tm&i 2010 VI.1

technology management & innovation

introduction to project management

(ii) project planning methods & tools

tm&i 2010 VI.2

TIME

MONEYRESOURCES

Project Culture

project

tm&i 2010 VI.3

TASK LIST

DELIVERABLES

OBJECTIVEevaluate a

new technology

written report and

presentation

review IP

analyse performance

determine manufacturing

compare with competition (SWOT)

make recommendation

prepare the report & presentation

Project Planning

plan your projects from

“the top down”

tm&i 2010 VI.4

ID Task Name

1 TM&I course 20092 Evaluate a New Technology3

4 Project Start5

6 Review IP15

16 Evaluate Performance (Data)17

18 Evaluate Manufacturing19

20 Compare with competition21

22 Make Recommendation23

24 Prepare Report & Presentation25

26 Presentation27

28 Project End

• compile task list• specify chronology (order in which tasks

occur)• assign task durations

• the sum of all sequential task

durations gives an estimate of the project duration (“end date”)

Tasks can be arranged in sequential steps (boxes), rather like a computer programme

This technique is known as a PERT chart

Each box is a task, and has a start date, finish date & duration

tm&i 2010 VI.5

Project Start

Milestone Date: Wed 02/ 12/ 09

I D: 4

Evaluate a New Technology

Start: 02/ 12/ 09 I D: 2

Finish: 28/ 12/ 09 Dur: 19 days

Comp: 0%

Project End

Milestone Date: Mon 28/ 12/ 09

I D: 28

Presentation

Start: 25/ 12/ 09 I D: 26

Finish: 28/ 12/ 09 Dur: 2 days

Res:

Evaluate Performance (Data)

Start: 14/ 12/ 09 I D: 16

Finish: 14/ 12/ 09 Dur: 1 day

Res:

Evaluate Manufacturing

Start: 15/ 12/ 09 I D: 18

Finish: 16/ 12/ 09 Dur: 2 days

Res:

Compare with competition

Start: 17/ 12/ 09 I D: 20

Finish: 18/ 12/ 09 Dur: 2 days

Res:

Make Recommendation

Start: 21/ 12/ 09 I D: 22

Finish: 22/ 12/ 09 Dur: 2 days

Res:

Prepare Report & Presentation

Start: 23/ 12/ 09 I D: 24

Finish: 24/ 12/ 09 Dur: 2 days

Res:

Review IP

Start: 02/ 12/ 09 I D: 6

Finish: 11/ 12/ 09 Dur: 8 days

Comp: 0%

TM&I course 2009

Milestone Date: Wed 02/ 12/ 09

I D: 1

tm&i 2010 VI.6

Project Start

Milestone Date: Wed 02/ 12/ 09

I D: 4

Evaluate a New Technology

Start: 02/ 12/ 09 I D: 2

Finish: 28/ 12/ 09 Dur: 19 days

Comp: 0%

define search keywords or IPC codes

Start: 02/ 12/ 09 I D: 7

Finish: 02/ 12/ 09 Dur: 1 day

Res:

search patent databases

Start: 03/ 12/ 09 I D: 8

Finish: 03/ 12/ 09 Dur: 1 day

Res:

review hits

Start: 04/ 12/ 09 I D: 9

Finish: 04/ 12/ 09 Dur: 1 day

Res:

shortlist 20 - 30 relevant hits

Start: 07/ 12/ 09 I D: 10

Finish: 07/ 12/ 09 Dur: 1 day

Res:

map out and analyse patent landscape

Start: 08/ 12/ 09 I D: 11

Finish: 08/ 12/ 09 Dur: 1 day

Res:

identify potential infringements / competition

Start: 09/ 12/ 09 I D: 12

Finish: 09/ 12/ 09 Dur: 1 day

Res:

send results to lawer for due-dilligence process

Start: 10/ 12/ 09 I D: 13

Finish: 10/ 12/ 09 Dur: 1 day

Res:

summarise & conclude in a brief report

Start: 11/ 12/ 09 I D: 14

Finish: 11/ 12/ 09 Dur: 1 day

Res:

Project End

Milestone Date: Mon 28/ 12/ 09

I D: 28

Presentation

Start: 25/ 12/ 09 I D: 26

Finish: 28/ 12/ 09 Dur: 2 days

Res:

Evaluate Performance (Data)

Start: 14/ 12/ 09 I D: 16

Finish: 14/ 12/ 09 Dur: 1 day

Res:

Evaluate Manufacturing

Start: 15/ 12/ 09 I D: 18

Finish: 16/ 12/ 09 Dur: 2 days

Res:

Compare with competition

Start: 17/ 12/ 09 I D: 20

Finish: 18/ 12/ 09 Dur: 2 days

Res:

Make Recommendation

Start: 21/ 12/ 09 I D: 22

Finish: 22/ 12/ 09 Dur: 2 days

Res:

Prepare Report & Presentation

Start: 23/ 12/ 09 I D: 24

Finish: 24/ 12/ 09 Dur: 2 days

Res:

TM&I course 2009

Milestone Date: Wed 02/ 12/ 09

I D: 1

Review IP

Start: 02/ 12/ 09 I D: 6

Finish: 11/ 12/ 09 Dur: 8 days

Comp: 0%

main tasks sub tasks

tm&i 2010 VI.7

Project Planning

PERT analysis• good for logical flow and Critical Path

Analysis (CPA)• but hard to visualise actual task durations

• The Gantt chart provides a simple graphical representation of task duration, plotted as a function of time

programme evaluation and review technique (PERT)

The Project Gantt Chart

tm&i 2010 VI.8

ID Task Name

1 TM&I course 20092 Evaluate a New Technology3

4 Project Start5

6 Review IP7 define search keyw ords or IPC codes

8 search patent databases

9 review hits

10 shortlist 20 - 30 relevant hits

11 map out and analyse patent landscape

12 identify potential infringements / competition

13 send results to law er for due-dilligence process

14 summarise & conclude in a brief report

15

16 Evaluate Performance (Data)17

18 Evaluate Manufacturing19

20 Compare with competition21

22 Make Recommendation23

24 Prepare Report & Presentation25

26 Presentation27

28 Project End

02/12

02/12

28/12

M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F30 Nov '09 07 Dec '09 14 Dec '09 21 Dec '09 28 Dec '09 04 Jan '10

tm&i 2010 VI.9

Gantt Chart

• easy to “grasp” at a glance• good for explaining project plans to

others• impact of human resource changes

clearly visible on timescale and “end date”

• good for monitoring project progress (more on this in next lecture)

tm&i 2010 VI.10

TASK LIST DELIVERABLES OBJECTIVE

RESOURCE ALLOCATION

TIMING

RESOURCE

PERT & CPA

Gantt

tm&i 2010 VI.11

summary

• top down approach to project plans is “common sense”• objective, deliverables, tasks, sub-tasks

• network diagram (PERT) illustrates task precedence (order) and helps to identify the critical path

• Gantt chart is good for explaining the project to others and clearly shows key project dates (e.g. milestones), and the effect resourcing has on these dates

tm&i 2010 VI.12

homework task 6• design a project plan for your Applied

Chemistry Master’s thesis• I recommend you use MS-Project Professional 2007

• prepare a Gantt chart of your project to clearly show tasks, duration and chronology (precedence), project start date, and end date (viva/graduation!)

• submission date 14/12/11• reading assigments Week 4, 5,6, i 7 • Download a free trial version of MS-Project here, or see Petar Kassel about using the lab PC in

ZOAK• http://www.microsoft.com/downloads/en/details.aspx?FamilyID=8e6c9977-69af-4cbc-8f39-d01