  • Aptitude (http://mrunal.org/category/aptitude) / 3 years Ago /54 Comments (http://mrunal.org/2012/11/speed-time-work-two-men-can-finish-work-3x-efficient-b-b-leaves-completion-variety-cases.html#comments)

    1. Case: A & B work start together but B leaves2. Case: A started work, B joined after 4 days, how days work lasted?3. Case: A starts, B joins, How long did B work?4. Case: A and B start together but A leaves5. Case: Efficiency given: A is thrice good than B

    Case: A & B work start together but B leaves

    Q.Kalmadi can build a stadium in 14 days, while Raja can do the same in 21 days. They startedworking together.

    Case #1: 3 days before the completion of work, Kalmadi was sent to Tihad jail. So find outTotal Number of days to complete the work?Case #2: Same question but Raja goes to jail.

    Step 1: Draw the STD Table

    Whether it is Pipes and Cistern problem or it is Time and Work problem, draw the STD table,fill up the values

    Kalmadi Raja Kalmadi + Raja

    Speed

    Time 14 21

    Distance

    [Speed Time Work] Two Men can nish a work, A is 3x more ecientthan B, B leaves before completion & variety of cases

    English: SP Bakshi(http://www.flipkart.com/objective-general-

    english-2012/p/itmdyuqqgafhtehp?pid=9788183480000&affid=mrunalrugm)

    Mrunal (http://mrunal.org/)

  • Step 2: Take LCM, update Table

    Now well take the LCM of 14, 21

    14=27

    21=37

    LCM (14,21)= 2x3x7=42

    Lets just visualize this stadium has just 42 seats. And these fine gentlemen have to place theseats, and drill the bolts.So 42 seats is the Total work to be done or Total Distance to be covered.

    Fill up the table

    Kalmadi Raja Kalmadi + Raja

    Speed

    Time 14 21

    Distance 42 42

    Now the speed of Kalmadi

    Sx T= D

    S x 14=42 ; because we know Kalmadi takes 14 days to finish this work

    Speed of Kalmadi= 42/14= 3 seats a day

    Same way Raja can fit 2 seats a day (because 21 x 2 = 42)

    Update the Table

    Kalmadi Raja Kalmadi + Raja

  • Speed 3 2

    Time 14 21

    Distance 42 42

    Step 3: Kalmadi + Raja Together?

    What if Kalmadi + Raja work together? Obviously their speed will increase.

    Now they can fit 3+2 = 5 seats per day.

    Kalmadi Raja Kalmadi + Raja

    Speed 3 2 3+2=5

    Time 14 21 ??

    Distance 42 42 ??

    BUT we dont know for how many days did they work together?

    So we cannot find how many seats they fixed. (STD formula requires two known values!)

    So leave the (Kalmadi+Raja) column and move ahead.

    Step 4: Kamadi goes to Jail, Raja Works Alone

    We are given that 3 days before the completion of work, Kalmadi was sent to Tihad jail.

    It means for the last three days, Raja worked alone, right ?

    So, Expand the table, create one more column for Raja Alone

    Kalmadi Raja Kalmadi + Raja Raja alone

    Speed 3 2 3+2=5 2

    Time 14 21 ?? 3

  • Distance 42 42 ?? 6

    So, how many seats did Raja fix in last three days?

    Speed x time = distance

    2 x 3 = 6. ; Because Rajas speed Is 2 and he works for 3 days.

    Step 5: Remaining seats

    We know that total seats= 42, and Raja fixed 6.

    Meaning 42 minus 6 = 36 seats were fixed by Kalmadi +Raja together.

    Plug the value back in the Table

    Kalmadi Raja Kalmadi + Raja Raja alone

    Speed 3 2 3+2=5 2

    Time 14 21 ?? 3

    Distance 42 42 36 6

    Again STD formula to find how many days did they work together ?

    Speed (Kalmadi + Raja) x Time = Distance

    5 x Time = 36

    Time = 36/5=7.2

    Thus, our final table looks like this

    Kalmadi Raja Kalmadi + Raja Raja alone

    Speed 3 2 3+2=5 2

  • Time 14 21 7.2 3

    Distance 42 42 36 6

    Were about to solve the problem now.

    What is the Total time taken by these two fine gentlemen of impeccable integrity, to build thisstadium?

    Look at the finished table.

    7.2 days they worked together

    Plus 3 days Raja worked alone.

    =7.2+3=10.2 days.

    Final answer= 10.2 days

    Similarly you do for case#2 when Raja is sent to Jail, 3 days before the completion of work.

    Case: A started work, B joined after 4 days, how days work lasted?

    Abdul and Bhide can do a piece of work in 20 days and 12 days respectively. Abdul startedthe work alone and then after 4 days Bhide joined him till the completion of the work.How long did the work last?

    Step1: Create STD table

    Abdul Bhide

    Speed

    x Time 20 12

    = distance

    Step2: Take LCM of time

  • LCM (20,12)

    in other words, which is the first number that comes in multiplication table of both 12 and 20?

    Well, we know that

    12 x 5 =60 and

    20 x 3 = 60

    Therefore, 60 is the least common multiple of (12, 20)

    Assume total distance = 60

    Update table

    Abdul Bhide

    Speed

    Time 20 12

    distance 60 60

    Step3: Take ratio of speed

    now we know that total distance is 60. and if Abdul took 20 minutes to finish, what is his speed?

    Speed x time = distance

    Speed x 20 = 60

    Therefore, Abduls speed is 3; similarly Bhides speed is 5.

    Update the table.

    Abdul Bhide

  • Speed 3 5

    x Time 20 12

    = distance 60 60

    in the exam, just do it in your head. you took LCM so youd already know that 203=60 and125=60 so automatically 3:5 is the ratio

    Step 4: start the work

    Given: Abdul started the work alone and then after 4 days Bhide joined him till the completionof the work

    Means, for the first four days, Abdul worked alone.

    Abdul Bhide Abdul started

    Speed 3 5 3

    Time 20 12 4

    distance 60 60 34=12

    In 4 days, he covered 12 kms.

    So remaining work = 60 minus 12 =48.

    Which was completed by X+Y

    Abdul Bhide Abdul started Abdul + Bhide

    Speed 3 5 3 3+5=8

    Time 20 12 4 ??

    distance 60 60 34=12 48

    Run std on last column

  • Speed x time = distance

    8 x time = 48

    Time =48/ 8 =6 days

    Final table looks like this

    Abdul Bhide Abdul started Abdul + Bhide

    Speed 3 5 3 3+5=8

    Time 20 12 4 6

    distance 60 60 34=12 48

    Question: How long did the work last?

    X started and X+Y finished.

    Look at the time cells of their respective columns. (i.e. last column and second last column)

    Total time= 4 + 6=10 days.

    Final Answer: work lasted for 10 days.

    Case: A starts, B joins, How long did B work?

    Q. Abdul & Bhide can do a job alone in 10 days and 12 days respectively. Abdul starts thework & after 6 days Bhide also joins to finish the work together. For how many daysBhide actually worked on the job ?

    Take LCM of (10,12)=60

    After 6 days, Bhide also joins. That means for the first 6 days, Abdul worked alone.

    Fill up the table.

  • Abdul Bhide Abdul starts Abdul+Bhide

    Speed 6 5 6 (6+5)=11

    Time 10 12 6 days ??

    Distance 60 36 (60-36)=24

    In the first 6 days, Abdul finished 6 x 6 = 36 kilometers. Hence remaining work= 60 minus 36= 24

    This 24 kilometers were done by Abdul+Bhide together. (last column)

    Run the STD on last column

    Speed x time = distance

    11 x Time =24

    Time =24/11= approx. 2.18

    Final answer: Bhide worked for 2.18 days.

    Case: A and B start together but A leaves

    Abdul and Bhide can do a job in 15 days & 10 days respectively. They began the work togetherbut Abdul leaves after some days and Bhide finishes the remaining job in 5 days. After howmany days did p leave?

    Take LCM of (15, 10)=30 and fill up the table

    Abdul Bhide A+B work together only Bhide

    Speed 2 3 3+2=5 3

    xTime 15 10 ?? 5

    Distance 30 ?? 15

  • According to last column, Bhide covered 3x 5= 15 kilmeteres out of total 30 km.

    Hence the remaining 30 minus 15 = 15 kilometers were covered by A+B together

    their combined speed is (3+2)= 5.

    Run the STD formula on (A+B) column

    5 x time = 15

    Time = 15/5=3

    Means P+Q worked together for 3 days. And then P left.

    Final answer: P left after 3 days.

    Case: Eciency given: A is thrice good than B

    Q. Abdul is thrice as good as workman as Bhide and therefore is able to finish a job in 60days less than Bhide. Working together, they can do it in how many days?

    Abdul is thrice as good means if speed of Bhide is b, then

    Speed of Abdul = 3b

    Given: Abdul can finish job in 60 days less than Bhide

    Means if B can do work in t days, then A can do it in t-60 days

    Fill up the table

    A B

    Speed 3b b

    Time (t-60) t

    distance

  • The distance covered in each column is same, therefore

    (Speed x time)As column = (speed x time) Bs column

    3b x (t-60)=b x t

    3(t-60)=t

    t=90

    Update the table with this value of t

    A B

    Speed 3b b

    Time 90-60=30 90

    distance

    In Bs column apply STD formula so you get

    b x 90 =90b that is our total distance.

    When A+B work together, theyve to cover the same distance (90b)

    A B A+B

    Speed 3b b 3b+b=4b

    Time 90-60=30 90 ??

    distance b x 90=90b 90b

    Apply STD in last column

    4b x time =90b

  • Time =22.5 days

    visit Mrunal.org/aptitude (http://mrunal.org/aptitude), For more aptitude articles

    Mrunal recommends

    SBI/IBPS Bank Exams

    UPSC Civil Service

    SSC CGL: Staff selection

    CDS: Defense Services

    CAT/IIM MBA Entrance

    ACIO Intel Officer

    More from this category

    [Studyplan] CSAT Aptitude Paper 2: Maths & Data Interpretation-High prioritytopics, Sample Questions, free studymaterial (part 2 of 3)(http://mrunal.org/2014/06/studyplan-csat-aptitude-paper-2-maths-data-interpretation-high-priority-topics-sample-questions-free-studymaterial-part-2-3.html)

    [Studyplan] CSAT Aptitude Paper 2: Decision Making + Maths Medium & Lowpriority topics, Sample Questions, free studymaterial (part 3 of 3)(http://mrunal.org/2014/06/studyplan-csat-aptitude-paper-2-decision-making-

  • So far 54 Comments posted

    maths-medium-low-priority-topics-sample-questions-free-studymaterial-part-3-3.html)

    [Studyplan] CSAT Aptitude Paper 2: Comprehension & Reasoning, analysis,previous papers, free studymaterial, cutoffs (part 1 of 3)(http://mrunal.org/2014/06/studyplan-csat-aptitude-paper-2-comprehension-reasoning-analysis-previous-papers-free-studymaterial-cutoffs-part-1-2.html)

    [Reasoning] Calendar Questions: Finding day or date, concepts, shortcutsexplained (http://mrunal.org/2013/08/reasoning-calendar-questions-finding-day-or-date-concepts-shortcuts-explained.html)

    [Trigonometry] Finding Minimum Maximum Values for SSC CGL Made Easywithout differentiation (http://mrunal.org/2013/07/trigonometry-finding-minimum-maximum-values-for-ssc-cgl-made-easy-without-differentiation.html)

    Print | PDF (need Chrome) (http://mrunal.org/2012/11/speed-time-work-two-men-can-finish-work-3x-efficient-b-b-leaves-completion-variety-

    cases.html/print/)

    Get notified whenever I post new article!(http://feedburner.google.com/fb/a/mailverify?uri=CivilServiceExam)

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 0 4 8 9 5 # R E S P O N D )

    SHOURABH JOSHIThank you so much for ur constructive support and all ur efforts

  • R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 0 4 8 9 6 # R E S P O N D )

    ashishI think answer to 1st case,1 subquestion I.e Kalamadi left the work 3daysbefore should be..12.9 days.Check and correct me , if I m wrong

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B -L E A V E S - C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 0 4 9 5 2 # R E S P O N D )

    Akhil@Ashish, you have mis-read the question, like I did in first attemptand ended up with the same answer. You must have calculatedtotal time as 42/5 and substracted 3 from that. There is theproblem, the time is given considering he already left 3 daysbefore. So equation would be like this,[(t-3)/14]+[t/21] = 1t = 10.2

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 0 4 9 2 0 # R E S P O N D )

    Basistthe answer (10.2) is correct.If raja goes to jail, the answer would be 9.6 days

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 0 4 9 5 1 # R E S P O N D )

    Rajesh

  • Question 1 can also be interpreted in this manner that they weresupposed to finish the work together in three days, but one was requiredto go to jail three days before project completion?

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 0 9 5 5 2 # R E S P O N D )

    ArunA does half as much work as B in three fourth of the time. IF togetherthey take 18 days to complete the work, how much time shall B take todo it?

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 1 1 1 2 2 # R E S P O N D )

    anand kumartime 2.18 of q 3 is of both not only of bhind

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 1 7 8 6 6 # R E S P O N D )

    sunny kumarkindly help with below question-my answer- 48.actual answer-24

    twenty four men can complete a work in 16 days.thirty two women can complete the same work in 24 days.sixteen men & sixteen women started working and worked for twelvedayshow many more men are to be added to complete the remaining work in2 days?

  • thanks.

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B -L E A V E S - C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 1 9 4 2 4 # R E S P O N D )

    Ronit will be better if u could also write ur procedure of solving this Q.Nevertheless,I think u made mistake by not subtracting 48(men reqto complete work in 4 days)-24(men already present)=24(men req).hope this will help

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T -B - B - L E A V E S - C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ?R E P L Y T O C O M = 2 4 7 3 4 0 # R E S P O N D )

    sunny kumar24M*16=32W*24M=2WSo 16*2W+16W = 48(Total work)w= 1m=2now no work left to be done as m again getting 48.please help

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X -E F F I C I E N T - B - B - L E A V E S - C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ?R E P L Y T O C O M = 3 2 6 4 2 7 # R E S P O N D )

    divyaM=2W16M+16W=24Mwe already know 24M can complete work in 16 days24M work for only for 12days and remaining needs to

  • be completed by additional men + existing men tocomplete in 2 days24Mx4=nx2n=48(this is existing men of 24 + additional men)

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 1 9 4 1 2 # R E S P O N D )

    Lakhan JadejaA B C together do work in 10 days. B C together work thrice as much as Aand A and B together work four time as much as C in what time thay cando each other ?sir i follow your method to solve time work quesiton but in this methodhow to put your method plz guide me

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 2 8 5 8 7 # R E S P O N D )

    AJHow to solve this one with STD approach:A pump can fill a tank with water in 2 hours. Because of a leak, it took 2hours to fill the tank. The leak can drain all the water of the tank in:

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B -L E A V E S - C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 2 8 5 9 5 # R E S P O N D )

    AJHow to solve this one also with STD approach:A tank is filled by three pipes with uniform flow. The first two pipesoperating simultaneously fill the tank in the same time duringwhich the tank is filled by the third pipe alone. The second pipe fillsthe tank 5 hours faster than the first pipe and 4 hours slower than

  • the third pipe. The time required by the first pipe is:A. 6 hours B. 10 hoursC. 15 hours D. 30 hours

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 2 8 5 8 9 # R E S P O N D )

    AJHow to solve this one with STD approach:A pump can fill a tank with water in 2 hours. Because of a leak, it took(7/3) hours to fill the tank. The leak can drain all the water of the tank in:

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 2 8 5 9 6 # R E S P O N D )

    AJHow to solve this one also with STD approach:A tank is filled by three pipes with uniform flow. The first two pipesoperating simultaneously fill the tank in the same time during which thetank is filled by the third pipe alone. The second pipe fills the tank 5hours faster than the first pipe and 4 hours slower than the third pipe.The time required by the first pipe is:A. 6 hours B. 10 hoursC. 15 hours D. 30 hours

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 3 1 6 4 3 # R E S P O N D )

    AryaI would like to ask one question, for which i am not able to get thesolution from above cases. Please help me in solving the question.

  • Ques: Two workers A and B working together completed a job in 5 days.If A worked twice as efficiently as he actually did and B worked 1/3 asefficiently as he actually did, the work would have been completed in 3days. To complete the job alone A would require how many days?

    Reply ASAP.

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B -L E A V E S - C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 4 7 3 5 0 # R E S P O N D )

    AanyaSuppose A alone can do the work in a days.Suppose B alone can do the work in b days.

    By First statement - 1/a + 1/b = 1/5

    Second statement A works twice as efficiently as he did means ifearlier he was taking a days now he will take only a/2 days.Similarly B will take 3b days .Thus,2/a + 1/(3b) = 1/3

    Solve above two to get value of a.

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B -L E A V E S - C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 4 7 3 5 2 # R E S P O N D )

    AanyaSuppose A alone can do the work in a days.Suppose B alone can do the work in b days.

    By First statement - 1/a + 1/b = 1/5

  • Second statement A works twice as efficiently as he did means ifearlier he was taking a days now he will take only a/2 days.Similarly B will take 3b days .Thus,2/a + 1/(3b) = 1/3

    Solve above two to get value of a.

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 3 3 6 8 4 # R E S P O N D )

    PreetiThanks Mrunal

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 3 3 7 6 1 # R E S P O N D )

    Sajal Sinhaperson A can do a job in x daysperson B can do a job in y dayspart of job done by person A alone in one day is 1/x th partpart of job done by person B alone in one day is 1/y th partpart of job done by A and B together in one day is 1/x + 1/y th partSo total days required to do the job is 1/(1/x +1/y) { Suppose I can do1/5th part of job in one day so I will need 1/(1/5) days i.e 5 days tocomplete the job}This is the only theory there are no other rules or tricksThe origin to this theory is that you cannot add inversely proportionalrelations

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 4 6 0 3 9 # R E S P O N D )

    sneha

  • snehamukul and vipin together do a work in 6 days. if mukul does 1/5 part ofthe work in 2 days, in how many days will vipin alone do the remainingwork ?

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B -L E A V E S - C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 4 6 0 6 5 # R E S P O N D )

    RaviMukul does 1/5 work in 2days therefore in one day he can do 1/10work. So he alone can complete work in 10 days

    Vipin and mukul together= 1/6

    Vipin alone= 1/6 1/10 = 1/15So vipin alone can do in 15 days.

    But 1/5 work has already been done by Mukul so the remainingwork is 4/5

    Vipin does 1 work in 15 days.He can do 4/5 work in 15X4/5 days = 12 days

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B -L E A V E S - C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 4 6 1 3 7 # R E S P O N D )

    Abhay12??Total combined efficiency= 100/6= 16.67Mukul can do 100 percent wrk in = 5*2=10Mukul efficiency= 100/10=10therefore Vipin efficiency= 16.67-10= 6.67

  • Work left=4/5=80%therefore numberbof days for vipin to complete= 80/6.67= 12days??

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B -L E A V E S - C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 4 6 1 4 5 # R E S P O N D )

    Praveenms 1day work= 1/10(m+v)s 1day work=1/6vs 1day work= 1/6-1/10 = 4/60v takes to complete the work alone= 60/4=15 days.

    hope im clear

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B -L E A V E S - C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 6 6 4 5 7 # R E S P O N D )

    ASHISHi think 7 days

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 4 7 2 3 6 # R E S P O N D )

    sunny kumarThe shape of a garden is rectangular in the middle and semi circularat the both ends . Find the area and the perimeterof this garden.total length of garden- 20 mbredth of garden- 7 m

  • i got the area right( 91+38.5)but not getting perimeter.my answer- perimeter of rectangl portion=40 & perimtr of circle=22, so intotal =62but answer is 48kindly help with thisthanks

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B -L E A V E S - C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 4 7 3 4 5 # R E S P O N D )

    AanyaYou are getting the area right so you are clear that garden is arectangle of 7*13 and 2 semi circles of radius 3.5 . These semicircles are adjacent to the sides of length 7.

    Now perimeter 13*2 (free sides) + 2*22/7*3.5 (2*22/7*r) = 48

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 4 7 3 3 9 # R E S P O N D )

    sunny kumar24M*16=32W*24M=2WSo 16*2W+16W = 48(Total work)w= 1m=2now no work left to be done as m again getting 48.please help

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 4 7 3 9 9 # R E S P O N D )

    kiran

  • kiransunny complete que liko plz y tnw ka

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 4 8 7 7 9 # R E S P O N D )

    sunny kumargot it.i was double counting the perimeter.thanks!

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B -L E A V E S - C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 3 2 8 9 7 3 # R E S P O N D )

    niharikapermiter of the garden is 76m

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 4 8 7 8 0 # R E S P O N D )

    sunny kumar1 more for you-

    kindly help with below question-my answer- 48.actual answer-24

    twenty four men can complete a work in 16 days.thirty two women can complete the same work in 24 days.sixteen men & sixteen women started working and worked for twelvedayshow many more men are to be added to complete the remaining work in2 days?

  • thanks.

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 4 8 7 8 4 # R E S P O N D )

    Anurag16x24M=32x24W => M=2W .Now the total work is 16x24M .16M+16W = 24M work completed 24x12M remaining 24x4M means96M work still remaining , 24M can do 24M work per day,means they willcomplete 48M work,remaining is 48M it needs 24 more Men or 48 morewomen.

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 5 1 9 7 7 # R E S P O N D )

    shivangican any1 plzz help me with this ques?20 women can finish a job in 20 days.after each day, a woman is replacedby a man and a man is twice as efficient as a woman.on which day doesthe job get completed?ans is 18th day.

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B -L E A V E S - C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 6 6 1 7 5 # R E S P O N D )

    rahulIn question, 20 women can finish a job in 20 days. assume everywomen has 2 units then total unit of work is 20*2*20=800 unit(20women has 2 unit each and work for 20 days).Second term of question, After each day a women is replaced by aman and a man is twice as efficient as a women,hence, man unit is 4 (because it is twice as efficient as a women)

  • so a woman does 2 units of work in a day and man does 4 units ofwork in a day

    starting with 20 women initially

    day 140 units completedday 238 + 4 = 42 units (1 women replace by 1 men)day 3 ..36 + 8 = 44 units (2 women replace by 2 men)day 4 ..34 +12 = 46 units(3 women replace by 3) men) etc.. etc

    now we have to find in how many days this will add to 800 uniteasy way to do this,adding each dayday1+day2+day3+day4..=800 unit.

    in 15 days total work done = 810 unit.

    so work gets over on the 15th day

    Answer is 15th days not 14th day

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 5 1 9 7 8 # R E S P O N D )

    shivangisorry typeing errroranswer to above question is 14th day..

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 8 5 0 6 4 # R E S P O N D )

    samikssha

  • A can do a piece of work in 36 days, B in 54 days and C in 72 days. All thethree began the work together but A left 8 days and B 12 days before thecompletion of the work. How many days in all did C put in till the entirework was finished?pls solve it in STD method

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 8 5 2 9 9 # R E S P O N D )

    rahulin last question why a and b work together for 90 days,in rest of thequestions its not like that

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 2 9 5 9 8 3 # R E S P O N D )

    AbhishekTwo pipes L and M can fill a tank in 15 and 12 h respectively and a 3rdpipe N can empty it in 4 h. If the pipes are opened at 8 am 10 am and 11am respectively find the time the tank will be emptied.

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 3 1 1 9 3 8 # R E S P O N D )

    Santhe answer is 16.50.

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 3 1 9 6 6 6 # R E S P O N D )

    muralithanku mrunal sir

  • R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 3 2 1 3 1 0 # R E S P O N D )

    mrunal fanBhai thanksItna bhadiya concept samjhane k liye

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 3 2 2 3 3 1 # R E S P O N D )

    Anas MMrunal Bhai, I am expert in Time and Work type question. all because ofyou.Thank you so much.

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 3 2 5 3 7 1 # R E S P O N D )

    Sai DattaMrunal sir.. Im deaf man. I understand your explanation clearly. Now Ivesome doubts. Please clear my doubts before having bank exam nextweek.

    Here some questions :

    1) A and B can do a piece of work in 30 days, while B and C can do thesame work in 24 days and C and A in 20 days. They all work together for10 days when B and C leave. How many days more will A take to finishthe work?

  • 2) 4 men can complete a piece of work in 2 days. 4 women can completethe same piece of work in 4 dayswhereas 5 children can complete the same piece of work in 4 days. If 2men, 4 women and 10 childrenwork together, in how many days can the work be completed?

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 3 2 8 2 9 8 # R E S P O N D )

    Parul10 men and 15 women can finish a work in 6 days. One man can alonefinish a work in 100 days. In how many days will a woman finish the work?sir how will it be solved by Std table?

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 3 2 8 7 2 7 # R E S P O N D )

    RashiCan someone solve this question with the above mentioned technique:Two pipes A and B can fill a tank in 24mins and 32 mins. If both pipes areopened together,after how much time B should be closed so that tank isfull in 18 mins. [Ans. 8mins]

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B -L E A V E S - C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 3 2 8 7 3 1 # R E S P O N D )

    deepak(18/24)+(x/32)=1

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B -L E A V E S - C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 3 2 8 7 7 8 # R E S P O N D )

    vipin

  • vipinits very easy. speed of a comes out to be 4 . speed of b= 3 . totaldistance or time = 96. a+b = 7 . now take time of a+b = x and aalone to be 18 x . now the equation will be 7x + 4 ( 18 x ) = 96 .solve it and you will get the value of x = 8 min .

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T -B - B - L E A V E S - C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ?R E P L Y T O C O M = 3 2 8 7 8 2 # R E S P O N D )

    vipintotal distance =96 and not time

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 3 2 8 7 9 7 # R E S P O N D )

    rakeshFOR MPPSC ADMIT CARD PLEASE GO TO APPLY ONLINE LINK CLICKSTATE SERVICES EXAM 2014 AMD DWLD ADMIT CARD

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 3 3 5 7 1 3 # R E S P O N D )

    SANTHOSH S KSir, how to solve using STD table A can do a work in 15 days and B in 20days. If they work on it together for 4 days, then the fraction of the workthat is left is?

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 3 3 7 9 1 1 # R E S P O N D )

    siddharth

  • Write your message!

    please tell me ho to solve by std approacha and b can do a job in 16 and 12 days respectively 4 days beforecompletion of job a joins b find out how many days b has worked alone ifb has started work alone ???????a 6b 4c5d7

    R E P L Y ( / 2 0 1 2 / 1 1 / S P E E D - T I M E - W O R K - T W O - M E N - C A N - F I N I S H - W O R K - 3 X - E F F I C I E N T - B - B - L E A V E S -C O M P L E T I O N - V A R I E T Y - C A S E S . H T M L ? R E P L Y T O C O M = 3 3 8 7 5 2 # R E S P O N D )

    tejaswiA can do a piece of work in 80 days.he works at it for 10days and then Balone finishes the remaining work in 42 days .in how much time will Aand B working together , finish the work????

    pls solve this using STD method ..

    ANS: 30 DAYS

  • Search B4 Asking

    Type n Press Enter

    Name?

    Email ID?

    What is your Message? Search before asking questions & confine discussions to exams related matter only.

    Notify me of follow-up comments by email.

    Notify me of new posts by email.

    Post Message

    4 Days : CMS-15

    18 Days : CAPF-15

    46 Days : SSC CGL15

    60 Days : CSAT-15

    101 Days : IBPS-PO-15

    164 : IBPS-Clerk-15

    177 Days : Mains-15

  • Recent Comments

    DEVENDER { Mrunal, what about may, June current affairs series?? } [Economy Lecture]GS2: UNFCCC Lima Summit, Paris Summit Post-2020... (http://mrunal.org/2015/06/economy-lecture-paris-summit-post-2020-climate-finance-framework.html/comment-page-1#comment-340678)

    ABHISHEK { now how many lecture still remain to complete the economic lecture. sir please discuss } [Economy Lecture] GS2: UNFCCC Lima Summit, Paris Summit Post-2020...(http://mrunal.org/2015/06/economy-lecture-paris-summit-post-2020-climate-finance-framework.html/comment-page-1#comment-340641)

    ISHU { THANKUUUUUU..SO MUCH SIR.. my economics was not so good and i have fear for that but after listening to ur lectures all doubts are clear.... } [Economy Lecture] GS2: UNFCCC LimaSummit, Paris Summit Post-2020... (http://mrunal.org/2015/06/economy-lecture-paris-summit-post-2020-climate-finance-framework.html/comment-page-1#comment-340627)

    DWARIKA { in composition of the interior of the earth need updation in part of crust property you are mentioned potassium is lowest in earth's crust ,... } [Geography Lecture1] Longitude,Latitude, Timezones, Earth Interior, Rock types,... (http://mrunal.org/2015/02/youtube-geography-l1-longitude-latitude.html/comment-page-2#comment-340620)

    ANN { Thanks for the MCQs on IYB :) } [Mock Test #3] India Yearbook Chapter 1 to 12:...(http://mrunal.org/2015/06/upsc-mock-test-paper-1-india-yearbook.html/comment-page-1#comment-340565)

    RAVIRAJDODIYA { Sir, I want to appear UPSC in Gujarati.Because I think I am comfortable in that language and I can write 10 time better that any... } [Analysis] Essay topic trends in last19 years (1993-2011)... (http://mrunal.org/2011/12/analysis-essay-topic-trends-in-last-19.html/comment-page-1#comment-340560)

    VIMAL { product of two number is 600.Lcm of thease number 10.What is the HCF of those two number? } [Aptitude] LCM, HCF, GCD: Basic concept, calculation, applications explained(http://mrunal.org/2013/03/aptitude-lcm-hcf-gcd-basic-concept-calculation-applications-explained.html/comment-page-2#comment-340559)

    HARSHADNARKAR { What is your Message? Search before asking questions & confine discussions to exams related matter only. sir,history lectures kab honge. } [Economy Lecture]GS2: UNFCCC Lima Summit, Paris Summit Post-2020... (http://mrunal.org/2015/06/economy-lecture-paris-summit-post-2020-climate-finance-framework.html/comment-page-1#comment-340552)

  • JOHNSSWARGIARY { ist true that double the money plz ans me } [Financial Inclusion]Kisan Vikas Patra (KVP): Features, Money Laundering,... (http://mrunal.org/2014/12/kisan-vikas-patra-kvp-features-money-laundering-black-money-tax-benefit.html/comment-page-1#comment-340548)

    NAVEEN { Prateek even i got.....291 marks.....what about the reserved list??? Whts the procedure?? } [CAPF-2014] Final result out, 105 selected, marksheets in 15...(http://mrunal.org/2015/02/upsc-capf-2014-final-result-marksheet.html/comment-page-2#comment-340545)

    VacanciesEntire List shifted to bottom. Scroll down

    (http://www.alexa.com/siteinfo/mrunal.org)

    Mega Jobs

    23-Jul: IBPS Rural PO & Asst. (http://ibps.in/html/cwe_rrb.htm)

    17-Aug: IGNOU PG Admission (https://onlineadmission.ignou.ac.in/Login.aspx)

    17-Jul: NDA Officers (http://upsconline.nic.in/mainmenu2.php)

    13-Jul: SSC 10+2 (http://www.ssconline.nic.in/)

    09-Jul: APFC Provident Fund Comm.

    (http://www.upsc.gov.in/recruitment/advt/2015/Spl.Advt.52-15%20Web%20Cell.pdf)

    09-Jul: Punjab Corp Engineer (http://202.164.52.147/serv1/docs/dysecyrect121017527.pdf)

    09-Jul: Punjab Corp Clerks (http://202.164.52.147/serv1/docs/dysecyrect121017527.pdf)

    07-Jul: RBI Assistants (504) (https://opportunities.rbi.org.in/Scripts/bs_viewcontent.aspx?

    Id=3024#AN)

    02-Jul: FCI MT (1Lakh Bond,3yr) (https://fcijobsportal.com/fcimt2015/pages/index.aspx)

    01-Jul: Haryana Health Services (http://haryanahealth.nic.in/)

  • 30-Jun: LIC ADO (25k Bond,4yr) (http://www.licindia.in/careers_pop0022.htm)

    24-Jun: Haryana Gramin Bank Assiatant (http://www.shgb.co.in/RecruitmentsandPromotions)

    24-Jun: IDBI Manipal Banking Admission (http://www.idbi.com/idbi-bank-careers-current-

    openings.asp)

    Rural Banks

    23-Jul: IBPS Rural PO & Asst. (http://ibps.in/html/cwe_rrb.htm)

    25-Jun: Odisha Gramya (http://www.odishabank.in/Recruitment.aspx)

    25-Jun: Assam Gramin (http://www.agvbank.co.in/recruitment.php)

    24-Jun: Haryana Gramin Bank PO (http://www.shgb.co.in/RecruitmentsandPromotions)

    IT Jobs

    20-Jul: CDAC Noida (http://www.cdac.in/index.aspx?id=ca_noida_may_2015)

    Engineers

    02-Jul: BEL Ghaziabad (http://bel-india.com/recruitment)

    02-Jul: ISRO Scientists (http://isro.gov.in/careers)

    02-Jul: FCI Engg.Trainee (http://www.fcijobsportal.com)

    30-Jun: Hindustan Latex Biomed. Engg (300) (http://www.hlfppt.org/)

    26-Jun: RBI JE (https://rbi.org.in/scripts/Bs_viewcontent.aspx?Id=3020)

    26-Jun: Bharat Dynamics (http://bdl.ap.nic.in/bdlrecruit.htm)

    25-Jun: Raipur Civil Engg (http://www.aiimsraipur.edu.in/Career.aspx)

    25-Jun: MP Electricity

    (https://www.mponline.gov.in/Portal/Services/Recruit_MPKVV/Indore/notification.aspx)

    24-Jun: KRIBHCO Noida (http://kribhco.indiainformative.com/Post4.aspx)

    Legal

  • 10-Jun: AAI Law (http://www.aai.aero/employment_news/Employee_Recruitment_new.jsp)

    Specialists

    31-Jul: IIIT Allahabad Gr. A & B (http://www.iiita.ac.in/announcements.php)

    20-Jul: State Trading corp. (http://www.stc.gov.in/careers/current-openings.aspx)

    20-Jul: NISER APO (http://www.niser.ac.in/drupal_new/)

    15-Jul: Jammu Univ. (http://www.cujammu.ac.in//Default.aspx?

    option=article&type=single&id=32&mnuid=734&prvtyp=site)

    15-Jul: MoEF Scientists (http://envfor.nic.in/advertisements)

    09-Jul: Allahabad Bank (https://www.allahabadbank.in/english/Recruitment.aspx)

    12-Jul: Mumbai Metro (https://mmrda.maharashtra.gov.in/tenders-notices)

    12-Jul: GBPUAT (http://www.gbpuat.ac.in/)

    09-Jul: Punjab Corp Law (http://202.164.52.147/serv1/docs/dysecyrect121017527.pdf)

    07-Jul: NBCC Building (http://www.nbccindia.com/nbccindia/nroot/njsp/Career.jsp)

    01-Jul: NIELIT Spec. (http://www.nielit.gov.in/recruitments.aspx)

    30-Jun: Rajendra Agro. (http://www.mangaldhwani.com/pusa/wp-

    content/uploads/2014/09/Advt_-01_2015.pdf )

    30-Jun: IIT Kanpur (http://www.iitk.ac.in/new/vacancies-in-administrative-and-technical-

    cadre )

    28-Jun: ONGC Rajbhasha (NET)

    (http://ongcindia.ongc.co.in/wps/wcm/connect/ongcindia/home/career/recruitment+notices/recruitment-

    of-olo-2015)

    25-Jun: Raj. Industrial Development (http://www.riicorecruitment.org/)

    25-Jun: HSCC Noida (http://www.hsccltd.com/)

    24-Jun: Haryana Gramin Agro (http://www.shgb.co.in/RecruitmentsandPromotions)

    24-Jun: Haryana Gramin Law Officer (http://www.shgb.co.in/RecruitmentsandPromotions)

    Medics

    14-Jul: MP medical officer (http://www.mppsc.nic.in/)

    30-Jun: HAL Medical officer (http://www.hal-

    india.com/Common/Uploads/Resumes/144_CareerPDF1_Med-advt-AC.pdf)

  • ParaMedics

    Not At the moment

    Deskjobs

    05-Aug: NBE Assistants (http://natboard.edu.in)

    31-Jul: IIIT Allahabad Gr.C (http://www.iiita.ac.in/announcements.php)

    20-Jul: NISER Clerks (http://www.niser.ac.in/drupal_new/)

    15-Jul: Jammu Univ. (http://www.cujammu.ac.in//Default.aspx?

    option=article&type=single&id=32&mnuid=734&prvtyp=site)

    07-Jul: NBCC Building (http://www.nbccindia.com/nbccindia/nroot/njsp/Career.jsp)

    01-Jul: NIELIT Deskjobs (http://www.nielit.gov.in/recruitments.aspx)

    13-Jun: Bank Note Press (http://www.jobapply.in/bnpdewas/)

    30-Jun: Lucknow Law univ. (http://rmlnlu.ac.in/recruitment-notification-process.html)

    30-Jun: Rashtriya Sanskrit Sansthan (http://sanskrit.nic.in/advt_22_05_2015.pdf)

    25-Jun: Pawan Hans Limited (http://pawanhans.co.in/site/Careern.aspx)

    24-Jun: SJVN (PH) (http://sjvn.nic.in/careerdetail.htm?10/jobdetail)

    Faculty

    31-Jul: IIIT Allahabad (http://www.iiita.ac.in/announcements.php)

    20-Jul: Raipur Univ. (http://www.prsu.ac.in:8010/Univ_Req.aspx)

    15-Jul: NIT Puducherry (http://www.nitpy.ac.in/assets/teaching.pdf)

    16-Jul: RPSC Home Science (http://rpsconline.rajasthan.gov.in/)

    15-Jul: Jammu Univ. (http://www.cujammu.ac.in//Default.aspx?

    option=article&type=single&id=32&mnuid=734&prvtyp=site)

    12-Jul: GBPUAT (http://www.gbpuat.ac.in/)

    10-Jul: NITTTR Chandigarh (http://www.nitttrchd.ac.in )

    07-Jul: Palampur, Himachal asst. (http://www.ihbt.res.in/recruit/recruitNotice.php)

    06-Jul: PEC Chandigarh (http://pec.ac.in/~pecac/new/jobs)

    03-Jul: SKHM Government Medical College (http://www.gmcmewat.ac.in)

    30-Jun: IIT Roorkee (http://www.iitr.ernet.in/administration/pages/Openings+Faculty.html)

  • 30-Jun: Ambedkar Uni. Delhi (http://aud.ac.in/careerataud)

    30-Jun: NEIGRIHMS (http://neigrihms.gov.in)

    30-Jun: Lucknow Law (http://rmlnlu.ac.in/recruitment-notification-process.html)

    30-Jun: AIIMS Raipur (http://www.aiimsraipur.edu.in/Career.aspx)

    28-Jun: Ranchi Agro (http://www.bauranchi.org/application-for-the-post-of-teachers-2/)

    22-Jun: DIATPune (http://14.139.111.180/admin.html)

    22-Jun: IGIT (http://www.igitsarang.ac.in/careers.php)

    22-Jun: Himachal Central Univ. (http://www.cuhimachal.ac.in/job_emp.aspx)

    Uniform

    19-Jul: Navy Officers (http://www.irfc-nausena.nic.in/hindi/join_indiannavy.htm)

    17-Jul: NDA Officers (http://upsconline.nic.in/mainmenu2.php)

    15-Jul: Army Dental (23) (http://indianarmy.nic.in)

    10-Jul: Army 10+2 (http://joinindianarmy.nic.in/)

    30-Jun: BSF Constable (http://bsf.nic.in/en/recruitment.html)

    15-Jun: Navy Sailers (SSR) (http://nausena-bharti.nic.in/forthcomingSailor.php)

    15-Jun: Daman Diu Constables (http://daman.nic.in/jobs/2015/616-12-05-2015.PDF)

    B.Com,CA,HR,MBA

    20-Jul: Pawan Hans Audit (http://pawanhans.co.in/site/Careern.aspx)

    06-Jul: GBPUAT Accountant (http://www.gbpuat.ac.in/)

    01-Jul: NIELIT Accounts (http://www.nielit.gov.in/recruitments.aspx)

    25-Jun: MP Electricity Accounts

    (https://www.mponline.gov.in/Portal/Services/Recruit_MPKVV/Indore/notification.aspx)

    21-Jun: Lucknow Metro Accounts

    (https://www.digialm.com/EForms/html/form2399/index.html)

    RESULT /MARKSHEET

    SSC 2014 T2

    NCLAT

  • (https://www.facebook.com/Mrunal.org)

    (https://twitter.com/mrunal_patel)

    (https://plus.google.com/109455346868280536907?

    rel=author)

    (http://www.youtube.com/user/TheMrunalPatel)

    (http://feedburner.google.com/fb/a/mailverify?

    uri=CivilServiceExam)HOME (HTTP://MRUNAL.ORG/) ECONOMY (HTTP://MRUNAL.ORG/ECONOMY)

    DOWNLOAD (HTTP://MRUNAL.ORG/DOWNLOAD) CONTACT ME (HTTP://MRUNAL.ORG/CONTACT)

    The work of Mrunal (http://mrunal.org/) is under the Creative Commons Attribution-Non Commercial-ShareAlike 4.0License (http://creativecommons.org/l icenses/by-nc-sa/4.0/deed.en_US).Permissions beyond the scope of this l icense

    may be available at Mrunal.org/contact (http://mrunal.org/contact).

    1. Online Form Part-I stops few days before deadline, so don't wait till last date. Dont forget

    reg.id & roll no.Note'em in Google Drive (https://www.google.com/drive/)

    2. I usually update vacancies every Monday.Purple link= newly added,Blue= existing.Last

    updated Mon. Jun 22, at 9:04PM

    Hotel Management

    TENTATIVE NOTIFICATIONS

    IAS-IPS-IFoS: 16 May

    IES: 7 Feb

    SSC CGL: 2 May

    SSC 10+2: 6 June

    SSC Sub insp: 28 Mar

    CAT: Aug 2015

    RBI Officer / Assistant: ??

    IBPS PO / Clerk / RRB: ??

    ACIO 2015: ??

    // /

  • (http://www.alexa.com/data/details/main?url=http://mrunal.org)