the construction programme - assurance and controls
DESCRIPTION
TRANSCRIPT
![Page 1: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/1.jpg)
London 2012 Learning LegacyThe Construction Programme:Assurance and Controls
Gordon AlexanderProgramme AssuranceOlympic Delivery Authority
![Page 2: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/2.jpg)
• 1 programme
• 19 major projects
• 15,000+ site workers
• 950 planning applications
• 4,400 unique design interfaces
• 2 site entry points (plus rail head)
• 869 critical Tier 2 and 3 suppliers
• 1,890 engineering technical reviews
• 120 NEC3 contracts, 149 JCT contracts
• 529 delivery vehicle movements each day
• 1,400 unique principal contractor boundaries
• 37,000 engineering drawings (and 35,000 revisions)
• 96 Tier 1 suppliers (29,000 contract communications)
• 27,000 activities and milestones in integrated plan
• 0.008 rolling Accident Frequency rate at completion
• 1 key date: 27 July 2012
529vehicle movements
each day
London 2012 in numbers
15,000+ site workers
135,000documents
controlled
37,000 engineering drawings
1Key date
![Page 3: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/3.jpg)
Work Breakdown Structure
London 2012 Work Breakdown Structure
• 69 Reporting Projects
• 1,000+ WBS Elements
• Common language across Programme
![Page 4: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/4.jpg)
Delivery of Olympic Park – The Plan (2006)
Year 1 (LDA, 2006/7) – Planning and Land AssemblyYear 2 (to Beijing 2008) – Demolish, Dig, DesignYear 3 (to 27 July 2009 – The Big Build (Foundations)Year 4 (to 27 July 2010) – The Big Build (Structures)Year 5 (to 27 July 2011) – The Big Build (Completion)Year 6 (to 27 July 2012) – Testing and Commissioning, the Games!
![Page 5: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/5.jpg)
Co-ordination of Land Areas
Management of 600+ LA areas
![Page 6: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/6.jpg)
Integrated Planning - The Need
Learning from previous Olympic programmes required an early need to address integration issues:
• Infrastructure and Venues works in parallel in a small area of land
• Key milestones for Infrastructure and Venues are driven from various project interfaces
• Design interfaces could lead to a project interface on site
• Principal Contractor methodology (site boundaries) and handovers of areas of land is a key interface factor
• Works by others in Principal Contractor areas could create disruption or re-sequence of works
![Page 7: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/7.jpg)
Integrated Planning
Delivery Partner fully accountable for managing the interfaces
• Planning
• Process / governance
• Scope / budget implications
• Assurance
One Programme• Priorities defined by the needs of the
Programme, not the loudest voice
Changing emphasis through lifecycle
![Page 8: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/8.jpg)
The Method• Establish a suite of processes,
meeting structure, reports and assurance framework
• Understand the interfaces using drawings, scope documents and the drivers for key deliverables
• Using weekly strategic and monthly detail integration meetings to review interfaces or understand and capture new ones
• Capture the timing of the interface, the type, and the cost and schedule impact to successor activities or projects (trend and raise changes)
• Implement in P6 using specific processes / procedures/Coding structures
• Intensive tracking and monitoring
![Page 9: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/9.jpg)
Delivery Platform - Schedule Milestone Integration
![Page 10: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/10.jpg)
The People• Construction Integration Teams to understand and capture the interface
• Integration Planners to implement the interface in P6
• Both teams to monitor the interface through meetings and regular reporting
• Regular weekly/bi-weekly co-ordination meetings with project teams
• Identification of 3rd Party representatives and regular meetings
• Infrastructure/Venue directorates responsible for park integration
• Monthly Executive level meetings to discuss Amber/Red integration issues
![Page 11: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/11.jpg)
The Logistics Project
7 venues, 70 projects
Over 5 utility providers
Enabling works North & South
Structures, Bridges & Highways
Landscape & Public Realm
Network Rail
Waterways
Security capital projects
All have their own supply chain,
workforce, programme, space
requirements and transport needs
Uncontrolled this would result in:
Unacceptable traffic congestion around
the Park
Congested principal road arteries in
east London
Restricted site access
Chaotic site management
arrangements
Delayed labour cost £250k per day
Difficult labour retention
No support for the sustainability agenda
A Logistics operation was established which controlled the entire site – Business case proved to government, also lesson learned from T5
![Page 12: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/12.jpg)
Objective
Project Controls
• Present trusted information to the right people, at the right time to facilitate effective decision making
• Challenge is to navigate a mass of data and convert it into transparent and actionable management information
00 Month 200715
![Page 13: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/13.jpg)
Key Processes
• Decision “Rules”
• Latest responsible date for action
• 80/20
• Protect the float
• Be flexible - adjust controls systems to suit the phase and nature of construction
• Keep it Simple – No jargon, clear, concise and graphic reporting – use data analytics but discuss the issue not the metric
![Page 14: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/14.jpg)
Earned Value to monitor progress
• All 32 criteria specified in ANSI / EIA 748 and APM were applied – but emphasised some more than others
• Single data collection structure implemented through project teams and into Tier 1 contractors
• Fully integrated budget-loaded programme
• Earned Value (£) as the common means of reporting progress across diverse projects
• Baseline kept current (via change control) to reflect the developing delivery strategies
• Strict financial control but did not differentiate between Budget and Funding
![Page 15: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/15.jpg)
Budget Forecasting and Management of Risk
Cost Planning Phase Delivery Phase(erosion of contingency)
Contingency
Risks
Design and
Construction
Costs
ODA Costs
CLM Fees
Contingency
Risks
Acknowledged Trends
UnsubstantiatedTrends
Mitigated
PM’s Assessment of Unsubstantiated Trends
and Risks
Original Contract Values
AcknowledgedTrends
Compensation Events
Potential AFC
QRA (P80) informs level of contingency
allowance
Savings Headroom
![Page 16: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/16.jpg)
Dynamic of Cost and Schedule Data
Baseline• Fixed• Controlled through Change
Management• Reflected current delivery strategies• Aligned with contract s• High Level – Project Milestones and
summarised Cost Loaded activities
Forecast• Dynamic• Reflects contractor current status &
progress • Includes mitigation strategies and
trends• Takes account of integration impacts• Forecasts outturn
Change Control
Fed from Trending process
Trending Process
Fed from forecast data and enabler for Risk mitigation
Compare Inform
Change
Drive
![Page 17: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/17.jpg)
Monthly Reporting Cycle
Gather data and upload to host systems
Assurance, analysis ,challenge and Project Reports
Executive Management Reviews & Programme Report
Executive Management Board and Change Board
![Page 18: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/18.jpg)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
F G I J K L M N O P Q R S T U
P ID ACTIVITY ID ACTIVITY DESCRIPTIONFORECAST MAY11
BASELINE MAY11
FORECAST JUN11
BASELINE JUN11
FORECAST JUL11
BASELINE JUL11
∆ FORECAST JUL11 - JUN11
∆ BASELINE
JUL11 - JUN11
∆ JUL11 FORECAS
T - BASELINE
REASON FOR VARIANCE (FC LAST MONTH - FC THIS MONTH)
EW EWSW7500 COMPLETION STOCKPILE MANAGEMENT OPERATION 04-Jul-11 04-Jul-11 27-Jun-11 04-Jul-11 27-Jun-11 04-Jul-11EW LKAV1050T HANDOVER TO AV - REMAINING MOL 6C AREA 25-Jul-11 25-Jul-11 25-Jul-11 25-Jul-11 25-Jul-11 25-Jul-11
EW LKEW2686THANDOVER OF ATHLETE'S VILLAGE TRANSPORT MALL (ZONE 6A) FROM EW TO SBH (PROV. 2010)
04-Jul-11 28-Sep-10 04-Jul-11 28-Sep-10 01-Aug-11 28-Sep-10 -28 0 -307Forecast for handover to SBH on 1st August.
Meets SBH requirement date.
EW EW1000 COMPLETION OF ALL ENABLING WORKS SCOPE 31-Aug-11 - 31-Aug-11 - 31-Aug-11 - 0 #VALUE!
NORTHPARK
LP LKLPR1000THANDOVER OF HOCKEY PITCH 1 (EXC. EAST STAND) AND HOCKEY PITCH 2 FROM CLM TO LOCOG
15-Jun-11 01-Jul-11 01-Jul-11 01-Jul-11 15-Jun-11 01-Jul-11
LP LKLVZ6.6D1TZ6.6 HANDOVER DUCTS & ELEC EQPT + DT - F03 EAST - NLR (CH.400) - LPR TO UTILITIES
31-May-11 18-Mar-11 28-Jun-11 18-Mar-11 28-Jun-11 18-Mar-11
LP LKLPSEZ6.6T Z6.6 - HANDOVER BASES, DUCTS, PITS & POSTS FOR CCTV - - - - 28-Jun-11 05-Aug-11
LP CLMLPR28301COMPLETION OF BACK OF HOUSE 4 - PHASE 1 HANDOVER to LOCOG for TEST EVENTS
- - 01-Jul-11 - 04-Jul-11 -
LP CLMLPR28302COMPLETION OF BACK OF HOUSE 4 - PHASE 2 HANDOVER TO LOCOG FOR TEST EVENTS
- - 15-Jul-11 - 11-Jul-11 -
LP LKLVZ5.4D1TZ5.4 HANDOVER DUCTS & ELEC EQPT + DT - F02 WEST-L03A - LPR TO UTILITIES
06-Jun-11 31-Mar-11 07-Jul-11 31-Mar-11 13-Jul-11 31-Mar-11
LP LKLVZ6.4D1TZ6.4 HANDOVER DUCTS & ELEC EQPT + DT - F02-B/BALL WEST - LPR TO UTILITIES
31-May-11 14-Jun-11 04-Jul-11 14-Jun-11 13-Jul-11 14-Jun-11
LP LKLVZ6.3D1TZ6.3 HANDOVER DUCTS & ELEC EQPT + DT - VELO WEST & STH / BMX STH - LPR TO UTILITIES
07-Jul-11 21-Jul-11 14-Jul-11 21-Jul-11 29-Jul-11 21-Jul-11
LP CLMLPR2300 COMPLETION OF SOFT LANDSCAPING 7 21-Jul-11 21-Jan-11 27-Jun-11 21-Jan-11 01-Aug-11 21-Jan-11 -35 0 -192All works in SL7 are now complete. Works were previously in delay to revised phasing strategy.
LP CLMLPR2190 COMMENCE BACK OF HOUSE 1 (HOCKEY) 01-Jul-11 15-Jul-10 01-Jul-11 15-Jul-10 01-Aug-11 15-Jul-10 -31 0 -382
Works proceeding in line with accepted programme. Works commenced in all areas of BH1 where handovers have occurred. Due to revised handover strategy some areas of BH1 have not yet started.
LP CLMLPR2260 COMPLETION OF SOFT LANDSCAPING 3 01-Jul-11 01-Mar-11 01-Jul-11 01-Mar-11 05-Aug-11 01-Mar-11 -35 0 -157
All works in SL3 are complete. Only item of remaining works is the final connection of the irrigation booster station to permanent power. This will be completed in August.
No programme impact to LPR.
LP CLMLPR24001 COMPLETION OF HL9 FOH BASKETBALL FOR TEST EVENT - - 05-Aug-11 - 05-Aug-11 - 0 #VALUE!
Works proceeding in line with accepted programme. Completion dates agreed in line with handover strategy to LOCOG.
No programme impact to LPR.
LP CLMLPR2310 COMPLETION OF SOFT LANDSCAPING 10 27-Jul-11 14-Feb-11 08-Aug-11 14-Feb-11 05-Aug-11 14-Feb-11 3 0 -172Works progressing in line with accepted programme. Due for completion early August 2011.
No programme impact to LPR.
LP LKLPSEZ6.4T Z6.4 - HANDOVER BASES, DUCTS, PITS & POSTS FOR CCTV - - - - 12-Aug-11 05-Aug-11 #VALUE! -7
Works being mitigated to achieve handover, but completion of amp base likely to be 19 Aug partially due to late instruction.
Possible impact on BT start.
LP LKLPSEZ6.3TZ6.3 - HANDOVER BASES, DUCTS, PITS & POSTS FOR CCTV & PA
- - - - 12-Aug-11 12-Aug-11 #VALUE! 0
Works proceeding in line with accepted programme. Completion dates agreed in line with handover strategy to ODA/BT.
No programme impact to LPR.
LP LKLVZ5.2D1TZ5.2 HANDOVER DUCTS & ELEC EQPT + DT - H01 WEST-F02 WEST - LPR TO UTILITIES
29-Jul-11 14-Aug-11 02-Aug-11 14-Aug-11 15-Aug-11 14-Aug-11 -13 0 -1
Works proceeding in line with accepted programme. Completion dates agreed in line with handover strategy to UKPN.
No programme impact to LPR.
ENABLING WORKS
LANDSCAPE & PUBLIC REALM
Schedule Reporting
• All Milestone Report≈700 key milestones in change-controlled Baseline, AMR includes commentary and RAG status
• Project Status ReportSimple view of project Baseline
• Critical Items ReportStatus/action on issues escalated in schedule integration process
• Critical PathsThe path or paths that drive project completion
• Strategic PlanHigh-level view of key interfaces and handovers for LOCOG Test Events and security lockdown of Olympic Park
![Page 19: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/19.jpg)
Project Cost Performance Reports At EVM Control Account level
Project Status ReportAdds Project Manager’s narrative and variance analysis to raw data
Programme Cost Performance ReportSummarises performance data in funding slices
Project and Programme Cost Reports Risk, Trends and Contingency / AFC modelling
Monthly Progress Report Short, simple distillation of status and key issues. Dashboards to communicate key performance trends to Executive
Progress, Performance & Cost Reporting
![Page 20: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/20.jpg)
Key Components of the Project Status Report
Awaiting graphic from Karen Astle
Health and Safety
Project Summary and critical issues
Quality Assurance
Design issues and decisions
Performance data (EVM) and cost / EV forecasts
...supported by quantities
Priority themes
Key risks and issues
Baseline milestones and forecasts
Project Cost Report – AFC model
![Page 21: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/21.jpg)
Single source of truth from off the shelf tools
A single source of truth for information
Schedule – Primavera
Budget – Cobra
Actual Cost – Oracle
Accruals – PCMS
Reporting – Crystal Reports
PCMS
OraclePrimavera P6
Crystal Reports
Cobra
![Page 22: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/22.jpg)
2006 2007 2008 2009 2010 2011
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
Controls Building Blocks in Place
Baseline developed & Yellow Book Published
Culture & Trust Established
Systems Maturing
Change Control implemented
Monthly & Quarterly Reviews
Trending Process
AFC process
Monthly Trend Reviews
Monthly Trend & AFC Reviews
Simplify Baseline
Schedule Integration maturing
Support & Training
Assurance, Support & Intervention (where necessary)
Align Reporting
Maturity Timeline
Big Build; CompletionBig Build; StructuresBig Build; FoundationsDesign, Dig, Demolish
Controls mature and
fully functional
![Page 23: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/23.jpg)
Organisation and Roles
![Page 24: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/24.jpg)
Commercial delivery - Who does what
Project controls
• Project financials
(ODA/CLM, central cost
allocation)• Project cash flow (phasing)• Cost to Complete• Schedule performance• Earned value, CPI & SPI• Data integrity• Project Change Control• Project WBS• Supplier project controls
Contract Admin
• Management of Contract
deliverable schedule• Payment Certification• Contract Accruals & Cash
Flow• EWN & CE (legitimacy &
value)• Contract variations• 2nd tier (VfM)• Monthly contract financials,
confirm input data• Contract risk/contingency
management• Pain/Gain incentivisation (if
applicable)• Cost to Complete (contract)• Disallowable cost
Cost verification
• Verify supplier’s cost collection system and processes are fit for purposes
• Audit supplier’s cost collection system, site labour and plant records.
• Confirm submitted invoices accurately reflect incurred cost as per supplier’s financial systems
Risk ( contingency)
• Ensure consistent approach to managing risk and opportunities across the project/contracts
• Fully costed time phased profiled contingency budget with mitigating actions.
• Assessment of risks (and opportunities) to determine what risks would benefit from programme focus, as opposed to project.
• Align project/contract change requests with contingency budget provisions.
Commercial Leader
• Overall project commercial management strategy• Integrity of reports and actions to improve commercial outcomes• Ownership and maintenance of the Cost Plan (budget, phaseing,etc)• Delivery of AFC/Project close out strategy• Project Supplier Relationships• Incentivisation strategy• Mitigation of contingency/risks• Ensure alignment with DP contract
Project Manager
Design ManagerCommercial Leader
Project Controls
Commercial Leader
Cost verification
Risk (contingency)
Contract Admin
![Page 25: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/25.jpg)
Connecting with the Supply Chain
Connecting with the Supply Chain
• Reach out to involve people in Tier 1 and beyond – management to workface
• Rigid control and assure outputs for objectives, standards and reporting toolset but not prescriptive about how they are delivered
• Benefits of collaborative framework
• Help and support to embed programme-wide practices for consistency
![Page 26: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/26.jpg)
Supplier and Contract Management
• Driven by Cost Management and Performance and control procedures
• Schedule of deliverables to track contract requirements
• Many programme specific requirements in the Works Information and Contract
– Cost reporting, security, health and safety, equality, industrial relations etc.
• Incentivised Contracts
• Closely linked to Risk and Integration Management
![Page 27: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/27.jpg)
Contract Incentivisation
• Majority of contracts used NEC on the Olympic Park
• Option C contracts used for larger value projects
• Fair pain/gain mechanism
• No retention
• Milestone bonuses – incentive payments
• Early completion bonus
• Low levels of LADs
![Page 28: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/28.jpg)
Cost Management
• Cost Management – driven by procedures in works information
• Align WBS – at Project and Programme Levels
• Monthly cost report
• Review in detail with the contractor– Tier 2 Cost reporting
– Unlet scope and contingency review
– Monitor gain share
• PM involved in Tier 2 procurement
• Contract administrators allocated to packages
![Page 29: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/29.jpg)
Programme Assurance – 3 lines of Defence
![Page 30: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/30.jpg)
Programme Assurance Role (2nd line of defence)
Executive Management
Programme Assurance
Delivery Partner Projects
ODA Projects
Data / Reports
• Interpret project and programme data
• Highlight project and programme risks and issues
• Governance reviews
• Overall custodian of programme governance and assurance framework
• Business case validation
• Identify and fix process gaps
• Programme and Financial data analysis and trending
• Manage external assurance
• Performance and Financial Challenge
• Risk Review
• Support to fix process / governance issues
![Page 31: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/31.jpg)
The Reporting Structure
Parliament
DCMS / Funders
ODA
Delivery Partner
Project management team
Contractor
Sub-contractor
NAO VfM Review
Programme Support & Assurance Team
Programme Assurance Office
Performance Assurance
PM / Sponsor client reviews
Contractor QA processes
Performance data
Performance report
Project status reports
Monthly programme report
Programme Performance report
Ministerial briefings
Reporting Assurance
SUPPLY CHAIN
DELIVERY PARTNER
CLIENT
![Page 32: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/32.jpg)
The Outcome
This slide is intended to show how a text slide can also contain an image. Images can be used half screen and set to below the body text.
Remember that text should not appear on top of an image.
![Page 33: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/33.jpg)
Learning Legacy
![Page 34: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/34.jpg)
Lessons Learnedhttp://learninglegacy.independent.gov.uk/index.php
• No single magic bullet
• Planning phase is critical – set a robust baseline with compatible programme targets
• Get the right people with delivery capability on board.
• Pay constant attention to governance and organisation – different structures, processes and people needed at different points of the programme
• Strong Programme management needed – programme priorities override projects
• It’s a team game – relationships between ODA, CLM, government and stakeholders are very important
• Performance culture becomes a virtuous circle
![Page 35: The construction programme - assurance and controls](https://reader033.vdocuments.mx/reader033/viewer/2022061122/5469a3d9af7959e3018b7560/html5/thumbnails/35.jpg)
Questions?