test track for indian railways by ed(testing) rdso, lucknow
TRANSCRIPT
TEST TRACK FOR INDIAN RAILWAYS
By ED(Testing)
RDSO, Lucknow
Why Testing?Statutory requirements as per Policy
Circular No 6 of Rly. Bd. For new/modified design rolling stock
Check safety Get natural frequency in various modes Check comfort level for passengers Performance rating of locos
Existing tests for new stock Detailed oscillation trials separately on service track (run-
down) maintained as per Main line standards C&M Vol-I standards (Rajdhani Track )
Confirmatory oscillograph car run on tracks above 110Kmph where induction is planned Usually on Rajdhani Routes
For trains involving new rolling stock EBD for speeds exceeding 110 for passenger & 75 kmph for
goods Computer simulation is adequate for lower speed
Coupler force trials of trains Rating & performance trials of locos
New rolling stock induction process Design & issue of speed certificate by RDSO Detailed oscillation trials
Joint safety certificate by PHoDs of zonal railway where trials are proposed
CRS sanction Actual trials
Issue of final speed certificate by RDSO after CRS approval
Zonal railways use new stock after CRS approval
Present Problems in testing Difficulty/ delay in obtaining CRS sanction Non availability of block / through path in
busy sections Track parameters are not precisely known Track parameters change after every run due
to track disturbance by normal traffic Safety related problems of adjacent track on
double line sections
Present problems in testing (contd)
Track / OHE fitness certificate is required after runs beyond sectional speed
Non-contiguous test stretch cause to & fro movement after every run
Need to reverse the locomotive after every run
Problem of berthing facilities of staff coaches Excessive TA of Test Unit staff
Why Test Track? Delay in formalities related to CRS sanction
No CRS sanction required for trials on test track
Testing on dedicated track No disturbance to normal traffic Precisely controlled track parameters No safety related problems on service track Testing time likely to drastically reduce
History of Test trackTest track at Mughalsarai sanctioned in
works programme1986-87 Total cost of Rs.5.98 crores (revised to Rs
12.45 crore in 1993) 4 km of closed loop with 1.1 km of
reversing cross- over was planned Railway Board reviewed and abandoned
the project in 1998 due to various problems
History of Test track (contd)Railway Board sanctioned Test Track in
2002 –03 for Rs 87.3 crores Proposed site in Kanpur-Lucknow
dropped due to protests by local people against acquiring their land in 2003
Proposal for test track in Jodhpur-Barmer area accepted by Board in March 2004
Present proposalTotal cost Rs 87.3 crores12 Kms stretch of straight section7.5 kms of Endurance test loopCurves incorporated in endurance loopTrack to main line maintenance
standards ( upto 120 Kmph) Additional 12 Kms straight costing Rs 25
crores for 160 kmph dropped by Rly Bd.
Endurance TestsFor track and rolling stock components
To estimate life of components Facility for accelerated service trials, FAST
When lead of service train insufficient Cost of condition monitoring very high Usually for railways where maintainer of
component not part of the system Actual service trials follow FAST
Present status Detailed estimate for construction of test
track to be made by NWRRDSO is making detailed estimate of
Facilities Instrumentation Equipment
Problems in existing proposal Test track length inadequate
Total length of 12 kms against 35 kms required Track for speeds upto 120 kmph only
Rajdhani track not provided. Does not have station yards which is essential
for oscillation trials Reversal of locomotive required after every run Curves in a separate endurance loop
Stoppage of endurance tests during testing on curves
Problems due to SiteTest track has to be closed during
summers due to sand storms Need for facility/staff to remove sand
breeches after every summer/sand-stormSand dunes near test trackSalt minesNo potable ground water
Problems due to Site (contd.)Jatropha Carcus is unlikely to act as
Sand barrier Stray Cattle barrier
Poor rail connectivity Dust/sand storm to effect visibility,
which is very critical for testingLow land inside loop
Low Cost Alternative Identify “single train only” sections like RJK-
SHTS section of MB division of NR 22.9 Km track 30 Kmph max speed Only one pair of train which is also not very
popular One level crossing Three halts/stations Other track features like bridges, culverts and
curves
Low Cost Alternative (contd) Upgrade the track to mainline standard with
reversal facility at SNK Existing train service can continue when there
is no trial Stop service train on the day of trial
All runs in one series can be completed in one day Since only one pair of train hence no problem About 3 kms of precise track parameters required General sanction can be sought from CRS as no
passenger safety would be involved
Cost Comparision of Present Proposal with Conversion of RJK-SHTS Sec
3.89
13.611.8
16
23.01
2.81 3.84 3.5
9.500295
87.950295
0
15.572
04
0 03.84 3.5 2.96032
29.87232
Landacquistion
Cost of track Earth work &Bridge
ROB/RUB Electrification Signalling Building Equipment Other costs Total
Present
Proposed
Test Track-Implications for Future of Indian Railways
Integrated Modernisation Plan (2005-2010)
Trains upto 300 Kmph Future rolling stock design efforts to be for this
speed potential, hence test track for 300 kmph needed
Safety related issues to become primary concern Crash-worthy rolling stock to be designed Better understanding of technical issues related to
derailments More reliable rolling stock and track
Test Track- Additional Use Track stress analysis under dynamic
conditions are possible only on test track Lateral forces recorded at rail level
Also help in calibration of measuring wheels
Analysis of effect of track parameters on rolling stock behaviour possible only on test track
Test Track-Additional Use (contd)
Crashworthiness tests can be doneStudies related to derailment possible
Telemetric data acquisition and remote controlled train can be planned
Re-railing/accident relief equipment may be required in derailment/collision related studies
Test Track Know-How Lack of adequate information related to
Other possible uses of test track Equipment and technology Technical and managerial problems related to test
track No information on high speed rolling stock
testing Safety related issues Testing procedures and precautions Testing personnel safety Construction related details
Proposed Action Plan Introduce mainline testing in RJK-SHTMBefore implementing the project, visit
world’s leading test track centres Interact with experts Observe actual testing Study available technology and equipment Understand problems, possible solutions
and their cost-effectiveness
Proposed Action Plan (contd.) Review existing proposal based on
knowledge gained for a cost-effective alternative related to Facilities Location Length Shape ( closed loop or straight) High speed test track Testing Procedure and analysis
Thank You!!!