tiara wp2 report and wrap-up final annual meeting r. aleksan nov. 27 th, 2013

12
TIARA WP2 Report and wrap-up Final Annual Meetin R. Aleksan Nov. 27 th , 2013

Upload: loraine-parks

Post on 26-Dec-2015

229 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: TIARA WP2 Report and wrap-up Final Annual Meeting R. Aleksan Nov. 27 th, 2013

TIARA WP2 Report and wrap-up

Final Annual MeetingR. Aleksan

Nov. 27th, 2013

Page 2: TIARA WP2 Report and wrap-up Final Annual Meeting R. Aleksan Nov. 27 th, 2013

Define the Governance of TIARA Actual work concentrating on

Statutes Management structure

Advisory mechanisms & bodies Collaboration with other bodies Financial aspects Organization of CD&O

Main tasks

All documents are on WP2 work space

February 23rd, 2011 April 4th, 2011 May 24th, 2011 October 17th, 2011 March 2nd, 2012 June 12th, 2012 October 31st, 2012

Meetings+ subgroup meetings

SubgroupReports Available

report available

February 18th, 2013 June 7th, 2013 October 12nd, 2013 November 25th, 2013

WP2 Tasks

Page 3: TIARA WP2 Report and wrap-up Final Annual Meeting R. Aleksan Nov. 27 th, 2013

4 deliverables

WP2 Tasks

Page 4: TIARA WP2 Report and wrap-up Final Annual Meeting R. Aleksan Nov. 27 th, 2013

Creation of a multi-field coordinated panEuropean multi-purpose Distributed Accelerator R&D Infrastructure within an Association (AISBL)

TIARA WP2 Objectives

WP2 is actively working toward finalizing the remaining documents, enabling to develop the framework for

allowing us to get supports for developing the programmes that have been discussed during this preparatory phase

b

Page 5: TIARA WP2 Report and wrap-up Final Annual Meeting R. Aleksan Nov. 27 th, 2013

The 4 Technical WPs are in great shape

WP6: SVET Very low emittance achieved at SLS <1pm (world record) Improved diagnostics being installed a even better ey

WP7: ICTF Nominal RF amplifier power reached (2MW) @Daresbury Being installed in ICTF hall @RAL for MICE operation New DiacrodeAmplifier developed and tested successfully at Los Alamos (3

MW)

WP8: HGA 2 New C-Band structures successfully constructed Being installed for high power tests on SPARC @LNF

WP9: TIHPAC Design of Multi-MW test Irradiation Facility completed Design of the versatile SC Cavity test Cryostat close to completion

Confirmation the great work done

b

Excellent Infrastru

cture showcase

Final WP Reports need to be done by end 2013

Page 6: TIARA WP2 Report and wrap-up Final Annual Meeting R. Aleksan Nov. 27 th, 2013

4 Organizational WPs have made impressive progress as well WP3: Infrastructures Survey and RI database established Finalization of the list of Infrastructures being part of TIARA Needs vs resources comparison and upgrades/ construction of new RI being

finalized

WP4: R&D programme Key Accel. Research Area and Key Tech. Issues been identified Final plan of the collaborative R&D Programme being finalized

WP5: Education and Training E&T Survey and resource database established Survey of Needs for Accel. Scientists done Recommendations for promoting Accel. Science and Tech. in Europe done

Work Status

bb

b

WP2: Governance Legal statutes of TIARA are being drafted a pressure on WP2

Excellent studies highlighting TIARA potential

to strengthen Accel. R&D

Final WP Reports need to be done by end 2013

Page 7: TIARA WP2 Report and wrap-up Final Annual Meeting R. Aleksan Nov. 27 th, 2013

… also with advertising material

Important to use them to promote TIARA

Promoting TIARA

To implement TIARA, important now to do lobbying at all levels EC level Funding agency level Laboratory level Your colleague level

You can be proud of the work you have done

Page 8: TIARA WP2 Report and wrap-up Final Annual Meeting R. Aleksan Nov. 27 th, 2013

… but also as shown by a lots of happy faces

Very successful meeting

as demonstrated by the great achievements reported

Page 9: TIARA WP2 Report and wrap-up Final Annual Meeting R. Aleksan Nov. 27 th, 2013
Page 10: TIARA WP2 Report and wrap-up Final Annual Meeting R. Aleksan Nov. 27 th, 2013
Page 11: TIARA WP2 Report and wrap-up Final Annual Meeting R. Aleksan Nov. 27 th, 2013

Heartily thanks toProf. Swapan Chattopadhyay

and

Prof. Peter McIntosh

Prof. Susan Smithand

for hosting TIARA

Finally and once again

But also and specially to

for doing all the work!!!Sue and Mary

Page 12: TIARA WP2 Report and wrap-up Final Annual Meeting R. Aleksan Nov. 27 th, 2013

Conclusions

Accelerator science; a powerful mean toward scientific, technical and industrial breakthroughs…

TIARA will strengthen further

The objectives of TIARA are very ambitious and challenging

The last 2 months are vital as we have to come to a concrete proposal for implementation

Overall Work is progressing very well, but there is still a lot to do for this endeavor to be successful

… this NOT the end, and we have still a lot of great things to to all together and your dedication will be essential

I wish you a safe trip back home