How-to GuideTracking project milestones for JIRA issues
using the Table Grid Editor
![Page 2: Tge how-to-add-project-milestone-tracking-in-jira-issues](https://reader035.vdocuments.mx/reader035/viewer/2022062406/558de5a31a28abdd428b46d8/html5/thumbnails/2.jpg)
FEATURES COVERED
![Page 3: Tge how-to-add-project-milestone-tracking-in-jira-issues](https://reader035.vdocuments.mx/reader035/viewer/2022062406/558de5a31a28abdd428b46d8/html5/thumbnails/3.jpg)
Add a Table with Project Milestones to JIRA Issues
![Page 4: Tge how-to-add-project-milestone-tracking-in-jira-issues](https://reader035.vdocuments.mx/reader035/viewer/2022062406/558de5a31a28abdd428b46d8/html5/thumbnails/4.jpg)
Find Projects that are Starting Late
![Page 5: Tge how-to-add-project-milestone-tracking-in-jira-issues](https://reader035.vdocuments.mx/reader035/viewer/2022062406/558de5a31a28abdd428b46d8/html5/thumbnails/5.jpg)
FOLLOW THESE STEPS TO ADD THE TABLE GRID TO YOUR JIRA ISSUES
![Page 6: Tge how-to-add-project-milestone-tracking-in-jira-issues](https://reader035.vdocuments.mx/reader035/viewer/2022062406/558de5a31a28abdd428b46d8/html5/thumbnails/6.jpg)
In JIRA AdministratorAdd a custom field
![Page 7: Tge how-to-add-project-milestone-tracking-in-jira-issues](https://reader035.vdocuments.mx/reader035/viewer/2022062406/558de5a31a28abdd428b46d8/html5/thumbnails/7.jpg)
Select Table Grid Editor and click next
![Page 8: Tge how-to-add-project-milestone-tracking-in-jira-issues](https://reader035.vdocuments.mx/reader035/viewer/2022062406/558de5a31a28abdd428b46d8/html5/thumbnails/8.jpg)
Give a name and description to the Table Grid Editor. For example, if you are going to use the Table Grid Editor to store offers made to the customer, you can call it Quotes.
![Page 9: Tge how-to-add-project-milestone-tracking-in-jira-issues](https://reader035.vdocuments.mx/reader035/viewer/2022062406/558de5a31a28abdd428b46d8/html5/thumbnails/9.jpg)
Select the screen(s) on which you want to include the Quotes.
![Page 10: Tge how-to-add-project-milestone-tracking-in-jira-issues](https://reader035.vdocuments.mx/reader035/viewer/2022062406/558de5a31a28abdd428b46d8/html5/thumbnails/10.jpg)
Go to the relevant screen and you will find your Table Grid Editor
![Page 11: Tge how-to-add-project-milestone-tracking-in-jira-issues](https://reader035.vdocuments.mx/reader035/viewer/2022062406/558de5a31a28abdd428b46d8/html5/thumbnails/11.jpg)
Now we will configure the Table Grid
![Page 12: Tge how-to-add-project-milestone-tracking-in-jira-issues](https://reader035.vdocuments.mx/reader035/viewer/2022062406/558de5a31a28abdd428b46d8/html5/thumbnails/12.jpg)
Within JIRA Administratora) Goto Custom Fieldsb) Hit configure
![Page 13: Tge how-to-add-project-milestone-tracking-in-jira-issues](https://reader035.vdocuments.mx/reader035/viewer/2022062406/558de5a31a28abdd428b46d8/html5/thumbnails/13.jpg)
Click Edit Default Value
![Page 14: Tge how-to-add-project-milestone-tracking-in-jira-issues](https://reader035.vdocuments.mx/reader035/viewer/2022062406/558de5a31a28abdd428b46d8/html5/thumbnails/14.jpg)
Let’s configure The Table Grid Editor for Quotes
![Page 15: Tge how-to-add-project-milestone-tracking-in-jira-issues](https://reader035.vdocuments.mx/reader035/viewer/2022062406/558de5a31a28abdd428b46d8/html5/thumbnails/15.jpg)
Download the configuration fileused in this example
Continue this presentation for the Explanation of the configuration file
Download
![Page 16: Tge how-to-add-project-milestone-tracking-in-jira-issues](https://reader035.vdocuments.mx/reader035/viewer/2022062406/558de5a31a28abdd428b46d8/html5/thumbnails/16.jpg)
gd.tablename=projectschedulegd.ds=jiragd.visiblerows = autogd.delete.confirmation = true
Name of the table in databaseWhere the table content is stored (datasource)
1. Basic Table Grid configuration and where to store its contents
How many rows are visible in one page; auto= table grid decides
Ask for confirmation before deleting a set of rows
![Page 17: Tge how-to-add-project-milestone-tracking-in-jira-issues](https://reader035.vdocuments.mx/reader035/viewer/2022062406/558de5a31a28abdd428b46d8/html5/thumbnails/17.jpg)
gd.columns=InternalMilestone, Planned, ActualStartDate, mComment
Column Identifiers
2. Define the column specifications
![Page 18: Tge how-to-add-project-milestone-tracking-in-jira-issues](https://reader035.vdocuments.mx/reader035/viewer/2022062406/558de5a31a28abdd428b46d8/html5/thumbnails/18.jpg)
gd.columns=InternalMilestone, Planned, ActualStartDate, mComment
3. Let’s define the first column : Nr
col.InternalMilestone= Internal Milestonecol.InternalMilestone.type = listcol.InternalMilestone.width=190col.InternalMilestone.defaultSort = Ascendingcol.InternalMilestone.defaultvalue=1. Use Case Outline
Column header name
Column type, “list” = elements in a dropdown boxCheck next page for available types Order the column
ascending
Width of column expressed in pixels
Default value when adding new rows
![Page 19: Tge how-to-add-project-milestone-tracking-in-jira-issues](https://reader035.vdocuments.mx/reader035/viewer/2022062406/558de5a31a28abdd428b46d8/html5/thumbnails/19.jpg)
Supported Column Types
list
date
col.name.type = ( checkbox | date | integer | list | number | radio | sequence | string | textarea )
radio
textarea
Some Examples:
String
![Page 20: Tge how-to-add-project-milestone-tracking-in-jira-issues](https://reader035.vdocuments.mx/reader035/viewer/2022062406/558de5a31a28abdd428b46d8/html5/thumbnails/20.jpg)
gd.columns=InternalMilestone, Planned, ActualStartDate, mComment
4. Let’s define next columns : Planned start date andActual start date
col.Planned= Planned Start Datecol.Planned.type = date
col.ActualStartDate = Actual Start Datecol.ActualStartDate.type = date
Column header name Column type,
“date” = shows a date selector when editing
![Page 21: Tge how-to-add-project-milestone-tracking-in-jira-issues](https://reader035.vdocuments.mx/reader035/viewer/2022062406/558de5a31a28abdd428b46d8/html5/thumbnails/21.jpg)
gd.columns=InternalMilestone, Planned, ActualStartDate, mComment
5. Let’s define the Comment column
col.mComment=Commentcol.mComment.type = stringcol.mComment.width=180 col.mComment.maxLength=40
Column header name
Column type, “string” = Plain text type
Width of column expressed in pixels
Allow max length of 40 characters
![Page 22: Tge how-to-add-project-milestone-tracking-in-jira-issues](https://reader035.vdocuments.mx/reader035/viewer/2022062406/558de5a31a28abdd428b46d8/html5/thumbnails/22.jpg)
How to find all projectare starting late
![Page 23: Tge how-to-add-project-milestone-tracking-in-jira-issues](https://reader035.vdocuments.mx/reader035/viewer/2022062406/558de5a31a28abdd428b46d8/html5/thumbnails/23.jpg)
How to find Project that are starting late?
Pull out filters
![Page 24: Tge how-to-add-project-milestone-tracking-in-jira-issues](https://reader035.vdocuments.mx/reader035/viewer/2022062406/558de5a31a28abdd428b46d8/html5/thumbnails/24.jpg)
How to find Project that are starting late?
Click advanced
![Page 25: Tge how-to-add-project-milestone-tracking-in-jira-issues](https://reader035.vdocuments.mx/reader035/viewer/2022062406/558de5a31a28abdd428b46d8/html5/thumbnails/25.jpg)
How to find Project that are starting late?
Here you can enter a JQL Query that includesTable Grid properties
![Page 26: Tge how-to-add-project-milestone-tracking-in-jira-issues](https://reader035.vdocuments.mx/reader035/viewer/2022062406/558de5a31a28abdd428b46d8/html5/thumbnails/26.jpg)
How to find Project that are starting late?
issuekey in grid("Project Milestones", "Planned < ActualStartDate")
name of the custom field Table Grid
SQL where clauseaccess your grid in JQL
![Page 27: Tge how-to-add-project-milestone-tracking-in-jira-issues](https://reader035.vdocuments.mx/reader035/viewer/2022062406/558de5a31a28abdd428b46d8/html5/thumbnails/27.jpg)
Save the Filter so you have it at a Click of a Button
Save the Filter
![Page 28: Tge how-to-add-project-milestone-tracking-in-jira-issues](https://reader035.vdocuments.mx/reader035/viewer/2022062406/558de5a31a28abdd428b46d8/html5/thumbnails/28.jpg)
Get the Table Grid Editor add-on for JIRA
from the Atlassian Marketplace
Download