D E P E N D A B L E N A T U R A L G A S

TGP Outages May, June, July August Customer Webex May 23, 2017

2

Review of Upcoming Outages

May

June

July

August

Future Significant Outages

Q&A

3

Anticipated Impacts are estimates. Actual nominations, market demand, weather and pipeline conditions, etc. will determine if, and through what level, restrictions become necessary.

Unless otherwise stated, all scheduled dates represent gas days as defined in the Tennessee Gas Pipeline tariff to mean a period of twenty-four consecutive hours, beginning and ending at 9:00 a.m. (Central Clock Time).

4

Scheduled dates are subject to change.

Projects may be added, altered, delayed or cancelled.

TGP will provide notice of such additions or changes via DART postings.

Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates within this presentation.

5

Yellow

Restrictions are possible, but not likely

With extended duration, restrictions could be necessary from time to time

(M) denotes that meter(s) may be impacted, refer to EBB posting

Red

Restrictions are probable

6

Zone 0 (May)

Spike Test (M) MLV 20-3 to 17-3 (3/20/2017 - 6/7/2017)

Pipe Replacement MLV 20-1 to 20-1A (3/202017 – 5/26/2017)

Capacity of 734k reduced to 550k (seg. 109 BH)

Hydrotest (M) MLV 17-3 to 13- 3 (4/26/2017 – 6/15/2017)

Capacity of 688k reduced to 600k (seg. 101 BH)

7

Zone L (May)

8

Zone 1 (May)

Trap Modifications Sta. 546 (4/10/2017 – 6/10/2017)

Capacity of 1,245 reduced to 1,000 (seg. 548 BH)

ILI/Cleaning MLV 538-2 to 542-2 (5/25/2017 & 6/8/2017) MLV 534-2 to 538-2 (5/232017 & 6/1/2017)

Capacity of 1,216 reduced to 1,150 - 1,100 (seg. 542 BH)

9

Zone 2 & 3 (May)

Pipe Replacement MLV 107-5 to 109-5 (3/13/2017 – 6/10/2017)

Capacity of 2,369 reduced to 2,300 (seg. 187 BH)

Unit Overhaul Station 871-1A (5/15/2017 – 6/5/2017)

Capacity of 2,369 reduced to 2,250 (seg. 187 BH)

10

Zone 4 (May)

ILI/Cleaning MLV 307-2 to 219-2 (5/23/17, & 5/25/17)

Capacity of 1,145 reduced to 540k (seg. 307 BH) Unit Maintenance

Sta. 310-1A (5/24/17 - 5/26/17) Capacity of 1,145 reduced to 800k (seg. 307 BH)

Landslide Remediation MLV 207-4 to 209-4 (5/26/2017 – 6/7/2017)

Capacity of 1,838 reduced to 1,609 (seg. 204 BH)

Unit Maintenance Sta. 307-6A (5/1/2017 – 5/28/2017) Sta. 307-4A (5/15/2017 – 6/4/2017

Capacity of 1,145 reduced to 1,050 (seg. 307 BH)

Unit Maintenance Sta. 315-1B (5/21/2017 – 5/24/2017)

Capacity of 1,781 reduced to 1,640 (seg. 315 BH)

11

Zone 5 (May)

Unit Maintenance Sta. 245 (8/11/2014 – 8/14/2014)

Unit Maintenance Sta. 249-1A (5/8/2017 – 6/4/2017)

Sta. 249-2A (5/22/2017 – 5/26/2017) Capacity of 1,013 reduced to 880k (seg. 245 FH)

12

Zone 6 (May)

New England Area ILI/Cleaning MLV 336-1 to 356-1 (4/27, 5/3, 5/8 & 5/31/2017)

New England Area Anomaly Remediation MLV 270A-100 (5/22/2017 - 6/23/2017)

Unit Maintenance Sta. 264-1C & 2C (5/22/2017 – 5/26/2017)

Capacity of 937k reduced to 680k (seg. 261 FH)

13

Zone 0 (June)

Hydrotest (M) MLV 17-3 to 13- 3 (4/26/2017 – 6/15/2017)

Capacity of 688k reduced to 600k (seg. 101 BH) Spike Test (M)

MLV 17-3 to 20-3 (3/20/2017 – 6/7/2017) MLV 17-2 to 20-2 (6/8/2017 - 8/8/2017)

Capacity of 734k reduced to 550k (seg. 109 BH)

14

Zone L (June)

Station Reversal Sta. 823 (6/30/2017 - 7/11/2017)

Capacity of 223k is reduced to 0 (seg. 823 BH)

15

Zone 1 (June)

Trap Modifications Sta. 546 (4/10/2017 – 6/10/2017)

ILI/Cleaning MLV 538-2 to 542-2 (5/25/2017 & 6/8/2017

Capacity of 1,216 reduced to 1,110 (seg. 542 BH)

ILI/Cleaning MLV 555-1 to 555-1 (6/13, 6/14, 6/20 & 6/22) Capacity 1,245 reduced to 1,040 ( seg. 548 BH)

16

Zone 2 & 3 (June)

Pipe Replacement MLV 107-5 to 109-5 (3/13/2017 – 6/10/2017)

Capacity of 2,369 reduced to 2,300 (seg. 187 BH)

Unit Overhaul Station 871-1A (5/15/2017 – 6/5/2017)

Compressor Overhaul Station 871 -2A (6/6/2017 – 6/27/2017)

Capacity of 2,369 reduced to 2,250 - 2,280 (seg. 187 BH)

17

Zone 4 (June)

Anomaly Remediation MLV 209-1 to 214-1 (6/12/2017 – 6/17/2017) MLV 209-2 to 214-2 (6/19/2017 – 7/1/2017)

Capacity of 1,838 reduced to 1,750 (seg. 204 BH)

Susquehanna West Project Sta. 315 (6/5/2017 –6/11/2017)

Capacity of 1,781 reduced to 1,490 (seg. 315 BH)

Susquehanna West Project Sta. 317 (6/11– 6/15/2017)

Capacity of 1,781 reduced to 1,680 (seg. 315 BH)

Unit Maintenance Sta. 303-1A (6/5/2017 – 6/10/2017)

Capacity of 1,145 reduced to 1,020 (seg. 307 BH)

Orion Expansion Project Sta. 323A (6/16/2017 – 6/29/2017)

Capacity of 1,597 reduced to 1,400 (seg. 324 FH)

Landslide Remediation MLV 207-4 to 209-4 (5/26/2017 – 6/7/2017)

Capacity of 1,838 reduced to 1,609 (seg. 204 BH)

18

Zone 5 (June)

Unit Maintenance Sta. 245 (8/11/2014 – 8/14/2014)

Unit Maintenance Sta. 249-1B (6/5/2017 – 6/16/2017) Sta. 249-2B (5/8/2017 – 6/4/2017)

Capacity of 1,013 reduced to 890k (seg. 245 FH)

ESD Test Sta. 241 (6/12/2017 – 6/16/2017) Sta. 245 (6/19/2017 – 6/23/2017)

Capacity of 1,013 reduced to 760 k– 800k (seg. 245 FH)

Anomaly Digs MLV 237-1 to 245-1 (6/26/2017 – 8/5/2017)

Capacity of 1,013 reduced to 935k (seg. 245 FH)

19

Zone 6 (June)

New England Area Anomaly Remediation MLV 270A-100 (5/22/2017 - 6/23/2017)

20

Zone 0 (July)

Spike Test (M) MLV 17-2 to 20-2 (6/8/2017 - 8/8/2017)

Capacity of 734k reduced to 550k (seg. 109 BH)

21

Zone L (July)

Station Reversal Sta. 823 (6/30/2017 - 7/11/2017)

Capacity of 223k is reduced to 0 (seg. 823 BH)

Hydrotest MLV 826-1 to 827-1 (M) (7/11/2017 - 8/5/2017)

Capacity of 223k is reduced to 0 (seg. 823 BH)

22

Zone 1 (July)

23

Zone 2 & 3 (July)

Pipe Replacement MLV 106-4 to 108-4 (7/17/2017 – 10/7/2017)

Capacity of 2,369 reduced to 2,280 (seg. 187 BH)

Power Side Overhaul Station 871 -3A (7/5/2017 – 8/16/2017)

Anomaly Remediation MLV 864-1 to 865-1 (7/24/2017 – 7/29/2017)

Capacity of 2,369 reduced to 2,220 (seg. 187 BH)

24

Zone 4 (July)

Anomaly Remediation MLV 200-4B to MLV 204-4 (7/3/12/2017 – 7/11/2017)

MLV 204-2 to MLV 209-2 (7/13/2017 – 8/5/2017 Capacity of 1,838 reduced to 1,441 – 1,804 (seg. 204 BH)

Susquehanna West Project Sta. 315 (7/3/2017 – 7/16/2017)

Capacity of 1,781 reduced to 1,490 (seg. 315 BH)

Susquehanna West Project Sta. 317 (7/17/112017 – 7/27/2017)

Capacity of 1,781 reduced to 1,680 (seg. 315 BH)

25

Zone 5 (July)

Unit Maintenance Sta. 245 (8/11/2014 – 8/14/2014)

Anomaly Digs MLV 237-1 to 245-1 (6/26/2017 – 8/5/2017)

Capacity of 1,013 reduced to 935k (seg. 245 FH)

26

Zone 6 (July)

Connecticut Expansion Tie-In MLV 257-3 (7/17/2017 – 9/2/2017)

MLV 251-2 & 251-3 (7/24/2017 – 7/29/2017) MLV 251-1 & 251-3: Tie-In (7/31/2017 – 8/22/2017)

Capacity of 1,164 reduced to 960k – 780k (seg. 256 FH)

Hydrotest MLV 251-2 to 252-2 (7/24/2017 – 8/1/2017

Capacity of 1,164 reduced to 785 k (seg. 256 FH)

27

Zone 0 (August)

Spike Test (M) MLV 17-2 to 20-2 (6/8/2017 - 8/8/2017)

MLV 17-1 to 20-1 (8/8/2017 - 10/8/2017) Capacity of 734k reduced to 550k (seg. 109 BH)

28

Zone L (August)

Hydrotest MLV 826-1 to 827-1 (M) (7/11/2017 - 8/5/2017)

Capacity of 223k is reduced to 0 (seg. 823 BH)

29

Zone 1 (August)

Delhi Lateral Tie-In MLV 836 -1 to 837-1 (8/7/2017 - 8/17/2017)

Station Tie-In Sta. 836A ( 8/7/2017 – 8/17/2017

Capacity of 223k is reduced to 0 (seg. 834 BH)

30

Zone 2 & 3 (August)

Pipe Replacement MLV 106-4 to 108-4 (7/17/2017 – 10/7/2017)

Capacity of 2,369 reduced to 2,280 (seg. 187 BH)

Power Side Overhaul Station 871 -3A (7/5/2017 – 8/16/2017)

Capacity of 2,369 reduced to 2,220 (seg. 187 BH)

31

Zone 4 (August)

Anomaly Remediation MLV 204-2 to MLV 209-2 (7/13/2017 – 8/5/2017

MLV 204-4 to MLV 208-4 (8/7/12/2017 – 8/19/2017) Capacity of 1,838 reduced to 1,570 – 1,800 (seg. 204 BH)

Anomaly Remediation MLV 321-2 to 325-2 (8/1/112017 – 8/11/2017)

Capacity of 1,597 reduced to 1,150 (seg. 324 FH)

32

Zone 5 (August)

Unit Maintenance Sta. 245 (8/11/2014 – 8/14/2014)

Anomaly Digs MLV 237-1 to 245-1 (6/26/2017 – 8/5/2017)

Capacity of 1,013 reduced to 935k (seg. 245 FH)

33

Zone 6 (August)

Connecticut Expansion Tie-In MLV 257-3 (7/17/2017 – 9/2/2017)

MLV 251-1 & 251-3: Tie-In (7/31/2017 – 8/22/2017) Capacity of 1,164 reduced to 960k – 780k (seg. 256 FH)

Hydrotest MLV 251-2 to 252-2 (7/24/2017 – 8/1/2017

Capacity of 1,164 reduced to 785 k (seg. 256 FH)

Connecticut Expansion Tie-In MLV 260-1 to 261-1 (8/7/2017 – 8/29/2017)

Capacity of 937k reduced to 660k – 780k (seg. 261 FH)

34

Zone 0

Automation Control Update Sta. 409A (Sep./Oct. Exact Dates TBD)

Spike Test MLV 405-2 to 408-2 (Jan./Feb. 2018 Exact Dates TBD)

35

Zone L& 1 (Cameron LNG Project)

Station Reversal Sta. 827 (5/9/2017 - 8/17/2017)

Sta. 847 (8/12/2017 - 12/14/2017) Cooling System Upgrade

Sta. 823 (9/1/2017 - 11/30/2017 Hydrotest

MLV 846-1 to 847-1 (9/15/2017 - 10/15/2017) Sta. 847 (9/15/2017 - 10/15/2017)

36

Zone 3

Pipe Replacement MLV 119-2 (9/1/2017 – 9/14/2017)

Broad Run Expansion Tie-In MLV 119-2 (9/1/2017 – 9/14/2017)

MLV 118-1 (11/24/2017 – 12/8/2017)

37

Zone 4

Power Company Outage Sta. 317 (10/2/2017 – 10/6/2017)

Capacity of 1,781 reduced to 1,680 (seg. 315 BH)

38

Zone 5

Pipe Replacement MLV 231-2 (3rd Qtr. 2017)

39

Zone 6

Controls Replacement (M) Sta. 266A (9/26/2017 – 10/20/2017)

40

Suggestions for improvements to this meeting

Are the meetings beneficial?

Is additional information needed?

Questions after the meeting?

Other? Email to one of the following:

Your scheduler

DART Portal