TIDVG2014 Production and installation Status. 30 /07/2014 – “TIDVG Follow-up Meeting”. Ivo Leitão. General Planning TIDVG2014. Graphite. A luminium. Tungsten. Lower Yoke. Core. U pper Yoke. Copper. Necessary operations to produce the TIDVG2014: - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: TIDVG2014 Production and installation Status

TIDVG2014PRODUCTION AND INSTALLATION

STATUS

30/07/2014 – “TIDVG Follow-up Meeting”Ivo Leitão

Page 2: TIDVG2014 Production and installation Status

General Planning TIDVG2014

Upper Yoke Core Lower Yoke

GraphiteAluminium

Copper

Tungsten

Necessary operations to produce the TIDVG2014:• Prepare spare yokes Disassemble TIDVG2004 (radioactive) and remove old core.• Prepare new core Finalize the bake-out and place temperature sensors.• Assemble and test TIDVG2014 (alignment survey + water leak test).• Remove TIDVG2013 (damaged TIDVG presently installed in BA1 - SPS).• Install, test and bake-out the new TIDVG2014.

OK

Ongoing

To be completed

To be completed

OK

Page 3: TIDVG2014 Production and installation Status

Completed Tasks Assembly of the TIDVG2004 + Pressure test (EN/STI, HE/HH

& DGS/RP)OK

Bldg. 954

Page 4: TIDVG2014 Production and installation Status

Operations for Next Weeks Week 28/07 – 01/08:

Installation of the PT100’s on the core & transport to Bldg. 954. Assembly of the TIDVG2014 & water leak test. External cabling preparation Alignment survey Acceptance of TIDVG2014 (Project milestone!)

Week 04/08 – 08/08: BA1-SPS area preparation

Week 11/08 – 15/08: Removal of TIDVG2013 Installation of TIDVG2014

Following weeks: Bake-out in tunnel

Page 5: TIDVG2014 Production and installation Status

THANK YOU

30/07/2014 – “TIDVG Follow-up Meeting”Ivo Leitão