THUBELISHA HOMES CLOSURE REPORT. Presented to the Portfolio Committee on 8 July 2009. Background. Thubelisha’s Closure Plan prepared in Sept 08. Approved by the Minister of Housing on 15 Dec 08 Delay in approval resulted in: Revised closure timeframe Updated closure cost estimates - PowerPoint PPT PresentationTRANSCRIPT
THUBELISHA HOMES CLOSURE
REPORT
Presented to the Portfolio Committee on
8 July 2009
Thubelisha’s Closure Plan prepared in Sept 08.
Approved by the Minister of Housing on 15 Dec 08
Delay in approval resulted in:•Revised closure timeframe•Updated closure cost estimates
Updated Closure Plan submitted to NDoH on 28 Jan 2009
Steering Committee request for commitment from NDoH to fund closure costs received on 3 March 2009
Implementation of closure process commenced on 9 March 2009 with a guarantee of closure costs by NDoH
Background
The Closure Steering Committee established the following Task Teams:
• Human Resources
• Projects
• Facilities & Assets
• Finance & Accounting
Closure Task Teams
The following processes have been completed: • H D A confirmed all staff in WC offered positions
• Firm undertaking from North West Province to absorb 5 staff; 2 still to be redeployed • Northern Cape Province will absorb 2 staff; 1 staff being offered a position by the H D A • Voluntary severance package taken up by 30 staff
• Staff where no commitments have yet been made (40): (See table attached)
Human Resources Task Team …
Human Resources Task Team …
Province Number of Staff
VSPs Boarded/
Died/Resig
HDA Province
Certain
Balance
Head Office
30 13 1 1 15
Gauteng 20 8 12
Eastern
Cape
1 1
Zanemvula
13 1 12 0
Western
Cape
10 2 8 0
N2 Gateway
23 1 22 0
Northern
Cape
5 2 1 2 0
North West
10 2 1 5 2
Limpopo 4 4
Kwazulu
Natal
8 1 1 6
Total 124 30 3 44 7 40
• Redeployment of staff to Gauteng & KZN is dependent on NDoH to funding these staff placements for the balance of the financial year
• Good progress made i.t.o. staff changes in provident funds and medical aid. Consultants made available to all staff
• All Stannic garage cards cancelled at the beginning of June; Nashua 3G contracts have yet to be cancelled
Human Resources Task Team … (con’t)
• Way Forward:
• Approval by NDoH regarding the payment of subventions particularly to Gauteng & KZN
• Alternate to above, commitment by NDoH to take over 40 remaining staff if not employed
• Meetings with Limpopo/KZN/Gauteng Provinces to have follow up meetings
• Finalisation of VSP, including application for tax directives
• Finalisation of offers of employment from H D A & Provinces where redeployments have been arranged
Human Resources Task Team … (con’t)
The following processes are underway / have been completed: • All rental agreements have been cancelled or agreed to be paid to lease termination. Negotiations with Nasdhua have been finalised and settlement agreed
• Negotiations with Telkom finalised; letters sent to Telkom cancelling remaining contracts; transfer of certain contracts for telephone and data lines to H D A
• All furniture for transfer to H D A from HO and Gauteng branch identified. Balance of furniture to be auctioned to staff or disposed of per Closure Plan with treasury approval
• Western & Eastern Cape assets will be transferred to the H D A with treasury approval
• Transfer of assets to N Cape and N West Provinces proposed along with transfer of staff with treasury approval
• Assets in Limpopo/KZN/E London with be dealt with at meetings with the Provinces
Facilities Task Team
• All loan contracts such as coffee and water machines cancelled from 31 July 2009
• Way Forward:
• Cancellation of Nashua 3 G cards to be formalised by no later then 31 July 2009;
• Timing of collection of unused Nashua printers to be handled by Thubelisha staff
• Thubelisha Management undertakes to facilitate auction of Head Office and Gauteng Offices assets
Facilities Task Team ….(Cont)
Way Forward:
• Response from Thubelisha regarding status of projects in EC/WC/Mpumulanga/Limpopo
• Meetings planned as follows:Eastern Cape - 30 JuneLimpopo - 30 JuneWestern Cape - 8 JulyMpumulanga - still to be
determined
• Draft contracts i.r.o. cessions to be approved by Legal
• Notification to all creditors to be sent out by 31 July 2009 notifying them of closure of operations
• Key focus of project closure team will be financial reconciliation of all projects after discontinuation of operations on 31 July 2009
Project Task Team ….
• NHFC loan repaid• MIG debtors of approximately R60 M still not received
• VAT verification process is almost complete which will enable further negotiations with SARS regarding recovery
• Claim submitted to NDoH for first portion of Closure Cost (VSP & contract terminations). No amount received from NDoH yet
Way Forward•Bring financial records up to date
•Analyze and collect all debts
•Meet with NHFC regarding settlement of Interest of loan
•Negotiate with H D A regarding future of MIG debtors
•Progress the VAT refund
Finance & Accounting