the fp7 hilumi lhc design study and hl-lhc project
DESCRIPTION
The FP7 HiLumi LHC Design Study and HL-LHC project. Lucio Rossi HL-LHC Project Coordinator – CERN FP7 HiLumi Public Meeting 18 November 2011. Luminosity : educated guess over 10 y. Shut down to fix interconnects and overcome energy limitation (LHC incident of Sept 2008). - PowerPoint PPT PresentationTRANSCRIPT
The FP7 HiLumi LHC Design Study and HL-LHC project
Lucio RossiHL-LHC Project Coordinator – CERN
FP7 HiLumi Public Meeting18 November 2011
LRossi-16Nov2011 2
Luminosity: educated guess over 10 y
Hdw limit?
Shut down to fix interconnects and overcome energy limitation (LHC incident of Sept 2008)
Shut down to overcome beam intensity limitation (collimation,New Cryo P4,…)Inj. upgrade
LRossi-16Nov2011 3
The need for the upgrade
LS3
LRossi-16Nov2011 4
High Luminosity LHC (HL-LHC) historyTask force chaired by Francesco Ruggiero in 2001
Radiation damage limit ~700 fb-1
CERN task force on LHC machine upgrade -> LHC PR 626+666Luminosity: Lnom=1034 -> 1035, Energy: Ecm=14 TeV -> 25 TeV
Plan luminosity upgrade by 2014. New low-b quads with high gradient and larger aperture based on Nb3Sn SC require 9-10 years for short model R&Dand component development, prototyping, and final production.
SC magnet R&D for lumi upgrade also useful for energy upgrade: can beintegrated with LHC magnet consolidation. Beam dynamics R&D for LHCcommissioning also useful for LHC upgrade: needed to guide new IR design.
Slide from F. Ruggiero , 2004
Plot J. Strait
LRossi-16Nov2011 5
High Luminosity LHC (HL-LHC) historyLHC construction period• Lhc Accelerator Research Programme, LARP
• LARP has given fundamental contribution to the hardware development and to the conceptual study for High Lumi
• FP6-CARE• HHH, a newtwork on accelerator physics & magnets design • NED Joint Research Activity : development of HF Nb3Sn SC
• 2007: following Lisbona EU strategy for HEP, White Paper: the split into Phase I and II• Phase I : 21034 peak with 120mm-120 T/m MQX for 2013• Phase II: 101034 peak ? with Nb3Sn MQX for 2020?
LRossi-16Nov2011 6
High Luminosity LHC (HL-LHC) historyLHC commissioning & first operation period
• Chamonix 2010: Phase for 2016-17 ? Longer than expected shutdown. Limited performance, machine less flexible.
• Decision of CERN Mngt, summer 2010 (formalized in Nov.2010) :
Regroup main upgrade for >2020: HL-LHC 3000 fb-1 in 10-12 year run 250 fb-1/yPeak lumi 51034 cm-2s-1 levelling
• Start thinking to HE-LHC• WG chaired by Steve Meyer, started March 2010• Workshop Malta, October 2010
LRossi-16Nov2011 7
LEP/LHC : the best use of the (renovated) existing infrastructure
LHeC ?
LRossi-16Nov2011 8
Cycle in the HL-LHC run20E+34 pile up
heat deposition in IR and DSother?
Levelling
150 days of Physics /y of this cyclewith 60% efficiency will give 250 fb-1
Which set of parameters we need to reach this goal?
LRossi-16Nov2011 9
Tuning of the goal after summer
Efficiency is defined as the ratio between the annual luminosity target of 250 fb-1 over the potential luminosity that can be reached with an ideal cycle run time with no stop for 150 days: trun= tlev+tdec+tturn. The turnaround time after a beam dump is taken as 5 hours, tdecay is 3 h while tlev depends on the total beam current
LRossi-16Nov2011 10
Our Final Goal: Given by Physics3000 fb-1 in 10-12 year of RUN
LRossi-16Nov2011 11
Many changes : IR Magnets (triplet, D1, D2, MQ4, …) SC Crab Cavities, IR Col, New Cryo IP1-IP5, Cold Powering on surface 0.1-1 GW d.c. HTS
LRossi-16Nov2011 12
Opportunity, just when HL-LHC started
• FP7 Design Study call: deadline 25 Nov 2010• (experience with FP7-sLHC-PP, FP7-EuCARD)
• Forming the consortium• 14 Institutes from the EU Research Area• 5 from USA, 1 from JP
• Called FP7 HiLumi LHC Grant Agreement 284404
LRossi-16Nov2011 13
Budget FP7 HiLumi and HL-LHC
Perfect score 15/15,
ALL request to EU
granted
Design in FP7 HiLumi
Extra effort for Design
R&D and proto
Industrialization & Construction TOT Industry
W1-WP6 27 10 50 200 287 160WP7-12 0 15 30 100 145 80Other 0 5 10 50 65 40TOT 27 30 90 350 497 280
Estimated cost for the the whole HL-LHC over 10 years in M€ (October 2010)
LRossi-16Nov2011 14
Status of the FP7 DS• Grant Agreement signed by EC in October and
now by all Beneficiaries
• First tranche of money (60% of the 4.9 M€) from EU has arrived to CERN, for redistribution
• Consortium Agreement sent to partner• The US labs will partecipate to FP7 HiLumi as
associate partner (under existing agreement or with a new MoU
LRossi-16Nov2011 15
Staff for HiLumi LHC (EU FP7)Sum of pm Column Labels
1 2 3 4 5 6 Grand TotalRow LabelsCERN 114 101 90 107 123.6 58 593.6CEA 24 48 6 78CNRS 40.8 40.8DESY 12 12INFN 67.2 44 22 133.2BINP 65 65CSIC 24 38 62EPFL 48 48RHUL 64 64SOTON 71 71STFC 28 31 59ULANC 70.5 70.5UNILIV 34.8 34.8UNIMAN 34.8 58 92.8KEK 19.2 72 68.5 159.7Grand Total 114 458 254 323.8 283.6 151 1584.4
LRossi-16Nov2011 16
Staff HiLumi with 377 p-m by US LabsSum of pm Column Labels
1 2 3 4 5 6 Grand TotalRow LabelsCERN 114 101 90 107 123.6 58 593.6CEA 24 48 6 78CNRS 40.8 40.8DESY 12 12INFN 67.2 44 22 133.2BINP 65 65CSIC 24 38 62EPFL 48 48RHUL 64 64SOTON 71 71STFC 28 31 59ULANC 70.5 70.5UNILIV 34.8 34.8UNIMAN 34.8 58 92.8KEK 19.2 72 68.5 159.7BNL 14.4 42 60 116.4FNAL 4 56.64 18 12 0 90.64LBNL 4 48 18 18 88ODU 48 48SLAC 4 14.4 16 0 34.4Grand Total 126 591.44 332 477.8 283.6 151 1961.84
163 FTE-y
LRossi-16Nov2011 17
The HL composition
WP1 Project Management and Technical Coordination
WP2 Accelerator Physics and Performance
WP3 Magnet Design
WP5 IR Collimation
WP6 Cold Powering
WP4 Crab Cavities
HiLumi LHC
WP7 Machine Protection
WP8 Collider-Experiment Interface
WP9 Cryogenics
WP10 Energy Deposition and shielding
WP11 11 tesla dipole two-in-one
WP12 Integration & (de)installation
Non-HiLumi LHC
HL-LHC Design Study
CollimationProject
Matching section and correctors
Beam Diagnostics
High Field Magnets R&D
HE-LHC Studies Hardware Commissioning
DS collimation shifted in 2018Cryo-col + 11 T Dip. is now in baseline (but it must be demonstratedSC links gets support
from various collaborations
Study on HE-LHC gets wider supportEuCARD2 WP on HTS dipoles
LRossi-16Nov2011 18
HL-LHC Project
1. Project Management & Technical Coordination
2. Accelerator Physics and Performance
3. Magnets for IRs
4. Crab Cavities (CC)
5. Collimation project
6. Cold Powering
7. Machine Protection
8. Collider-Experiment Interface
9. Cryogenics
10. Energy Deposition & Absorber
11. 11-T Dipole Two-in-One for DS
12. Vacuum
13. Beam Diagnostics
14. Integration and (de-)installation
15. Hardware commissioning
16. HE-LHC Studies
17. High Field Magnet R&D - FRESCA2
FP7 HiLumi
Same technology,
strong synergy
• 750 MCHF new evalution M• 1000 FTE-y P• P+M 1000 MCHF (CtC !!!)• For convenience each system
regroup activities under FP7 HiLumi and outside it
• The StCom (Steering Committe, were all WP/System leaders are represented) will alternate meetings restricted to HiLUmi and extended to whole HL.
• We will not distinguish between FP7 beneficiaries (EU+KEK) and US labs except when necessary
Budget under construction
LRossi-16Nov2011 19
HiLumi is the focal point of 20 years of converging International collaboration• The collaboration wiht US and JP
on LHC upgrade started during the construction of LHC
• EU programs have been instrumental in federating all EU efforts
•With Hi-Lumi the coordination makes a step further: from coordinated R&D to a common project
• CERN is not anymore the unique owner, rather is the motor and cathalizer of a wider effort.
• Managed like a large detector collaboration (with CERN in special position as operator of LHC)
LRossi-16Nov2011 20
Governace HL-LHCFP7 HiLumi LHC DS is the driver of a larger project, aimed to construction
L.Rossi-Mngm&TC@HiLumi 17Nov2011 21
List of WP/Systems Coordinators WP1 WP2 WP3 WP4 WP5 WP6 MNGT
Management & Technical Coordination
APPAccelerator Physics & Performance
MAGMagnet Design
CCCrab Cavities
COLIR Collimation
CPCold Powering
Coordinator Lucio Rossi CERN
Oliver Bruning
CERN
Ezio Todesco CERN
Erk Jensen CERN
Ralph AssmannCERN
Amalia BallarinoCERN
Co-Coordinator
Oliver Bruning CERN
Andy Wolski UniLIV (UK)
Gianluca Sabbi
LBNL (USA)
Graeme Burt UniLAN (UK)
Grahame Blair
RHUL (UK)
Francesco BroggiINFN (IT)
WP7 Mach.Protection: J. Wenninger, R. Schmidt (CERN)WP8 Coll-Exp Interface: A. Ball, M. Nessi, H. Burkhart (CERN)Wp9 Cryogenics: L. Tavian, R. van den Weelderen (CERN)WP10 (Energy deposition): F. Cerutti (CERN), N. Mokhoff (FNAL)WP11 : 11 T Dipole : M. Karppinen (CERN, A. Zlobin (FNAL)WP16 : HFM R&D & FRESCA2 dipole G. de Rijk (CERN), F. Kircher (CEA)Saftey, namely RP: S. Roesler (CERN)Resource-Cost-Risk Coordinator : P. Bonnal (CERN)FP7 HiLumi Administrative Manager: S. Stavrev (CERN)Dissemination and outreach : K. Kahle (CERN)
LRossi-16Nov2011 22
This program and budget to do what?
CB of 17 Nov 2011 (yesterday!), message from President of Council, Prof. Spiro:PDR neede in preliminary form by Oct 2012, endorsed by SAC and MAC, approved by CERN Mngt for Council and HEP strategy Group (final step : Council Bruxelles June 2013)
LRossi-16Nov2011 23
Is it so difficult? Beam related issues…• Beam of > 1 A @ 7TeV (700
Mjoules!!)
• Most probably need of 25 ns (e-clouds and less brightness form Inj): qaultiy of collision vs quantity
• Very challanging AP issues…
• Needs of novel optics schemes (S. Fartouk)b 15 cm or lower
LRossi-16Nov2011 24
Is it so difficult? Magnet technology jump• LHC is already very pushed• Passing from 8 T (4 T today!) to 11 T in 2018 in LHC dipole• Passing to 12-13 T in IR Triplet: 140 mm!!• But is the only way to be on the path toward HE-LHC (15-20 T
in 40 mm)
LQ , 4 m, 90mm: 11 THQ, 1 m, 120mm: 13T
LRossi-16Nov2011 25
Is it so difficult? Crab Cavity, for p-beam transverse manipulation at fs level!