time revision
TRANSCRIPT
-
8/8/2019 Time Revision
1/21
11
RS Management Consulting House
RS Management Consulting House
TimeTime
RevisionRevision According to PMBOK Third Edition
-
8/8/2019 Time Revision
2/21
22
RS Management Consulting House
RS Management Consulting House
Arrow Network Techniques
Case 1:
A < C, B & B < D & C < D
Dummy Activity (Dashed Arrow)Dummy Activity (Dashed Arrow)
(2 3) = activity C(2 3) = activity C
(2 3) = activity B(2 3) = activity B
1 2 3 4AA CC DD
BB
-
8/8/2019 Time Revision
3/21
33
RS Management Consulting House
RS Management Consulting House
Ca se 1
T he Right:
E is Dummy Activity (Duration = 0)
A < C, B & B < D & C < D
AA CC DD
BB EE
-
8/8/2019 Time Revision
4/21
44
RS Management Consulting House
RS Management Consulting House
Ca se 2A < C & B < E & C < D, E
Because B is not < DBecause B is not < D
AA CC DDBB
EE
-
8/8/2019 Time Revision
5/21
55
RS Management Consulting House
RS Management Consulting House
Ca se 2
A < C & B < E & C < D, E
AA CC DD
BBEE
-
8/8/2019 Time Revision
6/21
66
RS Management Consulting House
RS Management Consulting House
Ca se 3
A < D, E & B < E, F & C < F
A is not < FA is not < F
AA
CC
DD
BB
FF
EE
-
8/8/2019 Time Revision
7/21
77
RS Management Consulting HouseRS Management Consulting House
Ca se 3
AA
CC
DD
BB
FF
EE1 3 6
2
4
5
A < D, E & B < E, F & C < F
-
8/8/2019 Time Revision
8/21
88
RS Management Consulting HouseRS Management Consulting House
Ca se 4
A < C & B < D & C < D
1 2 4 5AA CC DD
BB 3 XX
Dummy x is unnecessaryDummy x is unnecessary
-
8/8/2019 Time Revision
9/21
-
8/8/2019 Time Revision
10/21
1010
RS Management Consulting HouseRS Management Consulting House
Ca se 5:
A < C & B < C, D, E & C < E
CC
1 5
4AA
DDBB
2
3
EE
xx zz
B is a redundant restriction on EB is a redundant restriction on E
-
8/8/2019 Time Revision
11/21
1111
RS Management Consulting HouseRS Management Consulting House
Ca se 5
No need for Dummy Z
1
54AA
CC
DDBB
2
3 6
EE
xx
A < C & B < C, D, E & C < E
-
8/8/2019 Time Revision
12/21
1212
RS Management Consulting HouseRS Management Consulting House
Example:Given the data for a small project.
-
8/8/2019 Time Revision
13/21
1313
RS Management Consulting HouseRS Management Consulting House
Solution:
Critical Path = A, C, D, F & GProject Duration = 24 days
A0 0 5
0 5 5
B5 5 11
10 6 16
C
5 0 9
5 4 9D
9 0 16
9 7 16
E9 3 18
12 9 21
F16 0 21
16 5 21
G21 0 24
21 3 24
-
8/8/2019 Time Revision
14/21
1414
RS Management Consulting HouseRS Management Consulting House
Example
Consider the simplified activity-on-arrow description of a project network given in the table:
(a) Draw the CPM network for this task structure.(b) Determine the project duration.
-
8/8/2019 Time Revision
15/21
1515
RS Management Consulting HouseRS Management Consulting House
DurationyA (1,2) 8B (2,3) 10C (2,4) 2
D (3,4) 16E (3,5) 4F (4,5) 8G (3,6) 7H (4,6) 12I (5,7) 3J (6,7) 8K (7,8) 2
ask Activity
-
8/8/2019 Time Revision
16/21
1616
RS Management Consulting HouseRS Management Consulting House
Solution:
Project Duration = 56 days
Critical Path = A, B, D, H, J & K
6
4
7 83
E
4
J
8
H 128
32 1034
C
2
34
34
D
16
1 2
5
0 A 8
0 8 8
8 B 18
8 10 18 54 B 56
54 2 56
18
39
G
7
2546
2251
1847 34
43 F8 4251
4646 54
5446 46
34 3418
18
4251
4554
I
3
-
8/8/2019 Time Revision
17/21
1717
RS Management Consulting HouseRS Management Consulting House
Ex. (3):Ex. (3):
A project consists of the activities shown in the table. The durationsA project consists of the activities shown in the table. The durationsrepresent the optimisticrepresent the optimistic ( a), ( a), most likely (m). and pessimistic (b)most likely (m). and pessimistic (b)times (days) for each activity. Find the critical path for this PERTtimes (days) for each activity. Find the critical path for this PERT
Network. Network.
a m b(1,2) 5 8 10(1,3) 18 20 22(1,4) 26 33 40(2,5) 16 18 20
(2,6) 15 20 25(3,6) 6 9 12(4,7) 7 10 12(5, 7) 5 7 8(6, 7) 3 4 5
ActivityDuration (days)
a m bA (1,2) 5 8 10 8B (1,3) 18 20 22 20C (1,4) 26 33 40 33D (2,5) 16 18 20 18
E (2,6) 15 20 25 20F (3,6) 6 9 12 9G (4,7) 7 10 12 8H (5,7) 5 7 8 7M (6,7) 3 4 5 4
Activity Duration
-
8/8/2019 Time Revision
18/21
1818
RS Management Consulting HouseRS Management Consulting House
S olution For Ex. ( 3 ):
-
8/8/2019 Time Revision
19/21
1919
RS Management Consulting HouseRS Management Consulting House
Examp le:Activity
duration(weeks)
PrecedingActive
Overlap
A 5 - -
B 4 A -
C 5 A Lag 1
D 5 A -
E 5 B Overlap 2
F 4 B,C -
G 6 D -
H 4 E Overlap 1
I 3 F, G - , overlap 2
j 2 H,A,I -
-
8/8/2019 Time Revision
20/21
2020
RS Management Consulting HouseRS Management Consulting House
Examp le:
Draw the network for above project.
Calculate the total project duration &indicate the C.P.
Calculate total Flout & Free flout for eachactivity.
-