Total Maximum Daily Load (TMDL) Program Lake Jesup Basin Management Action Plan (BMAP) Environmental Protection Division September 1, 2009

Upload: morgan-vanessa-craig

Post on 29-Jan-2016

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Total Maximum Daily Load (TMDL) Program Lake Jesup Basin Management Action Plan (BMAP) Environmental Protection Division September 1, 2009

Total Maximum Daily Load (TMDL) Program

Lake Jesup Basin Management Action Plan (BMAP)

Environmental Protection Division

September 1, 2009

Page 2: Total Maximum Daily Load (TMDL) Program Lake Jesup Basin Management Action Plan (BMAP) Environmental Protection Division September 1, 2009

Presentation Outline

Jesup Status

Options

Action Items

Page 3: Total Maximum Daily Load (TMDL) Program Lake Jesup Basin Management Action Plan (BMAP) Environmental Protection Division September 1, 2009

Presentation Outline

Jesup Status Options Action Items

Page 4: Total Maximum Daily Load (TMDL) Program Lake Jesup Basin Management Action Plan (BMAP) Environmental Protection Division September 1, 2009

Group 1

Group 2

Group 3

Group 4

Group 5

Jesup Status

Basin Groups

Kissimmee River(Group 4)

Upper

St. Johns

River

(Group 3)

Ock

law

ah

a

Riv

er

(Gro

up 1

)

Jesup

Middle St. Johns River(Group 2)

Page 5: Total Maximum Daily Load (TMDL) Program Lake Jesup Basin Management Action Plan (BMAP) Environmental Protection Division September 1, 2009

There are five phases to the TMDL program:

Phase 1 - Initial monitoring Phase 2 – Verified listing Phase 3 - TMDL development Phase 4 - Basin Management Action

Plan (BMAP) – Current Jesup Status Phase 5 - Implementation

Jesup Status

Page 6: Total Maximum Daily Load (TMDL) Program Lake Jesup Basin Management Action Plan (BMAP) Environmental Protection Division September 1, 2009

Management Options

Data & Information

People

BMAP

Jesup Status

Implementation plan to achieve a TMDL

Refined source identification Allocations Management strategies Funding Define monitoring needs

What is a Basin Management Action Plan?

Page 7: Total Maximum Daily Load (TMDL) Program Lake Jesup Basin Management Action Plan (BMAP) Environmental Protection Division September 1, 2009

Jesup Status

Lake Jesup

Orange County portion

Jesup Basin

Seminole CountyOrange County

Lake Jesup

Page 8: Total Maximum Daily Load (TMDL) Program Lake Jesup Basin Management Action Plan (BMAP) Environmental Protection Division September 1, 2009

Jesup Status

Total Jesup Reductions Req. 18,748 lbs divided between 17 stakeholders over a 15 year period

First 5 years (2009-2014) 6,250 lbs

Page 9: Total Maximum Daily Load (TMDL) Program Lake Jesup Basin Management Action Plan (BMAP) Environmental Protection Division September 1, 2009

Jesup StatusOrange County Reductions 1,707 lbs

-over a 15yr period

First 5 years (2009-2014) 569 lbs

Projects Credited -228 lbs

Remaining reductions 341 lbs

Projects not currently credited -141 lbs

Requested corrected reductions 200 lbs

Page 10: Total Maximum Daily Load (TMDL) Program Lake Jesup Basin Management Action Plan (BMAP) Environmental Protection Division September 1, 2009

Concerns expressed in letter to FDEP:

141 lbs of 1980’s era ponds not receiving credit

Flexibility of Orange County resolving the remaining reductions needed

Jesup Status

Page 11: Total Maximum Daily Load (TMDL) Program Lake Jesup Basin Management Action Plan (BMAP) Environmental Protection Division September 1, 2009

Unknowns in BMAP that apply to OC:

Lake Attenuation Annexation Sewer Service Area Calculation of Septic Load Water Quality Flow Data Collection for

Discharge In-Lake Issues

Jesup Status

Page 12: Total Maximum Daily Load (TMDL) Program Lake Jesup Basin Management Action Plan (BMAP) Environmental Protection Division September 1, 2009

Presentation Outline

Jesup StatusJesup Status Options Action ItemsAction Items

Page 13: Total Maximum Daily Load (TMDL) Program Lake Jesup Basin Management Action Plan (BMAP) Environmental Protection Division September 1, 2009

Options

1. Insist FDEP give credit now for the 141 lbs reductions

2. Request a deferral of 141 lbs to the next 5 year cycle

Ensuring that all stakeholders will have their credited/non-credited BMPs reevaluated based on water quality.

Page 14: Total Maximum Daily Load (TMDL) Program Lake Jesup Basin Management Action Plan (BMAP) Environmental Protection Division September 1, 2009

Presentation Outline

Jesup StatusJesup Status OptionsOptions Action Items

Page 15: Total Maximum Daily Load (TMDL) Program Lake Jesup Basin Management Action Plan (BMAP) Environmental Protection Division September 1, 2009

Action Item

Approval for EPD Manager to relay to FDEP concerns of BCC regarding the Lake Jesup Basin Management Action Plan

Page 16: Total Maximum Daily Load (TMDL) Program Lake Jesup Basin Management Action Plan (BMAP) Environmental Protection Division September 1, 2009

Total Maximum Daily Load (TMDL) Program

Lake Jesup Basin Management Action Plan (BMAP)

Environmental Protection Division

September 1, 2009