuai dengan bisnis yang sesuai dengan Anggaran Dasar yakni sebagai kontraktor erector untuk MEP menuju solusi total terpadu untuk energi. WIKA REKON akan menjadi mitra terpercaya anda dan melayani melebihi ekspektasi anda, karena kepuasan anda adalah prioritas utama kami.

“Keberhasilan bukanlah milik orang pintar, namun keberhasilan itu adalah milik mereka yang senantiasa berusaha” - B.J. Habibie

Page 4: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

Hendra JayusmanPresident Director & CEO

First of all, PT Wijaya Karya Rekayasa Konstruksi (WIKA REKON) is a sub-sidiary of PT Wijaya Karya (Persero), Tbk. (WIKA) which is designed to be an integrated, aggressive, innovative and professional Company in the fields of MEP (Mechanical, Electrical, Piping), EPCC (Engineering, Procurement, Construction, Commissioning), O&M (Operation & Maintenance), investment in the industrial and power plant sectors as well as infrastructure facilities.

In the future, with the vision of becoming a “Total Solution for Integrated and Leading Energy Sector in Southeast Asia” WIKA REKON will continue to progress and grow to maintain operating profitability to answer challenges by providing integrated solutions to the availability of energy in Indonesia and Southeast Asia.

Currently, we are handling several MEP and EPCC projects such as the first biodiesel plant in the South Kalimantan region as well as operating and carrying out routine maintenance at 7 power generating unit locations from Sumatra to Papua.

We believe that the Company has moved according to the business stipulated in the Articles of Association namely as a contractor erector for MEP towards a total integrated solution for energy. WIKA REKON will be your trusted partner and exceed your expectations, because your satisfaction is our top priority.

Words From CEO

“If you want to be successful, learn from other people’s mistakes, not their successes. No matter how smart you are, you will encounter these mistakes, and you’ll know how to deal with them.” - Jack Ma.

Page 5: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

EPCCEngineering, Procurement, Construction, Commissioning

Melangkah maju ke depan, WIKA REKON mengembangkan lini usahanya ke bidang konstruksi EPCC (Engineering, Procurement, Construction, Commissioning) yang melaksanakan secara inhouse untuk desain teknikal rinci, pengadaan equipment dan material konstruksi yang digunakan, dan serta proses konstruksi dan uji coba fungsi hasil konstruksi dengan baik dalam proses commissioning sebelum diserahterimakan kepada pemberi kerja.

Dengan kombinasi pengalaman para expertise dan dukungan profesional muda, kami yakin akan memberikan produk berkualitas tinggi tepat waktu dengan biaya kompetitif bagi para pengguna kami.

Moving forward, WIKA REKON is expanding its business line to the EPCC (Engineering, Procurement, Construction, Commissioning) construction sector which carries out in-house for detailed technical design, procurement of construction equipment and materials used, as well as the construction process and testing of construction results functions with both in the commissioning process before being handed over to the project owner.

With the combination of experienced expertise and support from young professionals, we are confident of delivering high quality products on time at competitive costs to our users.

MEPMechanical, Electrical, Piping

Didirikan sebagai perusahaan kontraktor erector Mekanikal, Elektrikal dan Piping (MEP) menjadikan WIKA REKON sebagai salah satu perusahaan erector yang diper-hitungkan di konstruksi nasional sebagai core competenciesnya.

WIKA REKON telah mencatatkan nama besarnya di erector MEP pada pembangkit listrik, pabrik industri, infrastruktur, gedung dan sebagainya.

Kami yakin, kompetensi inti dan pengala-man ini dapat memberikan harga yang kompetitif di antara para pesaing, jadwal konstruksi yang tepat waktu dan kualitas tertinggi pada instalasi mekanikal, steel structure, tangka, elektrikal dan pemipaan

Established as a Mechanical, Electrical and Piping (MEP) erector contractor Company, WIKA REKON is one of the erector Companies that are considered in national construction as its core competencies.

WIKA REKON has registered its reputation in the MEP erector in power plants, industrial plants, infrastructure, buildings, etc.

We believe this core competence and experience can provide competitive prices among competitors, on time construction schedules and the highest quality in mechanical, steel structure, tank, electrical and piping installations.

Page 6: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

InvestasiInvestment

Menandai satu dasawarsa berdirinya perusahaan, WIKA Rekon mendirikan lini usaha investasi yang mendukung visi perusahaan menjadi Perusahaan Total Solution Bidang Energi yang Ter-integrasi dan Terkemuka.

Lini usaha investasi yang terintegrasi dengan MEP, EPCC serta O&M, tentunya akan memberikan rasa nyaman dan aman bagi partner strategis kami untuk bersama melakukan investasi total solution energi.

Perusahaan juga memastikan bahwa setiap investasi yang berkelanjutan dan tidak bertentangan dengan pemegang saham.

Menerapkan strategi investasi yang kompetitif berdasarkan etika Tata Kelola Perusahaan yang Baik merupakan hal wajib bagi WIKA REKON. Marking a decade of the Company’s establish-ment, WIKA REKON established an investment business line that supports the Company’s vision to become an Integrated and Leading Total Solution Company for Energy.

An integrated investment business line with MEP, EPCC and O&M, of course, will provide a sense of comfort and safety for our strategic partners to jointly invest in total energy solutions.

The Company also ensures that any invest-ment is sustainable and does not conflict with shareholders.

Implementing a competitive investment strategy based on Good Corporate Governance ethics is mandatory for WIKA REKON.

Operasi & PemeliharaanOperation & Maintenance

Melengkapi lini usaha di MEP dan EPCC, WIKA REKON membentuk unit usaha O&M (Operation & Maintenance). Divisi Operasi dan Pemeliharaan mem-berikan solusi komprehensif untuk pengelolaan aset, termasuk pengoper-asian dan pemeliharaan di fasilitas pembangkit, industrial plant, migas dan infrastruktur serta dukungan pada tahap commissioning untuk Proyek EPCC.

WIKA REKON juga memberikan jasa konsultasi kepada klien untuk mening-katkan produktivitas peralatan di berbagai pekerjaan jasa O&M yang dikelola.

Karyawan yang terampil dan sesuai kompetensinya memastikan kami untuk memberikan standar operasi yang berkualitas tinggi, aman dan sehat.

Completing the business lines in MEP and EPCC, WIKA REKON formed an O&M (Operation & Maintenance) business unit. The Operation & Maintenance Division provides comprehen-sive solutions for asset management, including operation & maintenance of generating facilities, industrial plants, oil & gas and infrastructure as well as support at the commissioning stage for the EPCC Project.

WIKA REKON also provides consulting services to clients to increase equipment productivity in various managed O&M services.

Our skilled and competent employees ensure us to provide high quality, safe and healthy operating standards.

Bidang Usaha Business Lines

Page 7: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

“Menjadi Perusahaan Total Solution Bidang Energi yang Terintegrasi dan Terkemuka di Asia Tenggara”

Total Solution Merupakan strategi bisnis WRK yang meliputi MEP, EPCC mengarah pada

Renewable Energy dan Operation & Maintenance serta Investasi.

Terintegrasi Adalah bentuk sinergi dengan Holding dan Anak Perusahaan

Visi

Misi

Menerapkan Sistem Manajemen WRK dan GCG dalam semua kegiatan bisnis,

Menyediakan jasa MEP, EPCC Renewable Energy dan Operation & Maintenance serta melakukan investasi dalam bidang energi dengan mengoptimalkan sinergi BUMN dan WIKA Group untuk

menciptakan keuntungan dan bisnis yang berkelanjutan

Meningkatkan kompetensi dan kinerja serta mengembangkan kapabilitas Human Capital

Membangun Kerjasama bisnis dengan partner strategis untuk menciptakan peluang yang berkelanjutan baik di Indonesia.

Mengimplementasikan integrasi sistem manajemen berbasis digital dalam pengelolaan bisnis.

Page 8: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

AmanahKami memegang teguh kepercayaan yang diberikan.

KompetenKami terus belajar dan mengembangkan kapabilitas.

HarmonisKami saling peduli dan menghargai per-bedaan.

Corporate Values

Loyal Kami berdedikasi dan mengutamakan kepentingan bangsa negara.

AdaptifKami terus berinovasi dan antusias dalam menggerakkan ataupun menghadapi perubahan.

KolaboratifKami membangun kerja sama yang sinergis.

Page 9: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

MEP

EPCC

Investment

Operation &Maintenance

Page 10: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

“Imagination is everything. It is the preview of life’s coming attractions.” – Albert Einstein

Corporate Group

Page 11: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

PLTP Karaha BodasGarut

Bandara Terminal 3 Ultimate, Banten

South Pasific Viscose Purwakarta

Patra Badak Arun Solusi,Indramayu

PLTMG Bali

PLTD CPOBelitung

Dermaga BelawanSumatera Utara

Conveyor Pangkalan SusuSumatera Utara

IKBB, Riau

PLTD BorangSumatera Selatan

Bio Diesel Plant Batulicin, Kalsel

MEP Projects EPCC Projects O&M Projects

WIKA REKON Projects

PLTMG Tanjung Selor Kalimantan Utara

Page 12: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

PLTMG BiakPapua

PLTMG TernateMaluku Utara

PLTMG Nabire

PLTMH IlagaPapua

PLTMH OksibilPapua

PLTMH TolikaraPapua

PLTMG Sorong

PLTMG MeraukePapua

PLTMG SeramMaluku

PLTMG LanggurMaluku

PLTG SenipahKalimantan Timur

PLTMG Sumbawa

PLTG Kendari

Lokasi Proyek Project Location

Bandara Hassanudin Makasar

Page 13: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

No Project Name Scope of Works Project Owner Location & Year

MEP

1 PLTMG 11x17,5 MW Erection, Mechanical, Electrical & Instrument PT PP (Persero), Tbk Bali 2015

2 Storage Terminal at Karimun Island, Riau Erection Civil Works : Building, Foundation, Pipe sliper, Dayke Wall, etc

PT Indian Oil Tank EPC Indonesia Riau 2015

3 PLTD Oecusee 4 x 9 MW, Timor Leste Erection Works : Mechanical, Electrical, Instrument & Commisioning PT Wartsila Indonesia Timor Leste 2015

4 Storage LPG Mundu Civil Construction Service & Piping LPG Mundu PT Patra Badak Arun Solusi Indramayu 2015

5 Erector Raw Water Pipeline DN 800 Raw Construction Works of New DN 800 RAW Water Pipe Line at Purwakarta PT South Pacific Viscose Purwakarta 2015

6 Chipmill Erection, Mechanical & Electrical Cutt Size PT IKBB Pekanbaru PT IKBB Pekanbaru 2009

7 Wet Sulfur Acid (WSA) Construction Works , Mechanical, Electrical PT South Pacific Viscose Purwakarta 2016

8 Cutt Size PT IKBB Pekanbaru Mechanical & Piping PT IKBB Pekanbaru 2016

9 Conoco Dayung Compression Phase 2 - IKPT Civil, equipment Installation, Piping, Painting & Insulation PT IKPT Dayung 2016

10 Mobile and Fixed Type Gas Engine Power Plant Package VII

Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df

PT PP (Persero), Tbk

PT PP (Persero), Tbk

Ternate 2017

Nabire 2017

11 Mobile and Fixed Type Gas Engine Power Plant Package VIII

Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df

PT PP (Persero), Tbk

PT PP (Persero), Tbk

Jayapura 2017

Kendari 2017

12 Paket IV Sumbawa PLN Mechanical, Electrical dan Steel Structure Construction 3x16V34df

PT Wijaya Karya (Persero), Tbk Sumbawa 2017

13 Scatterd Dual Fuel Engine Mobile Power Plant 120 MW

Mechanical, Electrical dan Steel Structure Construction PT PP (Persero), Tbk Sorong 2018Merauke 2018

14 PLTU Pangkalan Susu Unit 3 dan 4 (2x200MW) Main Conveyor (Mechanical, Steel Structure, Piping & Electrical Installation) PT PLN (Persero) UIP KITSUM Sumatra Utara 2018

15 Dermaga Terminal Peti Kemas Belawan Paket II Mechanical, Piping & Electrical Installation PT Prima Terminal Petikemas Medan, Sumatra Utara 2018

16 PLTMG Kendari Mechanical, Electrical PT PP (Persero), Tbk Kendari 2017

17 PLTMG Betano 7x18 MW Erection, Mechanical, Electrical PT. Puri Akraya Timor Leste 2011

18 HERRA Timor Leste 6x18 MW Erection, Mechanical, Electrical PT. Puri Akraya Timor Leste 2012

Page 14: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

No Project Name Scope of Works Project Owner Location & Year

MEP

1 PLTMG 11x17,5 MW Erection, Mechanical, Electrical & Instrument PT PP (Persero), Tbk Bali 2015

2 Storage Terminal at Karimun Island, Riau Erection Civil Works : Building, Foundation, Pipe sliper, Dayke Wall, etc

PT Indian Oil Tank EPC Indonesia Riau 2015

3 PLTD Oecusee 4 x 9 MW, Timor Leste Erection Works : Mechanical, Electrical, Instrument & Commisioning PT Wartsila Indonesia Timor Leste 2015

4 Storage LPG Mundu Civil Construction Service & Piping LPG Mundu PT Patra Badak Arun Solusi Indramayu 2015

5 Erector Raw Water Pipeline DN 800 Raw Construction Works of New DN 800 RAW Water Pipe Line at Purwakarta PT South Pacific Viscose Purwakarta 2015

6 Chipmill Erection, Mechanical & Electrical Cutt Size PT IKBB Pekanbaru PT IKBB Pekanbaru 2009

7 Wet Sulfur Acid (WSA) Construction Works , Mechanical, Electrical PT South Pacific Viscose Purwakarta 2016

8 Cutt Size PT IKBB Pekanbaru Mechanical & Piping PT IKBB Pekanbaru 2016

9 Conoco Dayung Compression Phase 2 - IKPT Civil, equipment Installation, Piping, Painting & Insulation PT IKPT Dayung 2016

10 Mobile and Fixed Type Gas Engine Power Plant Package VII

Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df

PT PP (Persero), Tbk

PT PP (Persero), Tbk

Ternate 2017

Nabire 2017

11 Mobile and Fixed Type Gas Engine Power Plant Package VIII

Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df

PT PP (Persero), Tbk

PT PP (Persero), Tbk

Jayapura 2017

Kendari 2017

12 Paket IV Sumbawa PLN Mechanical, Electrical dan Steel Structure Construction 3x16V34df

PT Wijaya Karya (Persero), Tbk Sumbawa 2017

13 Scatterd Dual Fuel Engine Mobile Power Plant 120 MW

Mechanical, Electrical dan Steel Structure Construction PT PP (Persero), Tbk Sorong 2018Merauke 2018

14 PLTU Pangkalan Susu Unit 3 dan 4 (2x200MW) Main Conveyor (Mechanical, Steel Structure, Piping & Electrical Installation) PT PLN (Persero) UIP KITSUM Sumatra Utara 2018

15 Dermaga Terminal Peti Kemas Belawan Paket II Mechanical, Piping & Electrical Installation PT Prima Terminal Petikemas Medan, Sumatra Utara 2018

16 PLTMG Kendari Mechanical, Electrical PT PP (Persero), Tbk Kendari 2017

17 PLTMG Betano 7x18 MW Erection, Mechanical, Electrical PT. Puri Akraya Timor Leste 2011

18 HERRA Timor Leste 6x18 MW Erection, Mechanical, Electrical PT. Puri Akraya Timor Leste 2012

Page 15: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

No Project Name Scope of Works Project Owner Location & Year

EPCC

1 Erector, Mechanical & Electrical - Truck Mounted Gas Turbine Power Plant

Truck Mounted Gas Turbine Power Plant Jeranjang, Lombok (2x25 MW)

Truck Mounted Gas Turbine Power Plant Duri, Riau (3x25MW)

PT PP (Persero), Tbk

PT PP (Persero), Tbk

Lombok 2016

Duri 2016

2 Pembangunan PLTD CPO Belitung Civil, Mechanical, Electrical PT PP (Persero), Tbk Belitung 2016

3 Pembangunan PLTMH Tolikara, Prov Papua EPCC PT Wijaya Karya (Persero) Tbk Papua, Tolikara 2016

Pembangunan PLTMH Ilaga Prov Papua EPCC PT Wijaya Karya (Persero) Tbk Papua, Ilaga 2016

Pembangunan PLTMH Oksibil Prov Papua EPCC PT Wijaya Karya (Persero) Tbk Papua, Oksibil 2016

4 Proyek EPC System Conveyor dari Dermaga 2 PLTU Banten Suralaya EPCC Conveyor PT Indonesia Power Suralaya 2016

5 EPCC Panasbumi Karaha 1x30 MW-Nett Mechanical and Electrical Erection PT Alstom Power Energy Systems Indonesia Karaha 2017

O&M

1 PLTD 60 MW Pesanggaran Bali Operation & Maintenance KSO PT. Wijaya Karya (Persero) Tbk,dan Merlindo Pandu Kencana Bali, 2012-2017

2 PLTG Borang 80 MW Sumatera Selatan Operation & Maintenance KSO PT. Wijaya Karya (Persero) Tbk, dan PT. Navigat Energy Sumatera Selatan, 2013-2017

3 PLTG SENIPAH 80 MW Kalimantan Timur Operation & Maintenance PT Kertanegara Energi Perkasa Kalimantan Timur, 2017

4 Paket 3 PLTMG Tanjung Selor 15 MW Kalimantan Utara Operation & Maintenance PT PLN Kalimantan Timur-Kalimantan Utara Kalimantan Utara, 2019

5 Paket 3 PLTMG Seram 15 MW Maluku Operation & Maintenance PT PLN Maluku & Maluku UtaraMaluku 2019

6 Paket 3 PLTMG Langgur 15 MW Maluku Operation & Maintenance PT PLN Maluku & Maluku Utara Maluku 2019

7 Paket 3 PLTMG Biak 20 MW, Papua Barat Operation & Maintenance PT PLN Papua & Papua Barat Papua Barat 2019

8 Paket 3 PLTMG Merauke 20 MW, Papua Operation & Maintenance PT PLN Papua & Papua Barat Papua 2019

9 Terminal 3 Bandara Soekarno Hatta MEP Operation & Maintenance PT Angkasa Pura II (Persero) Banten 2017

Page 16: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

No Project Name Scope of Works Project Owner Location & Year

EPCC

1 Erector, Mechanical & Electrical - Truck Mounted Gas Turbine Power Plant

Truck Mounted Gas Turbine Power Plant Jeranjang, Lombok (2x25 MW)

Truck Mounted Gas Turbine Power Plant Duri, Riau (3x25MW)

PT PP (Persero), Tbk

PT PP (Persero), Tbk

Lombok 2016

Duri 2016

2 Pembangunan PLTD CPO Belitung Civil, Mechanical, Electrical PT PP (Persero), Tbk Belitung 2016

3 Pembangunan PLTMH Tolikara, Prov Papua EPCC PT Wijaya Karya (Persero) Tbk Papua, Tolikara 2016

Pembangunan PLTMH Ilaga Prov Papua EPCC PT Wijaya Karya (Persero) Tbk Papua, Ilaga 2016

Pembangunan PLTMH Oksibil Prov Papua EPCC PT Wijaya Karya (Persero) Tbk Papua, Oksibil 2016

4 Proyek EPC System Conveyor dari Dermaga 2 PLTU Banten Suralaya EPCC Conveyor PT Indonesia Power Suralaya 2016

5 EPCC Panasbumi Karaha 1x30 MW-Nett Mechanical and Electrical Erection PT Alstom Power Energy Systems Indonesia Karaha 2017

O&M

1 PLTD 60 MW Pesanggaran Bali Operation & Maintenance KSO PT. Wijaya Karya (Persero) Tbk,dan Merlindo Pandu Kencana Bali, 2012-2017

2 PLTG Borang 80 MW Sumatera Selatan Operation & Maintenance KSO PT. Wijaya Karya (Persero) Tbk, dan PT. Navigat Energy Sumatera Selatan, 2013-2017

3 PLTG SENIPAH 80 MW Kalimantan Timur Operation & Maintenance PT Kertanegara Energi Perkasa Kalimantan Timur, 2017

4 Paket 3 PLTMG Tanjung Selor 15 MW Kalimantan Utara Operation & Maintenance PT PLN Kalimantan Timur-Kalimantan Utara Kalimantan Utara, 2019

5 Paket 3 PLTMG Seram 15 MW Maluku Operation & Maintenance PT PLN Maluku & Maluku UtaraMaluku 2019

6 Paket 3 PLTMG Langgur 15 MW Maluku Operation & Maintenance PT PLN Maluku & Maluku Utara Maluku 2019

7 Paket 3 PLTMG Biak 20 MW, Papua Barat Operation & Maintenance PT PLN Papua & Papua Barat Papua Barat 2019

8 Paket 3 PLTMG Merauke 20 MW, Papua Operation & Maintenance PT PLN Papua & Papua Barat Papua 2019

9 Terminal 3 Bandara Soekarno Hatta MEP Operation & Maintenance PT Angkasa Pura II (Persero) Banten 2017

Page 17: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

PLTMG LANGGUR 15 MW

Page 18: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

PLTMG BIAK 20 MW

Page 19: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

PROJECT HIGHLIGHT Piping, LNG Project Mundu

Project : MEP & Civil construction of Spherical Tank 2x300 Ton LPG MunduClient : PT Patra Badak Arun SolusiLocation : Indramayu, West JavaYears : 2015 – 2016

OverviewPT. WIKA Rekon is specialized in construction and fabrication of exclusive Spherical tank and Pipe lines required for Oil & Gas industries. This project was held on 2015–2016 in Indramayu, West Java. WIKA REKON as subcontractor for PT. Pertamina’s sub-sidiary namely PT. Patra Badak Arun Solusi.

WIKA Rekon works for Erection, Mechanical Electrical Plumbing and civil construction for Spherical Tank with capacity 2 x 300 Ton.

Services

WIKA Rekon is already accustomed on working of exclusive Steel Tanks, Fixed Roof Tanks, Floating Roof Tanks, and pipe lines required for Oil & Gas industries, our services including:

• Civil Construction;• Assembly, Erection and Alignment of Equipment;• Tank and piping installation;• Quality Control;• Commissioning.

TinjauanWIKA Rekon berspesialisasi dalam konstruksi dan fabrikasi tangki spherical eksklusif dan jalur pipa yang dibutuhkan untuk industri minyak & gas. Proyek ini dilaksanakan pada tahun 2015 - 2016 di Indramayu, Jawa Barat. WIKA REKON sebagai subkontraktor untuk anak perusahaan PT Pertamina (Persero) yaitu PT. Patra Badak Arun Solusi.

WIKA Rekon mengerjakan Erection, Mekanikal, Elektrikal, Plumbing dan konstruksi sipil untuk tangki Spherical dengan kapasitas 2 x 300 Ton.

JasaWIKA Rekon sudah terbiasa mengerjakan tangki baja eksklusif, Fixed Roof Tank, Floating Roof Tank, dan jalur Pipa yang dibutuhkan untuk industri oil & gas, layanan kami meliputi:

• Konstruksi Sipil;• Perakitan, Pemasangan dan Penjajaran Peralatan;• Pemasangan tangki dan perpipaan;• Kontrol kualitas;• Commisioning.

MEP

Page 20: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

PROJECT HIGHLIGHT Wet Sulfur Acid (WSA)

Project : Contruction Works of New DN 800 RAW Water Pipe Line Client : PT South Pacific ViscoseLocation : Purwakarta, West JavaYears : 2009 – 2010

Overview

Erection pipe dn 800 RAW project was held on Purwakarta, West Java. This project was become one of our milestone project on rayon & textile industry with contract value IDR 39,6 Billion.

WIKA Rekon works for assembly, erection, alignment and commissioning for pipes with a diameter of DN 800 on the spin bath line – 5 and spinning line – 4 belong to PT. South Pacific Viscose plant.

ServicesWIKA Rekon was appointed as Owner’s contractor for mechanical, electrical and plumbing on rayon & textile Industry, our services including : • Assembly, Erection and Alignment of

Equipment;• Quality Control.

MEP

TinjauanProyek pemasangan pipa dn 800 RAW dilaksanakan di Purwakarta, Jawa Barat. Proyek ini menjadi salah satu tonggak sejarah proyek kami di industri rayon & tekstil dengan nilai kontrak Rp 39,6 Miliar.

WIKA Rekon bekerja untuk merakit, pemasangan, alignment dan commissioning untuk pipa dengan diameter DN 800 pada spin bath line -5 dan spinning line - 4 milik Pabrik PT. South Pacific Viscose.

Jasa

WIKA Rekon ditunjuk pemilik proyek sebagai kontraktor untuk mekanikal, elektrikal dan perpipaan pada industri rayon & tekstil, jasa kami meliputi:• Perakitan, Pemasangan dan Penjajaran Peralatan;• Kontrol kualitas.

Page 21: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

PROJECT HIGHLIGHT MEP DEPP 3 x 18 MW Bali

Project : MEP DEPP 3 x 18 MW BaliClient : KSO Wijaya Karya (Persero) Tbk Merlindo Pandu KencanaLocation : Pesanggaran, BaliYears : 2012 - 2017

MEP

OverviewDEPP 3 x 18 MW is located in the Pesang-garan Sector under PLN region XI, Since 1995, it became part of PT Indonesia Power and is now called Bali Generation Business Unit. addition of the DEPP 3 x 18 MW Bali 200 to the grid has helped govern-ment improving significantly the reliability of electricity supply to Bali in an economical way.

This DEPP 3 x 18 MW Bali was built by KSO Wijaya Karya (Persero) Tbk, Merlindo Pandu Kencana in 2010 with engine MAN: Diesel 18V48/60 – France, using MFO Fuel, with 85% Capacity Factor contract and Build–operate–transfer (BOT) form of project delivery method.

ServicesWIKA Rekon was appointed for operation & maintenance with with our production and services, such as: • Procurement MEP; • Assembly, Erection and Alignment of

Mechanical, Electrical and Instrumen-tation;

• Quality Control; • Commissioning.

TinjauanDEPP 3 x 18 MW berlokasi di Sektor Pesang-garan di bawah wilayah PLN wilayah XI, Sejak tahun 1995 menjadi bagian dari PT Indonesia Power dan sekarang disebut Unit Bisnis Pembangkit Bali. Penambahan DEPP 3 x 18 MW Bali 200 ke jaringan telah membantu Pemerintah meningkatkan secara signifikan keandalan pasokan listrik ke Bali dengan cara yang ekonomis.

DEPP 3 x 18 MW Bali ini dibangun oleh KSO Wijaya Karya (Persero) Tbk, Merlindo Pandu Kencana pada tahun 2010 dengan mesin MAN: Diesel 18V48/60-Perancis, mengguna-kan MFO Fuel, dengan faktor kontrak Kapasitas 85% dan metode proyek Build–Operate–Transfer (BOT).

JasaWIKA Rekon ditunjuk untuk operasi & pemeliharaan dengan produksi dan layanan kami, seperti:• Pengadaan MEP;• Perakitan, Pemasangan dan Penjajaran

mekanikal, elektrikal dan instrumentasi;• Kontrol kualitas;• Commisioning.

Page 22: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

PROJECT HIGHLIGHT MEP Package IV SUMBAWA 50 MWProject : MEP PACKAGE IV SUMBAWA 50 MWClient : PT. Wijaya Karya (Persero) TbkLocation : Sumbawa Island, West Nusa TenggaraYears : 2018

MEP

OverviewSumbawa 50 MW Fixed Type Gas Engine Power Plant which is owned by PLN and WIKA as main contractor, appointed WIKA Rekon as sub-contractor in mechanical, electrical and steel structure erection on this project.

This project was held in January 2018 till December 2018 in Sumbawa Island, West Nusa Tenggara. With additional works specifically Mobilization & Demobilization, WWTP & BWRO Installation, Radiography Test and Etc.

Services

WIKA Rekon was appointed as MEP contractor with with our production and services, such as : • Steel Structure Construction; • Mechanical and Electrical Erection; • Piping and Instrument Erection; • Quality Control;• Commisioning.

TinjauanPembangkit Listrik Tenaga Mesin Gas Fixed Type Sumbawa 50 MW milik PLN dan WIKA sebagai kontraktor utama, menunjuk WIKA Rekon sebagai subkontraktor dalam pem-bangunan mekanik, listrik dan struktur baja pada proyek ini.

Proyek ini dilaksanakan pada Januari 2018 hingga Desember 2018 di Pulau Sumbawa, Nusa Tenggara Barat. Dengan pekerjaan tambahan khusus Mobilization & Demobiliza-tion, Instalasi WWTP & BWRO, Uji Radiografi dan lain-lain.

JasaWIKA Rekon ditunjuk sebagai kontraktor MEP dengan produksi dan layanan kami, seperti: • Konstruksi Struktur Baja;• Pemasangan Mekanikal dan Elektrikal;• Pemasangan Pipa dan Instrumen;• Kontrol kualitas;• Commisioning.

.

Page 23: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

MEPPROJECT HIGHLIGHT Kualanamu Airport Project : Installation of Piping, Kualanamu Aviation Fuel Supply Facilities (Airside Facility) Construction Client : PT Wijaya Karya, Tbk Dept Utility Location : Kualanamu, Medan Years : 2009

JasaWIKA Rekon ditunjuk untuk proyek MEP, seperti:• Pekerjaan Perpipaan.

Services

WIKA Rekon was appointed for MEP project, such as: • Piping Works.

TinjauanBandara Udara Internasional Kuala-namu melayani Kota Medan, Sumatra Utara. Bandara ini terletak di Kabupaten Deli Serdang, 23 km arah timur dari pusat kota Medan.

Bandara ini adalah bandara terbesar ketiga di Indonesia. Lokasi bandara ini merupakan bekas areal perkebunan PT Perkebunan Nusantara II Tanjung Morawa yang terletak di Beringin, Deli Serdang, Sumatra Utara. Pembangunan bandara ini merupakan bagian dari MP3EI, untuk menggantikan Bandar Udara Internasional Polonia yang telah berusia lebih dari 85 tahun. Bandara ini mulai beroperasi sejak 25 Juli 2013.

OverviewKualanamu International Airport serves Medan City, North Sumatra. The airport is located in Deli Serdang Regency, 23 km east of the city center of Medan.

This airport is the third largest airport in Indonesia. The location of this airport is a former plantation area of PT Perkebunan Nusantara II Tanjung Morawa which is located in Beringin, Deli Serdang, North Sumatra. This airport construction is part of MP3EI, to replace Polonia International Airport which is more than 85 years old. This airport began operating since July 25, 2013.

Page 24: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

PROJECT HIGHLIGHT Sultan Hasanuddin AirportProject : Design & Build Development of Sultan

Hasanuddin Airport Stage 1 - Paket 1Client : PT. Angkasa Pura I (Persero)Location : Maros, Makassar, South SulawesiYears : 2019

MEP

OverviewSultan Hasanuddin International Airport has Operated a new Apron, newest runway and 1 taxiway. The extension of the second phase runway from 3,100 meters to 3,500 meters was carried out in early 2012.

Currently, Sultan Hasanuddin International Airport, Makassar is expanded from initially 6 gates to 12 gates which are targeted to be completed in October 2021.

Services

WIKA Rekon was appointed as MEP contractor with with our production and services, such as : • Plumbing; • Hydrant Installation; • Cable Feeder Installation.

TinjauanBandar Udara Internasional Sultan Hasanuddin sudah Mengoperasikan Apron baru, landas pacu terbaru serta 1 buah taxiway. Perpanjangan landasan tahap 2 dari 3,100 meter menjadi 3,500 meter dilaksanakan awal 2012.

Saat ini, Bandara Internasional Sultan Hasanuddin, Makassar diperluas dari awalnya hanya memiliki 6 gate menjadi 12 gate yang ditargetkan rampung pada bulan Oktober 2021 mendatang.

JasaWIKA Rekon ditunjuk sebagai kontraktor MEP dengan produksi dan layanan kami, seperti: • Plumbing;• Instalasi Hydrant;• Instalasi Kabel Feeder. .

Page 25: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

EPCC CONVEYOR SYSTEM SURALAYA POWER PLANT

Page 26: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

EPCCPROJECT HIGHLIGHT EPCC Conveyor System in DOCK-2 SURALAYA

Project : EPCC CONVEYOR SYSTEM in DOCK-2 SURALAYA Client : PT. Indonesia Power Location : Cilegon, Banten Province Years : 2016

Tinjauan

Sistem conveyor adalah suatu peralatan penanganan yang memindahkan material dari satu lokasi ke lokasi lain, dalam hal ini memindahkan Batubara sebagai Bahan Bakar CFPP dari dermaga ke tempat penyim-panan Batubara atau bunker Batubara.

Sistem Konveyor ini dibangun dengan panjang sekitar 400 meter, dengan tujuan sebagai jalur cadangan untuk mengirimkan Batubara dari jetty dock-2 ke penyimpanan Batubara. Sistem Konveyor ini terletak di pembangkit listrik Suralaya di bawah PT Indonesia Power, Pembangkit ini memiliki kapasitas pembangkit maksimum 4.025 megawatt.

JasaWIKA Rekon ditunjuk sebagai Kontraktor EPCC dengan jangkauan layanan antara lain:• Pekerjaan Pendahuluan;• Desain teknik;• Pengadaan;• Konstruksi;• Pra commissioning;• Commisioning.

OverviewConveyor system is a handling equipment that moves materials from one location to another, in this occasion moves coal as a CFPP’s Fuel from jetty to coal storage or coal bunker.

This Conveyor System was built with full-length around 400 Meter, with objective of being a backup route for transmit coal from jetty dock-2 to coal storage. This Conveyor System is located in the Suralaya Power Station under PT Indonesia Power, The station has a maximum generating capacity of 4,025 megawatt.

ServicesWIKA Rekon was appointed as EPCC Contractor with the range of services including: • Preliminary Works; • Engineering Design;• Procurement; • Construction; • Pre-commissioning; • Commissioning.

Page 27: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

PROJECT HIGHLIGHT PLTD CPO 5 MW Belitung Project : Belitung 5 MW DEPP CPO Power Plant Client : Kementerian ESDM RI Location : Belitung Sub Province, Bangka Belitung Province Years : 2017 - 2019

EPCC

OverviewThe construction of the CPO DEPP originates from the 2016 APBN Ministry of Energy and Mineral Resources budget, with total assets of IDR 96,351,207,886. The Government hopes that the assets that have been handed over will increase benefits for the community and increase regional income.

WIKA Rekon’s contribution to renewable energy through CPO DEPP power plant provides substitution which 100% CPO needed is 11.25 million liters/year and can substitute for the use of Manggar PLTD fuel by 7.7 million liters/year. The existence of PLTBn also provides added value by absorbing up to 1,281 people (on-farm & off-farm).

ServicesWIKA Rekon is proudly become the renewable energy that is appointed as Owner’s contractor, with the wide EPC range of services including : • Mass Balance Process Design; • Civil Construction; • Purchase, erection and installation of mechanical, electrical, piping and instrumentation;• Commissioning.

TinjauanPembangunan CPO DEPP berasal dari anggaran APBN Kementerian ESDM tahun 2016, dengan total aset sebesar Rp. 96.351.207.886. Pemerintah berharap aset yang telah diserahkan dapat meningkat-kan manfaat bagi masyarakat dan menambah pendapatan daerah.

Kontribusi WIKA Rekon terhadap energi baru terbarukan melalui PLTD CPO DEPP memberi-kan substitusi dimana 100% kebutuhan CPO sebesar 11,25 juta liter/tahun dan dapat meng-gantikan penggunaan bahan bakar PLTD Manggar sebesar 7,7 juta liter/tahun. Ke-beradaan PLTBn juga memberikan nilai tambah dengan menyerap hingga 1.281 orang (on farm & off-farm).

JasaWIKA Rekon dengan bangga menjadi energi terbarukan yang ditunjuk sebagai kontrak-tor Pemilik, dengan berbagai layanan EPC termasuk:• Desain Proses Mass Balance;• Konstruksi Sipil;• Pembelian, pemasangan dan pemasangan mekanikal, elektrikal, perpipaan dan instrumentasi;• Commisioning.

Page 28: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

EPCCPROJECT HIGHLIGHT EPCC PLTMH ILAGA (2 x 350 kW)

Project : Ilaga 2 x 350 kW Mini Hydro Power Plant Client : Kementerian ESDM RI Location : Puncak District, Papua Province Years : 2018 - 2020

Tinjauan

Pembangunan PLTMH Ilaga menggunakan skema multi years dengan nilai kontrak Rp 99 miliar. Pembangkit listrik energi baru terbarukan berbasis energi bersih ini baru melistriki 600 rumah tangga (KK) dari aliran air 2 x 800 liter/detik dengan menggunakan 2 unit turbin.

Kontribusi WIKA Rekon terhadap energi baru terbarukan melalui PLTMH memberikan kesempatan kepada warga di Papua untuk meningkatkan kualitas hidup dengan meman-faatkan potensi energi baru terbarukan lokal sekaligus membuktikan WIKA Rekon bergerak di bidang energi terbarukan EPCC.

JasaWIKA Rekon dengan bangga menjadi energi baru terbarukan yang ditunjuk sebagai kontraktor, dengan berbagai layanan EPCC termasuk:• Konstruksi Sipil dan Hidromekanikal;• Pembelian, Erection dan Pemasangan MEP;• Kontrol kualitas;• Commisioning.

OverviewThe construction of the Ilaga MHPP uses a multi years scheme with a contract value of IDR 99 billion. The clean energy-based Renewable power plant has only electrified 600 households (KK) from 2 x 800 liters/sec-ond water flow using 2 turbine units.

WIKA Rekon’s contribution to renewable energy through PLTMH provides an opportu-nity for residents in Papua to improve their quality of life by utilizing the potential of local renewable energy as well as proving WIKA Rekon to move in the EPCC Renewable energy field.

ServicesWIKA Rekon is proudly become the renewable energy that is appointed as Owner’s contractor, with the wide EPCC range of services including: • Civil and Hydromechanical Construction; • Purchase, Erection and Installation MEP; • Quality Control; • Commissioning.

Page 29: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

EPCCPROJECT HIGHLIGHT EPCC GEPP 15 MW & 20 MW Package 3 PLN Project : EPCC 2 x 15 MW and 3 x 20 MW GEPP Package 3 PLN Client : KSO WIKA - WRK Location : Tanjung Selor, Langgur, Seram, Marauke and Biak Years : 2019 - 2024

Tinjauan

GEPP 15 MW dan 20 MW Paket 3 dimiliki oleh PLN dan dibangun oleh KSO WIKA - WRK pada tahun 2017. Proyek ini berlokasi di 5 lokasi berbeda di Indonesia Barat, yaitu:

• GEPP 15 MW Tanjung Selor • GEPP 15 MW Langgur • GEPP 15 MW Seram • GEPP 20 MW Marauke • GEPP 20 MW Biak

Dengan tipe mesin: MAN L51 / 60 DF 9L dan 12 V, GEPP Paket 3 memegang peranan yang sangat penting dalam menunjang kehandalan sistem kelistrikan Papua dan Pulau Maluku.

JasaWIKA Rekon dengan bangga menjadi Kontraktor EPCC yang ditunjuk Pemilik Proyek sebagai Kontraktor, dengan berbagai layanan EPC antara lain:• Desain Proses Mass Balance;• Konstruksi Sipil;• Pembelian, erection dan pemasangan mekanikal, elektrikal, perpipaan dan instrumentasi;• Commisioning.

OverviewGEPP 15 MW and 20 MW Package 3 is owned by PLN and build by JO WIKA-WRK on 2017. This project located on 5 different location across West Indonesia, namely:

• GEPP 15 MW Tanjung Selor • GEPP 15 MW Langgur • GEPP 15 MW Seram • GEPP 20 MW Marauke • GEPP 20 MW Biak With Engine type : MAN L51/60 DF 9L and 12 V, GEPP Package 3 plays a very important role in supporting the reability of Papua and Maluku Island electricity system.

ServicesWIKA Rekon is proudly become the EPCC Contractor that is appointed as Owner’s contractor, with EPC range of services including: • Mass Balance Process Design;• Civil Construction; • Purchase, erection and installation of

mechanical, electrical, piping and instrumentation;

• Commissioning.

Page 30: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

EPCCPROJECT HIGHLIGHT 1500 TPD BIO DIESEL FACTORY DEVELOPMENT PROJECT Project : EPCC 1500 TPD BIODIESEL FACTORY and PRE-TREATMENT Client : PT. Jhonlin Agro Raya Location : Batu Ampar Village, South Kalimantan Years : 2020 - Present

Tinjauan

Biodiesel adalah bahan bakar diesel terbarukan yang dapat dibakar di mesin diesel yang tidak dimodifikasi pada konsentrasi berapa pun. B100 adalah 100% biodiesel dan dapat di-gunakan pada mesin diesel pada suhu yang lebih hangat. Proyek ini telah dimulai dari tanggal 26 September 2020 hingga saat ini dengan nilai Kontrak Rp 619 Miliar.

Kontribusi klien kami, PT. Jhonlin Agro Raya untuk bahan bakar terbarukan melalui bio-diesel atau biofuel memberikan peluang untuk solusi energi pilihan yang dapat diakses dan alternatif untuk minyak bumi. Dengan meningkatnya konsumsi biodiesel dalam negeri, proyek ini diharapkan dapat menjadi jawaban untuk mendongkrak kapasitas industri biodiesel dalam sistem kelistrikan Indonesia.

JasaWIKA Rekon ditunjuk sebagai Kontraktor EPCC dengan jangkauan layanan antara lain:• Pekerjaan Pendahuluan;• Desain teknik;• Pengadaan;• Konstruksi;• Pra commissioning;• Commisioning;

OverviewBiodiesel is a renewable diesel fuel that can be burned in any unmodified diesel engine at any concentration. B100 is 100% biodiesel and can be used in diesel engines in warmer temperatures. this project has been started from Sept 26th, 2020 until present with IDR 619 Billion contract value.

Our client, PT. Jhonlin Agro Raya contribu-tion to renewable fuel through biodiesel or biofuel provides an opportunity for accessible option energy solution and alternative to petroleum. With the increase in domestic biodiesel consumption, this project is expected to be the answer to boost the capacity of the biodiesel industry in Indonesia electricity system.

ServicesWIKA Rekon was appointed as EPCC Contractor with the range of services including: • Preliminary Works; • Engineering Design; • Procurement; • Construction; • Pre-commissioning; • Commissioning;

Page 31: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

PLTG SENIPAH 2 x 41 MW

Page 32: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

PROJECT HIGHLIGHT O&M GTPP 2 x 41 MW Senipah Project : Operation & Maintenance GTPP 2 X 41 MW Senipah Client : PT Kartanegara Energi Perkasa Location : Senipah, East Kalimantan Years : 2017 - Present

O&M

Tinjauan

GEPP 15 MW dan 20 MW Paket 3 dimiliki Produsen listrik swasta (Independent Power Producer/IPP) milik Kartanegara Energi yang sebelumnya telah mengoperasikan PLTG Senipah berkapasitas 82 MW (siklus sederhana) sejak 2015. Pada 2017, Kartanegara Energi melakukan ekspansi dengan kapasitas 35 MW (siklus gabungan).

Pembangkit Listrik Tenaga Gas Turbine 60 MW unit 1 dan 2 ini telah beroperasi secara komersial (COD) sejak tahun 2015 dengan tipe mesin: General Electric LM 6000 PG.

JasaWIKA Rekon ditunjuk untuk operasi & peme-liharaan dengan produksi dan layanan kami, seperti: • Jasa Ketenagakerjaan;• Pemecahan Masalah dan Perbaikan;• Sistem penjadwalan, laporan dan pemeliharaan.

OverviewAn private power producer (Independent Power Producer/IPP) owned by Kartanegara Energi which previously had operated the Senipah PLTG with a capacity of 82 MW (simple cycle) since 2015. In 2017, Kartanegara Energi expanded with a capacity of 35 MW (combined cycle).

This 60 MW Gas Turbine Power Plant for unit 1 and 2 has been commercially operated (COD) since 2015 with engine type : General Electric LM 6000 PG.

ServicesWIKA Rekon was appointed for operation & maintenance with our production and services, such as:• Man Power Services; • Troubleshooting and Repairing; • Schedulling, report and maintenance

system.

Page 33: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

PROJECT HIGHLIGHT O&M GEPP 15 MW & 20 MWPackage 3 PLN Project : O&M 2 x 15 MW and 3 x 20 MW GEPP Package 3 PLN Client : KSO WIKA - WRK Location : Tanjung Selor, Langgur, Seram, Marauke and Biak Years : 2019 - 2024

O&M

Tinjauan

GEPP 15 MW dan 20 MW Paket 3 dimiliki oleh PLN dan dibangun oleh KSO WIKA - WRK pada tahun 2017. Proyek tersebut berlokasi di 5 lokasi berbeda di seluruh wilayah Indonesia bagian timur, yaitu:

• GEPP 15 MW Tanjung Selor • GEPP 15 MW Langgur • GEPP 15 MW Seram • GEPP 20 MW Marauke • GEPP 20 MW Biak

Dengan tipe Mesin: MAN L51 / 60 DF 9L dan 12 V, GEPP Paket 3 memegang peranan yang sangat penting dalam mendukung kehandalan sistem kelistrikan pulau Papua dan Maluku.

JasaWIKA Rekon dengan bangga menjadi kontraktor jasa O&M selama 5 tahun dan sebagai paket dengan cakupan layanan EPCC termasuk:• Operasi dan Pemeliharaan;• LTSA.

OverviewGEPP 15 MW and 20 MW Package 3 is owned by PLN and build by KSO WIKA – WRK on 2017. The project located on 5 different location across East Indonesia, namely :

• GEPP 15 MW Tanjung Selor • GEPP 15 MW Langgur • GEPP 15 MW Seram • GEPP 20 MW Marauke • GEPP 20 MW Biak

With Engine type : MAN L51/60 DF 9L and 12 V, GEPP Package 3 plays a very important role in supporting the reability of Papua and Maluku island electricity system.

ServicesWIKA Rekon is proudly become the O&M services contractor for 5 years and as the package of EPCC range of services including: • Operation and Maintenance; • LTSA.

Page 34: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

PROJECT HIGHLIGHT MEP O&M Terminal 3 Soetta Project : MEP O&M Terminal 3 Soekarno-Hatta AirportClient : PT Angkasa Pura II Location : Tangerang City, Banten Years : 2017 - 2020

O&M

Tinjauan

Divisi Operasi & Pemeliharaan WIKA Rekon telah mengembangkan usahanya dengan memasuki sektor non pembangkit listrik. MEP O&M Terminal 3 Bandara Soetta merupakan hasil kesepakatan konsorsium antara WIKA Rekon dan Angkasa Pura Solusi (APS) pada tahun 2016.

Terdapat total 1641 Unit Alat Mekanikal Elek-trikal/Utilitas pada terminal 3 Bandara Soetta baik dari sisi Udara maupun sisi Darat.

JasaWIKA Rekon sebagai anggota konsorsium telah melakukan pemeliharaan dan peng-operasian MEP sejak 1 Juni 2017. Adapun peralatan yang akan dipelihara adalah sebagai berikut:

• Garbarata• Eskalator dan Travelator• Pemadam Kebakaran• AHU• Menara pendingin• Pendingin• WTP, STP, dll.

OverviewWIKA Rekon Operation & Maintenance Division has been expand his business by entering non power plant sector. MEP O&M Terminal 3 Soetta Airport was the product of consortium agreement between WIKA Rekon and Angkasa Pura Solusi (APS) in 2016.

There are total 1641 Unit Mechanical-Elec-trical equipments/Utilities on terminal 3 Soetta Airport both from Air side and Land side.

ServicesWIKA Rekon as a consortium member has been doing MEP maintenance and operation since June 1, 2017. As for the equipment to be maintained are as follows :

• Garbarata • Escalator and Travelator • Fire Supression • AHU • Cooling Tower • Chiller • WTP, STP and etc

Page 35: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

QUALITY DRIVE OUR BUSINESS QSHE

Budaya Kualitas, Keselamatan, Kesehatan dan Lingkungan (QSHE) WIKA REKON didorong oleh pemahaman dan tindakan kami sebagai organisasi yang digerakkan oleh proses untuk memberikan proses ketangkasan, kepedulian terhadap karyawan, dan keunggulan operasional. Kekuatan dan daya tahan korporasi dari waktu ke waktu dapat diuji dengan cara-cara berikut:• Menerapkan sistem manajemen mutu sesuai

dengan ISO 9001: 2015;• Menerapkan sistem pengelolaan SHE yang

sesuai sesuai dengan OHSAS 18001:2007 dan peraturan yang berlaku;

• Menerapkan sistem manajemen lingkungan sesuai dengan ISO 4001:2015;

• Penerapan upaya QSHE perbaikan terus menerus oleh seluruh karyawan.

WIKA REKON’s Quality, Safety, Health and Environment (QSHE) culture is driven by our understanding and action as a process-driven organization to deliver agility process, caring people and operational excellence. The strength and durability of the corporation time to time can be tested in the following ways: • Implementing a quality management system

in accordance with ISO 9001:2015; • Implementing an appropriate SHE manage-

ment system in accordance with OHSAS 18001:2007 and applicable regulations;

• Implementing an environmental management system in accordance with ISO 4001:2015;

• Implementation of continuous improvement QSHE efforts by all employees.

Page 36: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

CSR CORPORATE SOCIAL RESPONSIBILITY

Tanggung Jawab Sosial Perusahaan bukan hanya strategi membangun citra, tetapi juga upaya yang dilakukan setiap hari untuk mem-perbaiki kondisi hidup dan kerja, meningkat-kan kesadaran karyawan dan pemangku kepentingan, serta mendorong nilai dan pen-dekatan positif di berbagai bidang penting bagi Perusahaan. citra merek dan pengembangan bisnis. Di WIKA REKON, kami menerapkan CSR di bidang-bidang berikut:

• Kolaborasi dengan klien pada acara amal kemanusiaan di lingkungan proyek;

• Program Penanaman Pohon;• Memberikan bantuan kepada anak yatim;• Menawarkan beasiswa dan program

magang bagi mahasiswa.

Corporate Social Responsibility is not only an-image-building strategy, but also an effort made every day to improve the living and working conditions, increase the awareness of employee’s and stakeholders, as well as to promote positive values and approaches in different important areas for corporation brand image and business development. At WIKA REKON, we implement CSR in the following areas:

• Collaboration with client on the humanity charity event at project neighborhood;

• Planting Tree Programs; • Provide aid to the orphans; • Offering scholarship and internship program

for college students.

“Success is not the key to happiness. Happiness is the key to success. If you love

what you are doing, you will be successful.” – Albert Schweitzer

Page 37: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

State-Owned Enterprises

National Companies

Multinational Companies

Page 38: TotalSolution for Sustainability - WIKA Rekon...Mechanical, Electrical dan Steel Structure Construction for Diesel Engine 3x16V34df PT PP (Persero), Tbk PT PP (Persero), Tbk Ternate

PT WIJAYA KARYA REKAYASA KONSTRUKSITamansari Hive Office, 5th FloorJl. D.I. Panjaitan Kav.2 Jakarta 13340, IndonesiaPhone : (+6221) 2286 4446-8 Fax : (+6221) 2286 4445Email : [email protected] Website : www.wikarekon.co.id

Tamansari Hive Office, 5th FloorJl. D.I. Panjaitan Kav.2, Jakarta 13340, Indonesia.Phone : +62 21 2286 4446 - 8 Fax : +62 21 2286 [email protected] www.wikarekon.co.id