ÖBB-Infrastruktur/NA The Austrian Koralm tunnel - Investigation, Design and Construction Process for a large Base Tunnel Project Gerhard Harer ÖBB Austrian Federal Railways [email protected]

Upload: others

Post on 24-Mar-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: The Austrian Koralm tunnel - Investigation, Design and ...congresodevialidad.org.ar/congreso2012/... · The Austrian Koralm tunnel - Investigation, Design and Construction Process

ÖBB-Infrastruktur/NA (Öffentlich)

The Austrian Koralm tunnel -

Investigation, Design and

Construction Process for a large

Base Tunnel Project

Gerhard Harer

ÖBB – Austrian Federal Railways

[email protected]

Page 2: The Austrian Koralm tunnel - Investigation, Design and ...congresodevialidad.org.ar/congreso2012/... · The Austrian Koralm tunnel - Investigation, Design and Construction Process

ÖBB-Infrastruktur/NA (Öffentlich)

Project overview

11.05.2012 2

Koralm railway as a part of the

Baltic – Adriatic Corridor

Double-track line, electrified

127 km overall length (at present 228 km overall length)

Max. travel speed 250 km/h

Travel time Graz – Klagenfurt 55‘ (at present 2 – 3 h)

At present rd. 63% in operation or under

construction

Expected fright volume 24 mill. tons per year

Expected 15.000 passengers per day

Koralm railway

Page 3: The Austrian Koralm tunnel - Investigation, Design and ...congresodevialidad.org.ar/congreso2012/... · The Austrian Koralm tunnel - Investigation, Design and Construction Process

ÖBB-Infrastruktur/NA (Öffentlich)

Koralm tunnel – key data

25.10.2012 3

Großer

Speikkogel

Deutschlandsberg

St. Paul i.L.

St. Georgen

Wolfsberg

St. Andrä i.L.

Page 4: The Austrian Koralm tunnel - Investigation, Design and ...congresodevialidad.org.ar/congreso2012/... · The Austrian Koralm tunnel - Investigation, Design and Construction Process

ÖBB-Infrastruktur/NA (Öffentlich) 25.10.2012 4

Koralm tunnel – key data

Koralmtunnel length 32,9 km

Start of design and exploration 1998

Start of excavation works 2010

Expected completion of civil engineering works 2019

Final operation 2023

Target costs for Koralm railway 5.400 mill. EUR (for Koralm tunnel 2.100 mill. EUR)

Koralm tunnel - key data

Page 5: The Austrian Koralm tunnel - Investigation, Design and ...congresodevialidad.org.ar/congreso2012/... · The Austrian Koralm tunnel - Investigation, Design and Construction Process

ÖBB-Infrastruktur/NA (Öffentlich)

Koralm tunnel - key data

5

Tunnel system: twin-tube – single-track

tunnel

Tunnel i: 7,90 m

Max. overburden 1.200 m

25.10.2012

Page 6: The Austrian Koralm tunnel - Investigation, Design and ...congresodevialidad.org.ar/congreso2012/... · The Austrian Koralm tunnel - Investigation, Design and Construction Process

ÖBB-Infrastruktur/NA (Öffentlich)

Compliance with regulations

Escape and rescue system

Self rescue

Simplicity in ventilation

Elimination of crossovers & switches

Safer operation

Simplicity in ventilation

Less maintenance

Südröhre (TVM)

Begehbarer Querschlag Typ B (NÖT) Begehbarer Querschlag Typ B (NÖT)

Rettungsraum (NÖT) Nordröhre (TVM)

Technikraum Technikraum

NordröhreGleis 2

SüdröhreGleis 1

Omittance of fire fighting water system &

conventional signalling

Only ETCS

Less maintenance

Only one emergency halt

Less maintenance

Koralm tunnel – tunnel system simplicity

Page 7: The Austrian Koralm tunnel - Investigation, Design and ...congresodevialidad.org.ar/congreso2012/... · The Austrian Koralm tunnel - Investigation, Design and Construction Process

ÖBB-Infrastruktur/NA (Öffentlich)

Koralm tunnel – investigation process

7

Project phases

Requirements

Strategy

25.10.2012

Page 8: The Austrian Koralm tunnel - Investigation, Design and ...congresodevialidad.org.ar/congreso2012/... · The Austrian Koralm tunnel - Investigation, Design and Construction Process

ÖBB-Infrastruktur/NA (Öffentlich)

Koralm tunnel – investigation process

8

Investigation

Project phase

Desk studies Aerial &

satellite data

interpret.

Mapping Drilling Geophysical

survey

Feasibility study 1:25.000/

1:10.000

Route pre

selection

1:10.000

Route selection &

environmental

impact

assessment

1:5000

Detailed & tender

design

1:5.000/1:1.000

Σ 21.000 lfm

25.10.2012

Page 9: The Austrian Koralm tunnel - Investigation, Design and ...congresodevialidad.org.ar/congreso2012/... · The Austrian Koralm tunnel - Investigation, Design and Construction Process

ÖBB-Infrastruktur/NA (Öffentlich)

Koralm tunnel – investigation strategy

9

0,0

2000,0

4000,0

6000,0

8000,0

10000,0

12000,0

< 100m 100-300m 300-500m 500-1200m

62 Stk. 62 Stk. 4 Stk. 5 Stk.

Bohrmeter (gesamt [m])

9

Stepwise investigation campaigns – „from coarse to fine“

Investigations composed of: – Satellite- and aerial data interpretation

– Approx. 300 km² of engineering geological mapping

– 133 core drillings, overall length 21.000 rm

– Approx. 4.000 springs, wells, creeks under observation

– Geophysical surveys from surface and in boreholes

– Investigation tunnel system with10 km length in total

Special attention was paid to: – Structured processes

– 3-dimensional compilation of the

geological model

– Advancement of methods

– Diversity of methods

– High quality of work

– GIS-based data management

25.10.2012

Page 10: The Austrian Koralm tunnel - Investigation, Design and ...congresodevialidad.org.ar/congreso2012/... · The Austrian Koralm tunnel - Investigation, Design and Construction Process

ÖBB-Infrastruktur/NA (Öffentlich) 10

Koralmtunnel – integration of investigation data

25.10.2012

Page 11: The Austrian Koralm tunnel - Investigation, Design and ...congresodevialidad.org.ar/congreso2012/... · The Austrian Koralm tunnel - Investigation, Design and Construction Process

ÖBB-Infrastruktur/NA (Öffentlich)

Koralm tunnel – geological conditions

11

Crystalline basement

Tertiary sediments

W

32,9 km

Investigation tunnels

Tertiary sediments

E

25.10.2012

Page 12: The Austrian Koralm tunnel - Investigation, Design and ...congresodevialidad.org.ar/congreso2012/... · The Austrian Koralm tunnel - Investigation, Design and Construction Process

ÖBB-Infrastruktur/NA (Öffentlich) 12

KAT1

KAT3

KAT2

Koralm tunnel – geological conditions

25.10.2012

Page 13: The Austrian Koralm tunnel - Investigation, Design and ...congresodevialidad.org.ar/congreso2012/... · The Austrian Koralm tunnel - Investigation, Design and Construction Process

ÖBB-Infrastruktur/NA (Öffentlich)

Baulos Zeitraum Vortriebsmeter

gesamt Fortschritt

Investigationtunnel

Paierdorf 2004-2010 5.616 m finished

Investigationtunnel

Mitterpichling 2004-2007 2.516 m finished

Investigationtunnel

Leibenfeld 2005-2007 2.226 m finished

KAT1 12/2008-4/2013 4.825 m excavation works finished

KAT2 1/2011-3/2019 39.928 m at present 4.375 m excavated

Ventilation shaft

Paierdorf 1/2012-12/2012 under progress

KAT3 11/2013-6/2020 23.397 m tender process

Koralm tunnel – present status of works

13 25.10.2012

Page 14: The Austrian Koralm tunnel - Investigation, Design and ...congresodevialidad.org.ar/congreso2012/... · The Austrian Koralm tunnel - Investigation, Design and Construction Process

ÖBB-Infrastruktur/NA (Öffentlich) 14 G. Harer

Suitable site organization is essential for flexible response, particularly in case of

changing behavior !

Koralm tunnel – site organization

Owner / Client

Contractor

□ Site Management □ Site Supervision

Contract

… on behalf of the client

25.10.2012

Page 15: The Austrian Koralm tunnel - Investigation, Design and ...congresodevialidad.org.ar/congreso2012/... · The Austrian Koralm tunnel - Investigation, Design and Construction Process

ÖBB-Infrastruktur/NA (Öffentlich) 11.05.2012 15 G. Harer

Koralm tunnel – site organization

Owner / Client

Contractor

□ Site Management □ Site Supervision

Designer/ Experts

□ Geotechnical Engineer □ Engineering Geological Documentation □ Geotechnical Monitoring

□ Geotechnics □ Geology □ Hydrology □ Structure □ Objects □ …

Tunneling expert

Page 16: The Austrian Koralm tunnel - Investigation, Design and ...congresodevialidad.org.ar/congreso2012/... · The Austrian Koralm tunnel - Investigation, Design and Construction Process

ÖBB-Infrastruktur/NA (Öffentlich) 16 G. Harer

Koralm tunnel – site organization – regular behavior

Tunneling expert

□ Geotechnical Engineer □ Engineering Geological Documentation □ Geotechnical Monitoring

Owner / Client

Contractor

□ Site Management □ Site Supervision

Designer/ Experts

□ Geotechnics □ Geology □ Hydrology □ Structure □ Objects □ …

Daily evaluation of geological & geotechnical conditions of excavation Daily geotech. report

Information exchange

Decision making process (consensually no dispute!)

Design check

25.10.2012

Page 17: The Austrian Koralm tunnel - Investigation, Design and ...congresodevialidad.org.ar/congreso2012/... · The Austrian Koralm tunnel - Investigation, Design and Construction Process

ÖBB-Infrastruktur/NA (Öffentlich) 11.05.2012 17

Koralm tunnel – investigation tunnels

G. Harer

12.2003 beginning of construction

• 2003-2004 Investigation shaft Paierdorf

• 2004-2007 Investigation tunnel Mitterpichling

• 2005-2010 Investigation tunnel Paierdorf

• 2005-2007 Investigation tunnel Leibenfeld

Koralm tunnel – present status of works

Page 18: The Austrian Koralm tunnel - Investigation, Design and ...congresodevialidad.org.ar/congreso2012/... · The Austrian Koralm tunnel - Investigation, Design and Construction Process

ÖBB-Infrastruktur/NA (Öffentlich) 18

Lot KAT1

Koralm tunnel – present status of works

25.10.2012

Page 19: The Austrian Koralm tunnel - Investigation, Design and ...congresodevialidad.org.ar/congreso2012/... · The Austrian Koralm tunnel - Investigation, Design and Construction Process

ÖBB-Infrastruktur/NA (Öffentlich)

Control

center

Lot KAT2 – site installation

Koralm tunnel – present status of works

25.10.2012

Page 20: The Austrian Koralm tunnel - Investigation, Design and ...congresodevialidad.org.ar/congreso2012/... · The Austrian Koralm tunnel - Investigation, Design and Construction Process

ÖBB-Infrastruktur/NA (Öffentlich) 22

6 months after beginning

Koralm tunnel – present status of works

Lot KAT2 – site installation

25.10.2012

Page 21: The Austrian Koralm tunnel - Investigation, Design and ...congresodevialidad.org.ar/congreso2012/... · The Austrian Koralm tunnel - Investigation, Design and Construction Process

ÖBB-Infrastruktur/NA (Öffentlich) 23

15 months after beginning

Lot KAT2 – site installation

Koralm tunnel – present status of works

25.10.2012

Page 22: The Austrian Koralm tunnel - Investigation, Design and ...congresodevialidad.org.ar/congreso2012/... · The Austrian Koralm tunnel - Investigation, Design and Construction Process

ÖBB-Infrastruktur/NA (Öffentlich) 24

Material management

KAT2

Total excavation

8,6 Mio. to

Concrete

1,5 Mio. to

Dumping

3,0 Mio. to Removal

1,2 Mio. to

(by railway)

Open sections

2,9 Mio. to

Koralm tunnel – present status of works

25.10.2012

Page 23: The Austrian Koralm tunnel - Investigation, Design and ...congresodevialidad.org.ar/congreso2012/... · The Austrian Koralm tunnel - Investigation, Design and Construction Process

ÖBB-Infrastruktur/NA (Öffentlich) 26

Segment production KAT2

Ring

Width 1,90 m

Segmentation 6+0 (+ invert element)

Outer diameter 9,5 m

Thickness 35 cm

Production

Number of segments 103.500 pcs.

Number of invert elements 17.250 pcs.

Unit weight per ring 47,5 t

Unit weight invert element 13,4 t

Koralm tunnel – present status of works

25.10.2012

Page 24: The Austrian Koralm tunnel - Investigation, Design and ...congresodevialidad.org.ar/congreso2012/... · The Austrian Koralm tunnel - Investigation, Design and Construction Process

ÖBB-Infrastruktur/NA (Öffentlich)

Cross heading

for logistics

during

construction

27

Some impressions KAT2

Koralm tunnel – present status of works

25.10.2012

Page 25: The Austrian Koralm tunnel - Investigation, Design and ...congresodevialidad.org.ar/congreso2012/... · The Austrian Koralm tunnel - Investigation, Design and Construction Process

ÖBB-Infrastruktur/NA (Öffentlich) 28

Some impressions KAT2

Koralm tunnel – present status of works

25.10.2012

Page 26: The Austrian Koralm tunnel - Investigation, Design and ...congresodevialidad.org.ar/congreso2012/... · The Austrian Koralm tunnel - Investigation, Design and Construction Process

ÖBB-Infrastruktur/NA (Öffentlich) 29

Tunnel boring machine

Koralm tunnel – present status of works

25.10.2012

Page 27: The Austrian Koralm tunnel - Investigation, Design and ...congresodevialidad.org.ar/congreso2012/... · The Austrian Koralm tunnel - Investigation, Design and Construction Process

ÖBB-Infrastruktur/NA (Öffentlich) 30

Tunnel boring machine

Koralm tunnel – present status of works

25.10.2012

Page 28: The Austrian Koralm tunnel - Investigation, Design and ...congresodevialidad.org.ar/congreso2012/... · The Austrian Koralm tunnel - Investigation, Design and Construction Process

ÖBB-Infrastruktur/NA (Öffentlich) 31

Tunnel boring machine - installation

Koralm tunnel – present status of works

25.10.2012

Page 29: The Austrian Koralm tunnel - Investigation, Design and ...congresodevialidad.org.ar/congreso2012/... · The Austrian Koralm tunnel - Investigation, Design and Construction Process

ÖBB-Infrastruktur/NA (Öffentlich)

The portion of investigation with respect of the budget of time and

costs for large tunnel projects must not be neglected.

Therefore from the very early stages of planning a strategy of a

stepwise investigation has to be executed.

All investigations have to be

performed under high quality standards.

The knowledge obtained by this stepwise investigation procedure

has to be summarised in an expert system, e.g. by means of GIS.

Conclusion – design and investigation

25.10.2012

Page 30: The Austrian Koralm tunnel - Investigation, Design and ...congresodevialidad.org.ar/congreso2012/... · The Austrian Koralm tunnel - Investigation, Design and Construction Process

ÖBB-Infrastruktur/NA (Öffentlich) 01.12..2011 22.11.2011

The benefits of the performed stepwise investigation strategy and

design process are clearly evident and enabled us at the Koralm

tunnel to reduce risks and save significantly time and money.

Conclusion - design and investigation

Page 31: The Austrian Koralm tunnel - Investigation, Design and ...congresodevialidad.org.ar/congreso2012/... · The Austrian Koralm tunnel - Investigation, Design and Construction Process

ÖBB-Infrastruktur/NA (Öffentlich)

Essential aspects for site organization are:

Clear responsibilities of all project members

Competent staff on site at all times (contractor and owner)

Efficient decision making

allowing for a flexible response

Conclusion – site organization

25.10.2012

Page 32: The Austrian Koralm tunnel - Investigation, Design and ...congresodevialidad.org.ar/congreso2012/... · The Austrian Koralm tunnel - Investigation, Design and Construction Process

ÖBB-Infrastruktur/NA (Öffentlich) 01.12..2011 22.11.2011

Muchas gracias por su

atención!