Project Timor-Leste Cement Plant
![Page 2: Timor-Leste Cement Plant](https://reader030.vdocuments.mx/reader030/viewer/2022021417/586871c01a28abb73f8be9e0/html5/thumbnails/2.jpg)
27th November 2013 Page 1 / 43
Project Location - Baucau, 2nd biggest City in TL
Site Location
Dili
Baucau
![Page 3: Timor-Leste Cement Plant](https://reader030.vdocuments.mx/reader030/viewer/2022021417/586871c01a28abb73f8be9e0/html5/thumbnails/3.jpg)
27th November 2013 Page 2 / 43
Owner : TL Cement LDA
Capacity : 5,000Tons/day 1.65 Million Tons /Year (Cement Clinker Base)
Product: Clinker bulk 1.15 MTPY (Off-take for Australian Market)
Cement 0.5 MTPY (Timor Domestic Supply)
Schedule: 34 Months from Effective Date of Contract
Location: Baucau, Second biggest City in Timor-Leste
Why Timor-Leste: High quality and large resource of Limestone (key material
for Clinker), in close proximity to Australia. Compatible manufacturing cost
while providing good employment & investment to Timor-Leste which aligns
with the goals the Timor-Leste Government.
Project Summary & Background Information
![Page 4: Timor-Leste Cement Plant](https://reader030.vdocuments.mx/reader030/viewer/2022021417/586871c01a28abb73f8be9e0/html5/thumbnails/4.jpg)
27th November 2013 Page 3 / 43
Benefits to Timor-Leste
![Page 5: Timor-Leste Cement Plant](https://reader030.vdocuments.mx/reader030/viewer/2022021417/586871c01a28abb73f8be9e0/html5/thumbnails/5.jpg)
27th November 2013 Page 4 / 43
Project Site
![Page 6: Timor-Leste Cement Plant](https://reader030.vdocuments.mx/reader030/viewer/2022021417/586871c01a28abb73f8be9e0/html5/thumbnails/6.jpg)
27th November 2013 Page 5 / 43
Limestone Quarry
![Page 7: Timor-Leste Cement Plant](https://reader030.vdocuments.mx/reader030/viewer/2022021417/586871c01a28abb73f8be9e0/html5/thumbnails/7.jpg)
27th November 2013 Page 6 / 43
Limestone Sampling
![Page 8: Timor-Leste Cement Plant](https://reader030.vdocuments.mx/reader030/viewer/2022021417/586871c01a28abb73f8be9e0/html5/thumbnails/8.jpg)
27th November 2013 Page 7 / 43
Plant Capacity – Cement Clinker 5,000t/day
[Conceptual View]
![Page 9: Timor-Leste Cement Plant](https://reader030.vdocuments.mx/reader030/viewer/2022021417/586871c01a28abb73f8be9e0/html5/thumbnails/9.jpg)
27th November 2013 Page 8 / 43
Proposed Port Site
![Page 10: Timor-Leste Cement Plant](https://reader030.vdocuments.mx/reader030/viewer/2022021417/586871c01a28abb73f8be9e0/html5/thumbnails/10.jpg)
27th November 2013 Page 9 / 43
Proposed Jetty Layout
![Page 11: Timor-Leste Cement Plant](https://reader030.vdocuments.mx/reader030/viewer/2022021417/586871c01a28abb73f8be9e0/html5/thumbnails/11.jpg)
27th November 2013 Page 10 / 43
Using Clean Energy – Solar & Wind
[Conceptual View]
![Page 12: Timor-Leste Cement Plant](https://reader030.vdocuments.mx/reader030/viewer/2022021417/586871c01a28abb73f8be9e0/html5/thumbnails/12.jpg)
27th November 2013 Page 11 / 43
First Drilling Ceremony 5th of March 2014
![Page 13: Timor-Leste Cement Plant](https://reader030.vdocuments.mx/reader030/viewer/2022021417/586871c01a28abb73f8be9e0/html5/thumbnails/13.jpg)
27th November 2013 Page 12 / 43
Oct 2014 Drilling Completed – 400 years Reserve
![Page 14: Timor-Leste Cement Plant](https://reader030.vdocuments.mx/reader030/viewer/2022021417/586871c01a28abb73f8be9e0/html5/thumbnails/14.jpg)
27th November 2013 Page 13 / 43
Timor-Leste First Mining Approval
![Page 15: Timor-Leste Cement Plant](https://reader030.vdocuments.mx/reader030/viewer/2022021417/586871c01a28abb73f8be9e0/html5/thumbnails/15.jpg)
27th November 2013 Page 14 / 43
Strong Support from the TL Leaders
![Page 16: Timor-Leste Cement Plant](https://reader030.vdocuments.mx/reader030/viewer/2022021417/586871c01a28abb73f8be9e0/html5/thumbnails/16.jpg)
27th November 2013 Page 15 / 43
Strong Support from Australia
![Page 17: Timor-Leste Cement Plant](https://reader030.vdocuments.mx/reader030/viewer/2022021417/586871c01a28abb73f8be9e0/html5/thumbnails/17.jpg)
27th November 2013 Page 16 / 43
Strong Support from the Community
![Page 18: Timor-Leste Cement Plant](https://reader030.vdocuments.mx/reader030/viewer/2022021417/586871c01a28abb73f8be9e0/html5/thumbnails/18.jpg)
27th November 2013 Page 17 / 43
Future Schedule
2015 End Dec
March 2016
September 2018
End of Dec 2018
First Clinker Shipment
to Australia
Practical Completion
Start Construction
Obtain Environmental Approval And Mine License
1 February 2014
![Page 19: Timor-Leste Cement Plant](https://reader030.vdocuments.mx/reader030/viewer/2022021417/586871c01a28abb73f8be9e0/html5/thumbnails/19.jpg)
Your Dream, We will Build!
Thank you!