tinjauan pelaksanaan balok dan plat lantai bondek
DESCRIPTION
Presentasi Seminar KP MayTRANSCRIPT
![Page 1: Tinjauan Pelaksanaan Balok dan Plat Lantai Bondek](https://reader030.vdocuments.mx/reader030/viewer/2022033009/55cf9674550346d0338b9bf7/html5/thumbnails/1.jpg)
Maywuha Fitriana03081001045
![Page 2: Tinjauan Pelaksanaan Balok dan Plat Lantai Bondek](https://reader030.vdocuments.mx/reader030/viewer/2022033009/55cf9674550346d0338b9bf7/html5/thumbnails/2.jpg)
Latar Belakang : Perluasan Gedung JM Tahap II
Tujuan :Pengamatan dan identifikasi proses-proses pekerjaan pelat lantai dan balok
![Page 3: Tinjauan Pelaksanaan Balok dan Plat Lantai Bondek](https://reader030.vdocuments.mx/reader030/viewer/2022033009/55cf9674550346d0338b9bf7/html5/thumbnails/3.jpg)
Data-data Umum ProyekNama Proyek : Pembangunan Gedung JM
Sukarami Perluasan Tahap IILokasi Proyek : Jl. Kol. H. Burlian KM.8 Rt.
32 Rw.09Pemilik Proyek : Adam SautinKontraktor Pelaksana : PT. Delta Baja MasaWaktu Pelaksanaan : 10 bulanAwal Pelaksanaan : Januari 2012Akhir Pelaksanaan : Oktober 2012Waktu Pemeliharaan : 180 hari
![Page 4: Tinjauan Pelaksanaan Balok dan Plat Lantai Bondek](https://reader030.vdocuments.mx/reader030/viewer/2022033009/55cf9674550346d0338b9bf7/html5/thumbnails/4.jpg)
Data-data Teknis Proyek
Luas Areal ( 1 lantai ): 1557,15 m2
Luas Atap : 2589,67 m2
Mutu Beton : K300
Sistem Struktur : Komposit Beton-Baja Jumlah Lantai : 5 (termasuk basement)
![Page 5: Tinjauan Pelaksanaan Balok dan Plat Lantai Bondek](https://reader030.vdocuments.mx/reader030/viewer/2022033009/55cf9674550346d0338b9bf7/html5/thumbnails/5.jpg)
![Page 6: Tinjauan Pelaksanaan Balok dan Plat Lantai Bondek](https://reader030.vdocuments.mx/reader030/viewer/2022033009/55cf9674550346d0338b9bf7/html5/thumbnails/6.jpg)
![Page 7: Tinjauan Pelaksanaan Balok dan Plat Lantai Bondek](https://reader030.vdocuments.mx/reader030/viewer/2022033009/55cf9674550346d0338b9bf7/html5/thumbnails/7.jpg)
Plat atau slab adalah suatu elemen struktur yang mempunyai bentuk datar ataupun melengkung, yang ukuran tebalnya jauh lebih kecil dari ukuran-ukuran lainnya.
Jenis-Jenis Pelat Lantai :• Pelat Satu Arah (One Way Slab)
Pelat dengan nilai LY/LX > 2
• Pelat Dua Arah (Two Way Slab) Pelat dengan nilai LY/LX ≤ 2
![Page 8: Tinjauan Pelaksanaan Balok dan Plat Lantai Bondek](https://reader030.vdocuments.mx/reader030/viewer/2022033009/55cf9674550346d0338b9bf7/html5/thumbnails/8.jpg)
Komponen komposit didefinisikan sebagai suatu elemen yang terdiri dari dua jenis bahan atau lebih membentuk suatu elemen tunggal untuk memikul beban yang bekerja.
Elemen-elemen struktur komposit:Kolom kompositBalok kompositPelat komposit
![Page 9: Tinjauan Pelaksanaan Balok dan Plat Lantai Bondek](https://reader030.vdocuments.mx/reader030/viewer/2022033009/55cf9674550346d0338b9bf7/html5/thumbnails/9.jpg)
Ada dua tipe balok komposit, yaitu:
1. Balok komposit dengan penghubung geser.
2. Balok baja yang diberi selubung beton.
.Ada dua metoda pelaksanaan balok komposit, yaitu:
1.Memakai penyanggah (shored construction)2.Tanpa memakai penyanggah (unshored
construction)
![Page 10: Tinjauan Pelaksanaan Balok dan Plat Lantai Bondek](https://reader030.vdocuments.mx/reader030/viewer/2022033009/55cf9674550346d0338b9bf7/html5/thumbnails/10.jpg)
be
be /n
t b
bf
t f
tbD
Balok komposit berselubung beton
h Penampang komposit
b
yna
Penampang retak
b
Balok komposit dengan penghubung geser
![Page 11: Tinjauan Pelaksanaan Balok dan Plat Lantai Bondek](https://reader030.vdocuments.mx/reader030/viewer/2022033009/55cf9674550346d0338b9bf7/html5/thumbnails/11.jpg)
Langkah-langkah dalam pelaksanaan :PabrikasiPekerjaan ErectionPekerjaan Sambungan BajaPemasangan BondekPemasangan WiremeshPengecoran Pelat LantaiUji Beton : - Uji Slump
- Uji Kuat Tekan Beton
![Page 12: Tinjauan Pelaksanaan Balok dan Plat Lantai Bondek](https://reader030.vdocuments.mx/reader030/viewer/2022033009/55cf9674550346d0338b9bf7/html5/thumbnails/12.jpg)
![Page 13: Tinjauan Pelaksanaan Balok dan Plat Lantai Bondek](https://reader030.vdocuments.mx/reader030/viewer/2022033009/55cf9674550346d0338b9bf7/html5/thumbnails/13.jpg)
![Page 14: Tinjauan Pelaksanaan Balok dan Plat Lantai Bondek](https://reader030.vdocuments.mx/reader030/viewer/2022033009/55cf9674550346d0338b9bf7/html5/thumbnails/14.jpg)
![Page 15: Tinjauan Pelaksanaan Balok dan Plat Lantai Bondek](https://reader030.vdocuments.mx/reader030/viewer/2022033009/55cf9674550346d0338b9bf7/html5/thumbnails/15.jpg)
![Page 16: Tinjauan Pelaksanaan Balok dan Plat Lantai Bondek](https://reader030.vdocuments.mx/reader030/viewer/2022033009/55cf9674550346d0338b9bf7/html5/thumbnails/16.jpg)
![Page 17: Tinjauan Pelaksanaan Balok dan Plat Lantai Bondek](https://reader030.vdocuments.mx/reader030/viewer/2022033009/55cf9674550346d0338b9bf7/html5/thumbnails/17.jpg)
![Page 18: Tinjauan Pelaksanaan Balok dan Plat Lantai Bondek](https://reader030.vdocuments.mx/reader030/viewer/2022033009/55cf9674550346d0338b9bf7/html5/thumbnails/18.jpg)
Uji SlumpUji Kuat Tekan Beton
![Page 19: Tinjauan Pelaksanaan Balok dan Plat Lantai Bondek](https://reader030.vdocuments.mx/reader030/viewer/2022033009/55cf9674550346d0338b9bf7/html5/thumbnails/19.jpg)
Nilai output Mu pelat lantai yang didapat dari perhitungan program SAP2000 1,226x107 N-mm (pada area pelat lantai 1)
![Page 20: Tinjauan Pelaksanaan Balok dan Plat Lantai Bondek](https://reader030.vdocuments.mx/reader030/viewer/2022033009/55cf9674550346d0338b9bf7/html5/thumbnails/20.jpg)
Nilai output Mu balok yang didapat dari perhitungan program SAP2000 7,284x107 N-mm (pada balok 35)
![Page 21: Tinjauan Pelaksanaan Balok dan Plat Lantai Bondek](https://reader030.vdocuments.mx/reader030/viewer/2022033009/55cf9674550346d0338b9bf7/html5/thumbnails/21.jpg)
Struktur atas gedung JM Sukarami ini merupakan sistem rangka baja
Gedung JM Sukarami memiliki empat lantai upper floor dan satu lantai basement.
Kekuatan rencana kolom pada output SAP2000 lebih kecil daripada kekuatan rencana kolom di lapangan, sehingga profil yang dipakai di lapangan sudah memenuhi syarat perencanaan.
![Page 22: Tinjauan Pelaksanaan Balok dan Plat Lantai Bondek](https://reader030.vdocuments.mx/reader030/viewer/2022033009/55cf9674550346d0338b9bf7/html5/thumbnails/22.jpg)
Dalam pelaksanaaan proyek ini terdapat berbagai kendala yang menghambat jadwal pekerjaan, antara lain adanya kerusakan mesin (aus) pada alat crane yang digunakan untuk mengangkat balok, keterlambatan bahan dan alat ke lokasi, serta faktor cuaca (hujan) yang menghambat pelaksanaan pengecoran
Ada banyak ilmu hasil kerja praktek yang didapat langsung di lapangan kemudian dapat dibandingkan dengan teori-teori dari buku yang diberikan pada saat kuliah maupun dari berbagai literatur ilmiah lainnya.
![Page 23: Tinjauan Pelaksanaan Balok dan Plat Lantai Bondek](https://reader030.vdocuments.mx/reader030/viewer/2022033009/55cf9674550346d0338b9bf7/html5/thumbnails/23.jpg)
Untuk menghindari dan meminimalkan kesalahan perencanaan dan perhitungan yang terjadi di lapangan yang berdampak pada kerugian biaya, tenaga kerja, dan waktu, maka hendaknya harus lebih diperhatikan faktor-faktor di sekitar lokasi proyek, seperti kondisi tanah, lingkungan sekitar, keamanan, dan sebagainya;
Sebaiknya dalam pembangunan gedung yang cukup besar digunakan alat dengan kapasitas yang cukup besar juga dengan kualitas yang baik. Hal ini untuk menghemat waktu pembangunan suatu proyek;
![Page 24: Tinjauan Pelaksanaan Balok dan Plat Lantai Bondek](https://reader030.vdocuments.mx/reader030/viewer/2022033009/55cf9674550346d0338b9bf7/html5/thumbnails/24.jpg)
Kondisi peralatan pengangkutan balok dan kolom hendaknya selalu dirawat dan diperhatikan keadaannya, agar penggunaannya dapat dilakukan secara optimal;
Pengiriman bahan bangunan maupun Erection baja sebaiknya lebih dikontrol lagi agar tidak terhambat dalam pengiriman sehingga datang tepat waktu dan tidak menghambat pekerjaan pembangunan.