time trap analysis

9
SPS W7C01 – Rev 10-07 © 2006 George Group Consulting, Time Trap Analysis Validating Project Focus

Upload: sangitadipak1979

Post on 04-Apr-2015

550 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Time Trap Analysis

SPSW7C01 – Rev 10-07

© 2006 George Group Consulting, L.P.

Time Trap Analysis

Validating Project Focus

Page 2: Time Trap Analysis

SPSW7C01 – Rev 10-07

© 2006 George Group Consulting, L.P.

What Is a Time Trap?

A time trap limits the output of the process (operational or transactional) and therefore has less capacity than the prior or following steps/operations. It constrains throughput.

A time trap can change over time (monthly, weekly, even daily) based upon “product” mixes or special causes (new product introductions, special orders).

A time trap can be caused by physical problems (such process flow, personnel availability, part/supply shortages, equipment availability).

A time trap can also be caused by non-physical problems (such as procedures, morale, unsafe environment, or training).

There is ALWAYS a time trap in a process!

A Constraint is a time trap that cannot meet customer demand (a Constraint is ALWAYS a time trap, but a time trap may not be a Constraint!).

This is aTime Trap!!

Page 3: Time Trap Analysis

SPSW7C01 – Rev 10-07

© 2006 George Group Consulting, L.P.

How Are Time Traps Created? Poor process flow

Machine

People

Lack of parts

Transportation methods (cranes, foot, etc)

Handoffs

Large batch sizes

Operational deficiencies Setup Scrap (low yield) Downtime Rework

Distance

Safety concerns

Poor scheduling

Product mix

Excessive WIP

Variability of the process

Stress

Turnover

Etc.

Page 4: Time Trap Analysis

SPSW7C01 – Rev 10-07

© 2006 George Group Consulting, L.P.

More Lean Definitions

The following terms are used frequently to quantitatively describe the output of a process: Capacity: The maximum amount of product (output) a

process can deliver (produce) over a continuous period of time Example: The capacity of our process is 120 mortgage

applications per day Time Trap: The process step that inserts the largest

amount of time delay into a process (there can be only one time trap at a time in a process!) Example: Our property appraisers evaluate 120 properties per

day, all other process steps can process 145 applications per day

Constraint: A time trap that is unable to produce at the exit rate required to meet customer demand (internal or external) Example: Our property appraisers can only evaluate 120

properties per day, but customer demand is currently 130 applications per day!

Page 5: Time Trap Analysis

SPSW7C01 – Rev 10-07

© 2006 George Group Consulting, L.P.

The Importance of Time Traps

The time trap of this process is here:

If we do not understand where a time trap exists, we may end up focusing our improvement project on the wrong task/activity.

Unless we attack the time trap, throughput will not be affected.

Activity 1 2 3 4 5 6 7

Max ExitRate

Demand

Page 6: Time Trap Analysis

SPSW7C01 – Rev 10-07

© 2006 George Group Consulting, L.P.

The Importance of Constraints

This time trap is also a constraint

If we do not alleviate the constraint, our process will be unable to meet customer demand!

Activity 1 2 3 4 5 6 7

Max ExitRate

Demand

Page 7: Time Trap Analysis

SPSW7C01 – Rev 10-07

© 2006 George Group Consulting, L.P.

Time Trap Identification vs Constraint Identification

With Time Trap Identification, we are interested in finding the operation or process that will facilitate improving process efficiencies

With Constraint Identification, we are interested in finding the operation or process that will facilitate increasing capacity

Time traps impact efficiencies by requiring more inventory, more equipment, more people, more material, and more time in order to meet customer demand. Constraints tend to be more serious in nature as they limit our ability to satisfy our customers!

Page 8: Time Trap Analysis

SPSW7C01 – Rev 10-07

© 2006 George Group Consulting, L.P.

Where Are the Time Traps? Where the Inventory Stacks Up?

Careful!

Assy E (from

A, B, C,/D)

Page 9: Time Trap Analysis

SPSW7C01 – Rev 10-07

© 2006 George Group Consulting, L.P.

Copyright Notice

This Training Manual and all materials, procedures and systems herein contained or depicted (the "Manual") are the sole and exclusive property of George Group Consulting, L.P. (“George Group”).

The contents hereof contain proprietary trade secrets that are the private and confidential property of George Group. Unauthorized use, disclosure, or reproduction of any kind of any material contained in this Manual is expressly prohibited. The contents hereof are to be returned immediately upon termination of any relationship or agreement giving user authorization to possess or use such information or materials. Any unauthorized or illegal use shall subject the user to all remedies, both legal and equitable, available to George Group. This Manual may be altered, amended or supplemented by George Group from time to time. In the event of any inconsistency or conflict between a provision in this Manual and any federal, provincial, state or local statute, regulation, order or other law, such law will supersede the conflicting or inconsistent provision(s) of this Manual in all properties subject to that law.

© 2007 by George Group Consulting, L.P. All Rights Reserved.