Testing & Inspection Services - REF
March 10,2010 Preproposal Presentation
Agenda
• Introduction
• Related Projects
• Project Schedule
• Site and Building
• Construction Documents
• Proposal
QA/QC PhilosophySection 01456
Contractor—Quality Control Program• Testing• Inspection
Owner—Quality Assurance Program• Testing 24 hours• Inspection 48 hours
• Contractor is still responsible
Contract 28: Renewable Energy Facility
What’s it all about?
Contract 28 builds a 50,600 square foot multi-story building at the Southerly Wastewater Treatment Center to house the following new systems:
• Biosolids dewatering and conveyance
• Fluidized bed incineration
• Steam production using waste heat from incineration
• Electricity production using steam
This will allow Southerly to abandon its existing thermal conditioning, dewatering and conveyance, and multiple hearth incineration systems.
Contract 28: Renewable Energy Facility
Turbine Generator Bldg.
Truck Loading
Incineration
Dewatering
NORTHSOUTHERLY WASTEWATER
TREATMENT CENTER
MAINT. BLDG.
SLUDGE STORAGE
TANKS
SO
LID
S H
AN
DL
ING
&
INC
INE
RA
TIO
N
AB
AN
DO
NE
D
IMH
OF
F T
AK
S
DIGESTER “A” TANK GROUP
SITE OF RENEWABLE ENERGY FACILITY
NORTH
TCSTs
CONSTRUCTION STAGING AREA 2
CONSTRUCTION STAGING AREA 3
RO
AB
“B
”
DELIVERIES THRU ROAD “B” GATE
Scope of Work TCIS-28(Full Time)
1. Project Resident Chief Inspector – fulltime; supported by coordinating Special Inspector (PE)
(As Needed Basis)
1. Specialty Testing Services – Section 01416
2. Construction Inspection Services – all disciplines
3. Shop Witness Testing/Inspection4. Laboratory Testing Services – Section
01451
Related ProjectContract 28B: Fluidized Bed
Incinerator Equipment Procurement
Infilco Degremont is supplying equipment for three fluidized bed incinerator trains to be installed under Contract 28
Price: $49,753,000
Contract 28B Integration Issues:
• Equipment delivered by IDI will be received by the Contract 28 contractor.
• Most of the equipment IDI is supplying will be installed by the Contract 28 contractor.
• IDI’s installation responsibilities are limited to:
– Construction of fluidized bed incinerator shells and refractory lining of shells’ interiors
– Code welding of waste heat boilers
• An IDI representative will be on site to provide technical assistance for the installation of IDI-supplied equipment by the Contract 28 contractor.
• For IDI-supplied equipment, site visits by manufacturers’ representatives are covered under IDI’s contract.
• Contract 28 contractor will assist IDI in start-up and testing of the incinerator trains.
Project Schedule
• Start: June, 2010• 28B Delivery: Oct, 2010-Oct, 2011• Start Commissioning: Late 2012• Complete Work: 2013
Site Plan
INCINERATION
TU
RB
INE
G
EN
ER
AT
OR
BIOSOLIDS HANDLING & CONVEYANCE
TRUCK LOAD-OUT
OF
FIC
ES
Building Area = 50,600 SF; Pavement Area = 29,800 SF
BIOSWALE (1 OF 3)
GRAY WATER CISTERN
INCINERATIONTURBINE GENERATOR
BIOSOLIDS HANDLING & CONVEYANCE
(POLYMER SYSTEM)
TRUCK LOAD-OUT
MECHANICAL SPACES
Building Level SchematicBasement (El. 590.5)
INCINERATIONTURBINE GENERATOR
BIOSOLIDS HANDLING & CONVEYANCE
TRUCK
LOAD-OUT
CONTROL RM.
LAB
MULTI-PURPOSE
RM.
Building Level SchematicGround Floor (El. 605.5)
SUBSTATIONS
NOTE:
IF CROSSED OUT, THERE IS NO FLOOR AT THE LEVEL
DEPICTED
INCINERATIONTURBINE GENERATOR
BIOSOLIDS HANDLING & CONVEYANCE
(STORAGE BINS, CAKE PUMPS)
TRUCK
LOAD-OUT
OFFICES
Building Level SchematicSecond Floor (El. 615.5 and 620.5)
MCCs
EL. 615.5 EL. 620.5EL. 620.5
INCINERATIONTURBINE GENERATOR
BIOSOLIDS HANDLING & CONVEYANCE
(CENTRIFUGES)
TRUCKLOAD-OUT
COMM. RM. & LOCKER
RMS.
Building Level SchematicThird Floor (El. 635.5)
UNASSIGNED
ROOF EL. 630.50
TRUCKLOAD-OUT
Building Level SchematicRoof (El. 650.5)
ROOF EL. 630.50
ROOF EXTENSION TO ACCOMMODATE OVERHEAD CRANE ON THIRD FLOOR)
ROOF EXTENSION TO ACCOMMODATE WASTE HEAT BOILERS
General Building Information:
• 1,057 14x73 75-ton H-piles under Biosolids Handling & Conveyance, Incineration and Offices
• 17 14x73 75-ton H-piles under Truck Loading
• 77 14x73 90-ton H-piles under turbine generator
• 50 10x42 H-piles under biofilter
• Nominal 18” thick basement floor slab; thicker at pile layouts and pile caps
• Nominal 16” thick concrete perimeter walls from basement floor slab to El. 601.83
• 31’ x 10’ x 4’ thick isolated concrete pad for turbine generator
General Building Information (Cont.):
• Floor grating (excluding platforms) is limited to portion of third floor in Incineration area. Remaining floors are concrete.
• One freight elevator; adjacent stairwell extends from basement to roof.
• One passenger elevator; adjacent stairwell extends from basement to third floor.
• Modified built-up roof system. Metal roof panel system for roof extensions.
• Aluminum curtain wall for Office area.
• Face brick on masonry block backup for remainder of building.
North Building Exterior
East Building Exterior
South Building Exterior
West Building Exterior
Contract 28 Bid Documents
3 Drawing Volumes Containing a Total of 903 Sheets
Volume 1 of 3: Title (T) 6 sheetsGeneral (G) 3 sheetsDemolition (D) 21 sheetsSite Civil (C) 32 sheetsProcess Mechanical (M) 110 sheetsArchitectural (A) 81 sheets
Volume 2 of 3: Title (T) 6 sheetsStructural (S) 109 sheetsHVAC (H) 45 sheetsPlumbing (P) 35 sheetsFire Protection (F) 7 sheetsInstrumentation (I) 121 sheets
Volume 3 of 3: Title (T) 6 sheetsElectrical (E) 321 sheets
Contract 28 Bid Documents
3 Technical Specification Volumes Containing aTotal of 269 Individual Specification Sections
Volume 1 of 3: Div. 1 – General Requirements (49 Sections)Div. 2 – Site Construction (15 Sections)Div. 3 – Concrete (7 Sections)Div. 4 – Masonry (5 Sections)
Volume 2 of 3: Div. 5 – Metals (14 Sections)Div. 6 – Wood and Plastics (2 Sections)Div. 7 – Thermal and Moisture Prot. (17 Sections)Div. 8 – Doors and Windows (7 Sections)Div. 9 – Finishes (8 Sections)Div. 10 – Specialities (10 Sections)Div. 11 – Equipment (27 Sections)Div. 12 – Furnishings (3 Sections)Div. 13 – Special Construction (23 Sections)
Contract 28 Bid Documents
3 Technical Specification Volumes Containing aTotal of 269 Individual Specification Sections
Volume 3 of 3: Div. 14 – Conveying Systems (5 Sections)Div. 15 – Mechanical (43 Sections)Div. 16 – Electrical (34 Sections)
Pre-Proposal Communication
Information and Data requests• [email protected]
• (March 16th is the last day)
Proposal Content• Executive Summary (5 pages)
• Qualifications (20 pages)– Individuals– Project Team
• Technical Approach (30 pages)
• Local Participation ~ 80% (3 pages)
• SBE Participation ~ 15% (2 pages)
• Testing Services Rate Schedule
• Proposed Overhead Rates: field, office
Evaluation Criteria
• Written Qualifications ~ 60%
• Written Technical Approach ~ 25%
• Presentation & Interview ~ 15%
(Optional)
Requirements
15% SBE Goals• Certified List Updated Monthly
• Tiffany Jordan, Contract Compliance Manager
80% Local Requirement
Presentation by up to Three (3) Top Ranked Firms (Optional)
• 90 minutes for presentation including 30 minutes for questions
• Selection committee members will not be announced