    total station manual under thePrepared by c-4 section guidance of 2k10 batch DR. MAHESH PAL

    Starting the Survey Using /TS02/TS06 New

    FOR SURVEYING WHEN THE INSTRUMENT IS SETUP FIRST TIME

    1. Switch on the instrument.

    2. Press function key(FNC) for Laser Beam for centering and leveling. Press FNC F1 for Leveling & PlummetThe intensity of laser can be altered by using up or down arrow keys.

    Do the centering with the help of laser Do the approximate leveling with the help of tripod legs so that the bubble come in the circle& then level accurately with the help of screws as shown in screen.Centering will be slightly disturbed due to levelling , the instrument is moved from its basedto center it again. After proper centering it is clamped.

  • 7/28/2019 Total Station Manual

    2/24

    total station manual under thePrepared by c-4 section guidance of 2k10 batch DR. MAHESH PAL

    3. Press MENU .4. Press (PROGRAMS) .

    5. Press F1 (STATION SETUP) .

    6. Press F1 (Set Job) .

    7. Press F1 (NEW) to give a new job name.

  • 7/28/2019 Total Station Manual

    3/24

    total station manual under thePrepared by c-4 section guidance of 2k10 batch DR. MAHESH PAL

    8. To write the name of the job. Press F1 (INPUT) and then using the Function keys F1 to F4give the name and Then Press Enter Key.

    9. Press F4 (OK)

    10. Press F2 (Set Accuracy limit)

    11. Press F4 (OK) OR you may give some accuracy limit

  • 7/28/2019 Total Station Manual

    4/24

    total station manual under thePrepared by c-4 section guidance of 2k10 batch DR. MAHESH PAL

    12. Press F4 (OK)

    13. Press F4 (OK)

    14. Now select the method of orientation initially we dont have any back-sight point so weuse the method of orientation with angle .Press F3 New station

    15. Now give the Station Point ID and give the Easting, Northing & Height with the help of F1to F4 (Functional Keys ) and press F4 (OK)

  • 7/28/2019 Total Station Manual

    5/24

    total station manual under thePrepared by c-4 section guidance of 2k10 batch DR. MAHESH PAL

    16. Now bring the cursor on instrument height hi and measure the instrument height

    And give the height. Press F4 OK

    17. Now give the back side point ID or you can select from list if back side ID is stored inmemory and you can also give the new number of point ID by pressing New F3 and give thecoordinate. Suppose your backside point ID is 2

    18. Press Enter

    19. Press F4

  • 7/28/2019 Total Station Manual

    6/24

    total station manual under thePrepared by c-4 section guidance of 2k10 batch DR. MAHESH PAL

    20. Press F3 (ENH)

    21. Give the Easting, Northing and Height of back side point ID. And press F4 OK

    22. Now give reflector height for prism say (1.300m) and sight the prism press DIST you cansee your error in then press REC.

    23. Press F4 Compute

  • 7/28/2019 Total Station Manual

    7/24

    total station manual under thePrepared by c-4 section guidance of 2k10 batch DR. MAHESH PAL

    24. Press F4 SET now your station and orientation has been set.Afterthat you can do anyProgram suppose you are doing surveying1. In main menu bring the cursor to program icon and press Enter key.

    2. Now press F2 for surveying

    3. Press F1 (Set Job).

  • 7/28/2019 Total Station Manual

    8/24

    total station manual under thePrepared by c-4 section guidance of 2k10 batch DR. MAHESH PAL

    4. Press F1 NEW.

    5. Give the Job Name with the help of F1 to F4 Functional key and press F4 OK

    6. If you have set station setup already then Press F4 Directly Now your survey is started.By giving Pt ID and hr you can collect data.

  • 7/28/2019 Total Station Manual

    9/24

    total station manual under thePrepared by c-4 section guidance of 2k10 batch DR. MAHESH PAL

    At last you can start any program in Program menu .The station setup is same for allprograms.

    3.STAKEOUT1.In main menu bring the cursor in program and press Enter key

    2. Press F3

  • 7/28/2019 Total Station Manual

    10/24

    total station manual under thePrepared by c-4 section guidance of 2k10 batch DR. MAHESH PAL

    3. Press F1 set job

    4. Press F1 New and give job name or chose the job from memory and press F1 ok

    5. Press F4 ok

    If your station setup is already done then press F4 start

  • 7/28/2019 Total Station Manual

    11/24

    total station manual under thePrepared by c-4 section guidance of 2k10 batch DR. MAHESH PAL

    After that select the point ID from memory it will indicate angle & distance make the anglezero with the help slow motion key.

    If mark the new points press F4 arrow key until ENH is appear

    Press F2 (ENH)

    Give the Pt ID and give the Easting, Northing, Height. And press F4 OK

  • 7/28/2019 Total Station Manual

    12/24

    total station manual under thePrepared by c-4 section guidance of 2k10 batch DR. MAHESH PAL

    Now it is same as before.

    STEPS FOR OPERATING RESECTION PROGRAM

    The Program Free Station is used in places where you have the location of two points on theground and there coordinates but you are keeping the total station at a third place where thecoordinates of the station are not known.

    1. Press MENU.2. Press F1 (Programs).

    3. Press F1 (Resection).

  • 7/28/2019 Total Station Manual

    13/24

    total station manual under thePrepared by c-4 section guidance of 2k10 batch DR. MAHESH PAL

    4. Press F1 (Set Job).

    5. Enter the Name of the Job by Pressing F1 (INPUT) and the using the Function keysF1 to F4; enter the name of the job.

    6. Press F4 (Start).

    7. In front of the method select Resection with the help of navigation key and press F4ok

  • 7/28/2019 Total Station Manual

    14/24

    total station manual under thePrepared by c-4 section guidance of 2k10 batch DR. MAHESH PAL

    8. Now we can give the coordinate of the Pt ID by pressing new F3 key9. In front of the Point ID enter the number of the First Point where the Prism is kept.

    10. In front of hr (Height of the Reflector) enter the height to which the prism pole isopened.

    11. Press F3 (OK).12. Press F4 (ENH).13. Enter the Easting, Northing and Elevation of this first point.

  • 7/28/2019 Total Station Manual

    15/24

    total station manual under thePrepared by c-4 section guidance of 2k10 batch DR. MAHESH PAL

    14. Press F4 (OK).15. Now Sight this point and Press F3 (ALL).

    16. Press F2 (Next Pt).

    17. In front of Pt ID Enter the number of the second point whose location coordinatesyou know.

    18. Press F3 (OK).19. Press F4 (ENH).20. Enter the East, North and Elevation of the next point.21. Press F4 (OK).

  • 7/28/2019 Total Station Manual

    16/24

    total station manual under thePrepared by c-4 section guidance of 2k10 batch DR. MAHESH PAL

    22. Now Sight the point and press F3 (ALL).23. Press F1 (COMPUTE).24. The coordinates of the Instrument station will be displayed to you.

    Steps for Operating the Reference Line.The Reference line Program is used to establish points in reference to a base line byusing the line and offset values from the first point of the base line,

    1. Press MENU.2. Press F1 (Programs).

    3. Press F4 (Reference Element)

    4. Now set the station and orientation by using the steps given already in station setupmethod program.

    5. Press F4 (Start).

  • 7/28/2019 Total Station Manual

    17/24

    total station manual under thePrepared by c-4 section guidance of 2k10 batch DR. MAHESH PAL

    6. Now put the prism on the first point of the base line.7. Press F3 (ALL).

    8. In front of the point2 enter the number of the last point of the base line.9. Now sight the point and Press F3 (ALL).

    10. Press F3 (StOut).

    11. Now enter the values of the offset and line with respect to the baseline first point.

  • 7/28/2019 Total Station Manual

    18/24

    total station manual under thePrepared by c-4 section guidance of 2k10 batch DR. MAHESH PAL

    Input center line Distance in front of Line

    Input Offset value if you want to input right side value than input 5.00 if you want to inputleft side value than input -5.00 in front of offset.

    12. Press F4 (OK).

    13. Now the rest process is same as the stake out process.

    Steps for Operating the Tie Distance Program.

  • 7/28/2019 Total Station Manual

    19/24

    total station manual under thePrepared by c-4 section guidance of 2k10 batch DR. MAHESH PAL

    The Tie Distance Program is used to find the horizontal distance between two pointseither by measurement in the field or if the coordinates of the points are present in thememory.

    1. Press MENU2. Program

    3. Press PAGE.

    4. Press F1 (Tie Distance).

    5. The First three steps will remain the same for your convenience,

    6. Press F4 (Start).

  • 7/28/2019 Total Station Manual

    20/24

  • 7/28/2019 Total Station Manual

    21/24

    total station manual under thePrepared by c-4 section guidance of 2k10 batch DR. MAHESH PAL

    When the coordinates of the points are already in the memory.

    1. In front of the point enter the number of the first point and Press F2 (FIND).2. If the Point is in the memory it will be found then press F4 (OK).3. In front of Point 2 Enter the number of the second point again Press F2 (FIND).4. Press F4 (OK).5. The results are displayed on the screen.

    Steps for Operating the Area Program.

    1. Press MENU.2. Press F1 (Programs).

    3. Press PAGE.

    4. Press F2 (Area).

  • 7/28/2019 Total Station Manual

    22/24

    total station manual under thePrepared by c-4 section guidance of 2k10 batch DR. MAHESH PAL

    5. The First three steps are the same.6. Press F4 (Start).

    The points whose area is to be found can be either in the memory or can be shot directlyin the field.

    7. In front of Point ID Enter the number of the first point Press F3 (ALL).

    8. Keep on sighting the point in a proper sequence until you have all the points onceyou have shot all the point for the enclosing area Press F2 (RESULTS) the resultsare displayed on the screen.

    The point whose area is to be found is already in the memory.

    9. In front of the point ID enter the number of the point, which forms the enclosed area.

    10. After entering the point number Press FIND.11. Press F4 (OK).12. Keep on repeating this procedure until you have all the point imported in the point

    and Press RESULT.13. The results will be displayed on the screen.

    REMOTE HEIGHT PROGRAM.

  • 7/28/2019 Total Station Manual

    23/24

    total station manual under thePrepared by c-4 section guidance of 2k10 batch DR. MAHESH PAL

    The Remote height program is used to find the elevation of the remote points where it ispossible to place the prism directly below the point the point whose remote elevation isto be found.1. Press MENU.2. Press F1 (Programs).

    3. Press PAGE.

    4. Press F3 (Remote Height).

    5. The first three steps will remain the same.

  • 7/28/2019 Total Station Manual

    24/24

    total station manual under thePrepared by c-4 section guidance of 2k10 batch DR. MAHESH PAL

    6. Now put the prism on the base point and Sight it and press F3 (ALL).

    7. Now move the telescope and focus the top point whose elevation is to be found.8. The height value will be displayed on the screen.