tender document for - rites financial bid... · tender document for earthwork in formation,...
TRANSCRIPT
IPRCL
1 | P a g e
Signature of Tenderer Under seal of the firm
TENDER DOCUMENT FOR
Earthwork in Formation, Construction of Bridges, Retaining Wall, P-Way
Linking, Supply of PSC Sleepers, P&C, P-Way fittings & Track Ballast in
connection with Rail Connectivity from Basulya to Shalukkhali for KoPT
at Haldia, W.B
Part – 2 (FINANCIAL BID)
OPEN TENDER NOTICE NO: 64/OT/IPRCL-HALDIA/Civil & P.Way/2015 Dated.
29.10.2015
OCTOBER – 2015
Issued to (Name of Tenderer):________________________________________
Address of tenderer:_________________________________________________
Signature of officer issuing the documents___________________
Designation _______________________________
Date of Issue___________________
PROJECT MANAGEMENT CONSULTANT
RITES LTD
(A Govt. of India Enterprise)
Regional Project Office, KOLKATA
56, C. R. Avenue, 2nd
floor, Kolkata – 700 012
e.mail : [email protected]
Phone No: (033) 2236 7118/7146/7162/7143(Fax)
IPRCL
2 | P a g e
Signature of Tenderer Under seal of the firm
PART – 2
FINANCIAL BID
SCHEDULE (BILL) OF QUANTITIES
IPRCL
3 | P a g e
Signature of Tenderer Under seal of the firm
PART –2
FINANCIAL BID
SCHEDULE (BILL) OF QUANTITIES
(PERCENTAGE RATE TENDER)
ABSTRACT OF COST
(PERCENTAGE TO BE QUOTED BY THE BIDDER)
SCHEDULE DESCRIPTION TOTAL ESTIMATED COST (IN
RUPEES)
A Earthwork in Formation,
Construction of Bridges, Retaining
Wall, P-Way Linking, Supply of
PSC Sleepers, P&C, P-Way fittings
& Track Ballast in connection with
Rail Connectivity from Basulya to
Shalukkhali for KoPT at Haldia,
W.B
2397.23 Lakh
(Rupees Two Thousand Three
Hundred Ninety Seven Lakh and
Twenty Three Thousand only)
TOTAL ESTIMATED COST
OF SCHEDULE (A) (RUPEES
2397.23 Lakh
(Rupees Two Thousand Three Hundred Ninety Seven Lakh
and Twenty Three Thousand only)
PERCENTAGE ABOVE (+) OR
BELOW (-) OR AT PAR OF
TOTAL ESTIMATED COST
OF SCHEDULE (A) AS
QUOTED
PERCENTAGE IN
FIGURES
* (+) OR (-) OR (AT PAR)
PERCENTAGE IN
WORDS
*(PLUS) OR (MINUS) OR (AT
PAR)
TOTAL QUOTED COST OF
SCHEDULE (A) BASED ON
PERCENTAGE QUOTED (+)
OR (-) OR AT PAR (RUPEES)
AMOUNT IN
FIGURES
(RUPEES)
AMOUNT IN
WORDS (RUPEES)
LESS REBATE ( %) IF ANY
(IN FIGURES)
LESS REBATE ( %) IF ANY
(IN WORDS)
Rs.
NET QUOTED COST OF
SCHEDULE (A)
* Strike out which is not applicable
i) SIGNATURE OF AUTHORISED
SIGNATORY OF TENDERER
ii) NAME OF SIGNATORY
iii) NAME AND SEAL OF TENDERER
iv) DATE
v) PLACE
IPRCL
4 | P a g e
Signature of Tenderer Under seal of the firm
Note:
TENDERERS ARE REQUESTED TO QUOTE THEIR RATE IN THE PREVIOUS PAGE ONLY AND NOT IN
SCHEDULES. BASIC RATES HAS BEEN SHOWN IN SCHEDULES FOR GUIDENCE.
SCHEDULE OF QUANTITY
Earthwork in Formation, Construction of Bridges, Retaining Wall, P-Way Linking, Supply of PSC
Sleepers, P&C, P-Way fittings & Track Ballast in connection with Rail Connectivity from Basulya to
Shalukkhali for KoPT at Haldia, W.B
Sl
No
Description of Item Unit Rate (Rs.) Quantity Amount (Rs.)
From Ch.0/000 to Ch.3625.
(A) Rly. Formation Work
1 Dressing Surface (average excavation or filling upto
15 cm) including removing vegetation in all kind of
soil.
Sqm 7.22 58043 418794.76
2 Felling trees of girth (measured at a height of 1m
above ground level ) including lead and stacking of
materials within 100 m
a) Girth over 30 cm upto 60 cm No 126.30 30 3788.93
b) Girth over 60 cm to 1.5 m No 303.31 30 9099.30
3 Earth work in filling in embankment, guide bunds,
around buried type abutments, bridge gaps, trolley
refuges, rain bunds if provided, platforms etc. with
earth excavated from outside railway boundary
entirely arranged by the contractor at his own cost as
per RDSO's latest guidelines and specifications and
special condition of contract including all leads,
royalty, lifts, ascents, descents, crossing of nallahs, or
anty other obstructions. The rates shall include all
dressing of bank to final profile, demarcation and
setting out of profile, site clearance, removing of
shrubs, roots of vegetations growth, heavy grass,
benching of existing slope of old bank, all
handling/rehandling, taxes, octroi and royalties etc. as
a complete job.
cum 401.32 146693 58871164.82
4 Mechanical compaction of earth filled in embankment
with contractor's roller of suitable capacity, type and
size to achieve specified density as per specification ,
testing as per IS codes incl. cost of water , T & P
consumable materials and all labour as a complete job.
The work is to be executed as per latest edition of
'Guidelines for Earthwork in Railway Projects" issued
by RDSO, Lucknow.
Cum 17.32 146693 2540942.80
IPRCL
5 | P a g e
Signature of Tenderer Under seal of the firm
5 Supplying and laying of blanketing materials with
approved quality moorum in layers not exeeding 300
mm in loose to make the embankment of designated
profile as per specifications.The rate is inclusive of
site clearance, benching if required on existing
embankment, surfacing and levelling to give required
slope , dressing and finishing of bank,mechanical
compaction of desired density as per RDSO
guidelines, watering, all lead, lift, ascent, descent and
top surface as per specified camber using contractor's
own machinery, equipment and labour.
Cum 1200.71 20727 24887079.90
6 Providing Turfing including all lead and lift, and
watering as required until properly rooted with. Note-
initially payment of only 40% will be made. Balance
60% will be paid only after 3 months of maintenance
period if turfing is properly rooted.
Turfing with sods, 10 cm thick and 20 cm square
closely laid.
Sqm 61.31 35152 2155213.06
Total of Schedule -"A" (Formation Work) Total 88886083.56
(B) Minor Bridge Work, RCC Retaining Wall, Pucca Boundary Wall work.
Sl
No
Description of Item Unit Rate (Rs.) Quantity Amount (Rs.)
1 Earth work in excavation for foundations and floors of
the bridges, retaining walls etc. including setting out,
dressing of sides, ramming of bottom, getting out the
excavated materials, back filling in layers with
approved materials and consolidation of the layers by
ramming and watering etc. incl. all lift, disposal of
surplus soil upto a lead of 300 m, all types of shoring
and strutting with all labour and material complete as
per drawing and technical specification as directed by
Engineer in Charge.
All kinds of soils Cum 344.46 7970 2745328.27
2 Supply and laying of Coarse sand including
compaction and consolidation, supply of all materials,
labour, lead, lift, tools, plants, crossing of tracks as per
drawing and technical specification as directed by the
Engineer in Charge.
Cum 856.90 2279 1953218.66
3 Providing and laying in position machine mixed ,
machine vibrated and machine batched Design Mix
Cement Concrete M20 grade using 20 mm graded
crushed stone aggregate and Coarse sand of approved
quality in raft, wall, R/wall etc. including finishing
complete as per specifications and directions of the
Engineer in charge. Payment for reinforcement and
shuttering shall be paid extra.
cum 5358.64 589 3155142.15
IPRCL
6 | P a g e
Signature of Tenderer Under seal of the firm
4 Providing and laying in position machine mixed ,
machine vibrated and machine batched Design Mix
Cement Concrete M35 grade using 20 mm graded
crushed stone aggregate and Coarse sand of approved
quality in raft, wall, R/wall etc. including finishing,
using admixtures in recommended proportions, if
approved in Mix design to accelerate or retard setting
of concrete and/or improve workability without
impairing strength and durability complete as per
specifications and directions of the Engineer in
charge. Payment for reinforcement and shuttering
shall be paid extra.
cum 6123.04 2133 13060444.32
5 Centring and shuttering including strutting, propping
etc and removal of form for RCC Box, Boundary wall,
Wing Wall, R/Wall etc.
Sqm 260.56 8592 2238710.04
6 Supply of Reinforcement of HYSD bars of FE-500 for
RCC work including straightening, cutting, bending,
placing in position and binding all complete.
MT 59302.25 311 18442999.75
7 Providing weep holes by making suitable opening in
plain/RCC concrete abutment, wing wall/return
wallwith 100 mm dia AC pipe extending through the
full width of the structural complete.
Meter 411.32 608 250082.56
8 Supply and Providing boulder backing behind wing
wall, return wall, retaining wall with hand packed
boulders & cobbles with smaller size boulders towards
the back including all lead, lift, labour & other
incidental charges as complete work in all respect.
Cum 1442.63 373 538102.30
9 Providing and laying pitching with stone boulders
weighing not less than 35 kg each with the voids filled
with cement sand mortar 1:4 on slopes laid over
prepared filter media including boulder apron laid dry
in front of toe of embankment complete as per
drawing and Technical specifications.
Cum 2937.71 225 660984.58
10 Providing and laying of filter media consisting of
granular materials of GW,GP,SW groups as per
IS:1498-1970 in required profile behind boulder
filling of box portion , Wing wall/Retaining wall etc.
above bed level with all labour and material complete
job as per drawing and Technical Specification of
RDSO guidelines.
Cum 2024.80 770 1559097.93
11 Brick work with modular bricks of class designation
7.5 in foundation and plinth in Cement mortar 1:3 (1
cement : 3 coarse sand)
Cum 3936.73 1740 6849916.29
12 15 mm Cement plaster on the rough side of Brick
work with 1 : 4 (1 cement : 4 Coarse sand)
Sqm 143.19 15250 2183651.31
13 White washing with lime to give an even shade
New work (three or more coats)
Sqm 11.22 15250 171120.25
IPRCL
7 | P a g e
Signature of Tenderer Under seal of the firm
14 Distempering two or more coats on new work with 1st
quality acrylic washable distemper (ready mixed) of
approved manufacturer and of required shade and
colour complete as per manufacturer’s specification.
Sqm 39.08 15250 595931.88
15 Providing and fixing concertina coil fencing with
required dia. 600 mm having 50 nos round per 6 m
length upto 3.5 m height of wall with existring angle
iron "Y" shaped placed 2.4m or 3 m apart and with 9
horizontal RBT stud tied with GI staples and GI clips
to retain horizontal including necessary bolts or GI
birbed wire tied to angle iron all complete as per
direction of Engineer in Charge with reinforced birbed
tape (RBT)/Spring core (2.5mm thick) wire of high
tensile strength of 165kg/sq.mm with tape (0.52 mm
thick) and weight 43.478 gm/metre.
Metre 216.64 2475 536187.09
16 Structural steel work welded in buildup section
including cutting, bending, straightening, hoisting,
fixing in position, including applying a priming coat
of approved steel primar complete in all respect upto 6
m height above GL.
In RSJ, tees, angles and channels.
Metre 89.23 8250 736139.25
Total of Schedule -"B" (Boundary wall, Retaining
wall & Minor Bridge Work)
55677056.63
(C) P. Way Work
1 Laying, B.G. straight or curve Track with following
rail section (SWR of 33m to 40m rail pannel ) and
concrete sleeper (M+7) density with standard fittings
ensuring correct specing of sleepers, fixing and
tightening of Fish Bolts & Nuts and maintaining
proper guage, alignment, level (both cross &
longitudinal ), expansion gap at rail joints, super
elevation as necessary and with one initial through
packing. The rate should be inclusive of dekinking of
rails as required, cutting of rails as required on straight
and curve track for squaring of joints, drilling holes on
web of rail square to rail surface by using proper
template for fish plated joints, champhering of drilled
holes, greasing and oiling of fish plates and fish bolts
and nuts and at fishing zone of the rail ends including
supply of grease oil etc. Sleepers spacing
versine,super elevation etc. shall also be marked by
the contractor with white paint at his own cost. The
work has to be carried out as laid down in IRPWM
and as per direction of the Engineer-in-charge at site.
The unit of track metre consists both sides rails,
sleepers and all other fittings required thereof.
TM 444.850 3562 1584555.70
With 60 Kg Rail
IPRCL
8 | P a g e
Signature of Tenderer Under seal of the firm
2 Laying, B.G.straight or curve P.Way following rail
section (single rail) and concrete sleeper (M+7)
density with an additional sleeper to be provided at
Mid staggard Joint and standard fittings as per
drawing, ensuring correct spacing of sleepers, fixing
& tightening of Fish bolts & nuts and maintaining
proper guage, alignment, level (both cross &
longitudinal), expansion gap at rail joints, super
elevation where necessary and wih one initial through
packing. The rate should be inclusive of dekinking of
rails as required, cutting of rails as required on
straight and curve track for squaring of joints, drilling
holes on web of rail square to rail surface by using
proper template for fish plated joints as required for
single rail track, champhering of drilled holes,greasing
and oiling of fish plates & fish bolts and nuts and at
fishing zone of the rail ends including supply of
grease oil etc. Sleeper spacing, versine,
superelevation etc shall also be marked by the
contrctor wih white paint at his own cost. The work
has to be carried out as laid down in IRPWM and as
per direction of the Engineer-in-Charge at site. The
unit of track metre consists both sides rails, sleepers
and all other fittings required thereof.
TM 518.040 233 120703.32
With 60 Kg Rail
3 Supply & delivery of Machine crushed stone ballast
of 50 mm size clean angular, hard and durable track
ballast as per specification and stacking the same on
cess of the formation or toe of the bank or at suitable
place as directed by Engineer-in-Charge at site. The
rate includes all cost of lead, lift, royalty, sales tax &
other tax and duties and all incidental charges
complete as applicable. Tools, plants and screens of
approved mesh & dimensions required for inspection
and passing at the time of measurement are to be
arranged by the contractor. The rate also includes
leveling of ground, if necessary, where the ballast are
to be stacked.
Note: 90% payment shall be released on the net
quantity accepted and balance 10% shall be
released after spreading the same as per item no.4
below.
Cum 2600.00 11355 29523000.00
4 Handling, lifting and leading of ballast from stacks
with lead of 100m, which have been duly measured
and spreading ballast on formation, Track & turnouts
to ensure uniform and compact ballast cushion under
the sleepers desired ballast profile. Spreading of
ballast should be as per specified line and level and
maintaining approved profile as provided in the
technical specifications. Spreading of ballast on
formation will be done only after supply is completed
for a particular stretch as decided by Engineer in
charge and ballast stacks have been released for
spreading.
Cum 215.910 11355 2451658.05
IPRCL
9 | P a g e
Signature of Tenderer Under seal of the firm
5 Through packing of any kind of sleepers with stone
ballast to maintain correct alignment cross and
longitudinal level as required for maintaining track
gauge, versine, super elevation etc. on both straight
and curve track laid with contractor's tools and labour
inclusive of all charges as per IRPWM and as directed
by Engineer-in-charge.
a First through packing of track (M+7) Density of
sleepers
TM 64.290 3795 243980.55
b 2nd through packing of track (M+7) Density of
sleepers
TM 53.390 3795 202615.05
c 3rd through packing of track (M+7) Density of
sleepers
TM 53.390 3795 202615.05
d 4th through packing of track (M+7) Density of
sleepers
TM 53.390 3795 202615.05
6 Assembling, linking and laying in position
B.G.Standard 60 kg/52 kg turn-outs on P.S.C.
sleepers including approach & exit PSC sleeper
portion to correct alignment & gauge.This includes
switches lead rails, stock rails both straight and curve,
crossing with 60 kg/52 kg rails and standard fittings
ensuring correct spacing of sleepers fixing &
tightening of Fish bolts & nuts and maintaining proper
guage, expansion gap at rail joints and with one initial
through packing. The rate should be inclusive of
delinking of rails as required, bending stock rails,
cutting of rails to required
a 1 in 8½ Turnout/Sym. split SET 92604.510 5 463022.55
b 1 in 12 Turnout SET 123472.680 3 370418.04
7 Manufacturing and fixing of check rails as per
RDSO drg. no. T-4215 by Machine cut of 52 kg
rails of required size. Drilling holes on web by
drilling machine as per requirement. Fixing the check
rail to inner side of both the running rails of L-Xing
with the help of C.I. Bracket bolts and nuts and plate
screw at an intervals as directed by engineer-in-charge
maintaining proper check rail clearance and fixing
them on each concrete sleeper. (Rails will be
provided by RITES/employer free of cost).
Meter 1235.840 313 386817.92
8 Dismantling of existing B.G.Track of 60kg/52Kg/90R
or any section of rails with any kind of sleepers with
fittings and fastenings. The rate should be inclusive of
cutting of rails, bolts & nuts, if necessary, for
dismantling of track. Released materials should be
kept seperately i.e. Rails , Sleepers, fastenings etc. by
the side of the track up to a free lead of 30m as per
direction of the Engineer-in-Charge.
TM 132.680 200 26536.00
IPRCL
10 | P a g e
Signature of Tenderer Under seal of the firm
9 Through packing of 1 in 8½ Turn-out/Sym. split on
any kind of sleepers with stone ballast to maintain
correct alignment cross and longitudinal level as
required for maintaining track gauge, versine, super
elevation etc. on both straight and curve track laid
with contractor's tools and labour inclusive of all
charges as per IRPWM and as directed by Engineer-
in-charge. (Note: Length of turnout will be considered
from stock rail joint to the rail joint after 4th exit
sleeper)
a 1st through packing Set 8752.540 5 43762.70
b 2nd through packing Set 7568.500 5 37842.50
c 3rd through packing Set 7173.820 5 35869.10
d 4th through packing Set 7173.820 5 35869.10
10 Through packing of 1 in 12 Turn-out on any kind of
sleepers with stone ballast to maintain correct
alignment cross and longitudinal level as required for
maintaining track gauge, versine, super elevation etc.
on both straight and curve track laid with contractor's
tools and labour inclusive of all charges as per
IRPWM and as directed by Engineer-in-charge.
a 1st through packing Set 11909.980 3 35729.94
b 2nd through packing Set 10725.940 3 32177.82
c 3rd through packing Set 9541.900 3 28625.70
d 4th through packing Set 9541.900 3 28625.70
11 Trolleying new rails, PSC sleepers from the
Client/RITES Site store to the site of work by
contractors transport/dip lorry upto a distance of 1 km
including handling, loading, unloading of materials
with all lead, lift, crossing road/ rly. tracks etc
complete.
MT 738.040 2466 1820281.74
12 Making and fixing in position cement concrete
(1:2:4) Fouling Mark as per enclosed drawing
with proper painting and lettering as per
directives of the Engineer-in-Charge of the work.
The rate is inclusive of all materials like cement,
stone agreegates, sand and paints etc, with all
incidental works required for fixing in position
complete in all respects.
Each 2614.130 8 20913.04
13 Making and fixing in position cement concrete
(1:2:4) Kilometre/Curve/Gradient pillar as per
enclosed drawing with proper painting and lettering
as per directives of the Engineer-in-Charge of the
work. The rate is inclusive of all materials like
cement, stone agreegates, sand and paints etc.,
earth work in excavation and all incidental works
required for fixing in position complete in all
respects.
Each 3013.950 15 45209.25
IPRCL
11 | P a g e
Signature of Tenderer Under seal of the firm
14 Manufacturing, fabricating, supply and fixing in
position of steel boards e.g. W/L boards, STOP
boards, CAUTION boards with stand or any other
similar type of boards as per drawing and
specification mention in IRPWM with contractor's all
materials such as steel sheets (2mm thick), M.S.
angles (65 X 65 X 10mm), electodes, etc. including
earth work in excavation & grouting complete in all
respect. The rate should be inclusive of painting with
two coats of priming coat of approved quality,
lettering incl. supply of contractor's paint with all lead,
lift, ascent, descent, etc.
Each 4131.940 10 41319.40
15 Anticorrosive painting (two coats) of 60 kg, 52 kg rail
for all tracks.
TM 60.000 7903 474180.00
16 Fabrication, manufacturing and supply of glued
insulated joint of following rail section as per RDSO
drg no. provided with 2 nos. X 3.25 m long rail and
joining by 1 m long fish plates & upto date atl. &
conforming to IRS specification including cost of all
supplied materials required thereof i.e. the cost of
rails, fish plates, fish bolts & nuts complete in all
respect.
With 60 kg/m (UIC) 1st quality rails to RDSO Drg.
No. T-5843 (G3L type) (With contractor supply of
rails)
Each 59164.560 100 5916456.00
17 Welding of rail joints 60 kg from single rail to 3-rail
panel on 'Cess' or in position SKV process with
contractors PORTION provided from RDSO
approved manufacturer, dry moulds including
supplying skilled/artisan staff like welder, moulder,
chipper,lutter, aligner, striker/hammerman & adequate
nos. of semi-skilled and un-skilled labour and
supplying petrol, as required for facilitating welding
works on track by shifting the joint sleepers upto 30
cm on either side, providing suitable gap of about 23
mm to 25 mm for welding, fixing the petrol tanks &
heating the rail ends by approved contractor's
equipment and chipping the exess materials if
required, aligning, levelling etc. complete including
filing after welding on cess.
Each 6028.280 664 4002777.92
18 Construction of R.C.C. buffer as per RITES drawing
including supply of reinforcement, cement, buffer
wooden sleepers (2.75m x 0.3m x 0.20m), bolts &
nuts, washers and all other materials. The rate
should also include painting of buffer wooden
sleeper with approved quality red paint. The rate
should also be inclusive of digging of foundation
trenches, shuttering & forma finishing with all lead,
lift ascent, descent etc. complete (as per RITES
drg.).
Each 258716.130 2 517432.26
Total of Schedule -"C" (P.Way Work) Total 48895609.45
IPRCL
12 | P a g e
Signature of Tenderer Under seal of the firm
(D) Supply of P. Way materials
1 Elastic Rail clips with flat Toe (MK.III) conforming to
RDSO Drg No T-3701 (Alt.3) conforming to
specifications IRS-T-31/1989
Each 83.35 23656 1971727.60
2 Elastic Rail clips with type 'J' as per RDSO Drg. No
T-4158 for use at Fish Plated joints.
Each 84.82 2900 245978.00
3 Supply of GFN Liners RDSO Drg. No T-3706 Each 20.48 26556 543866.88
4 Grooved Rubber Sole Plate as per RDSO Drg No. T-
3711
Each 29.25 13278 388381.50
5 Supply Fish Plates to RDSO Drg. No T-1898 with
upto date alteration conforming to IRS specification.
Pair 2836.67 724 2053749.08
6 Supply Fish Plates 52 kg as per RDSO Drg No. T-090
IRST-1 with upto date alteration conforming to IRS
specification.
Pair 1960.78 45 88235.10
7 Fish Bolts and Nuts (25 mm x 140 mm) RDSO Drg
No. T-1899 Alt-2
Each 92.14 3080 283791.20
8 Plate Screw as per RDSO No T-3913 conforming to
IRS T-16
Each 61.41 1276 78359.16
9 Bolts and Nuts (22 mm x 110 mm) as per DRSO Drg.
No T-11550, IRS T-23
Each 77.50 776 60140.00
10 C.I. Bracket as per RDSO Drg no-T-4917 conforming
to IS:210-1962 and IRS-T-10
Each 579.04 590 341633.60
11 Distance Bracket as per RDSO Drg no-T-4785
conforming to IS:210-1962 and IRS-T-10
Each 78.96 186 14686.56
12 Double Coil Spring Washer RDSO Drg No. EDO/T-
1214
Each 21.92 2550 55896.00
13 Single Coil Spring Washer RDSO Drg No. T-10773 Each 10.24 776 7946.24
Total of Schedule -"D" (Supply of P.Way
Materials)
D 6134390.92
(E) Building Work
1 Construction of S&T Panel building or Other
ancilliary buildings & Level crossing Goomty/Gate
lodge as per approved drawing……directed by
Engineer-In-Charge
Sqm 40000.00 230 9200000.00
Total of Schedule -"E" (Building Work) E 9200000.00
(F) Supply of Rail Sleeper & Switches
1 B.G.Prestressed Monoblock Concrete sleepers
(pretensioned type Category-I) as per RDSO Drg.No.
T-2496 (PSC-14) and conforming to IRS
Specification T 39-85(with latest alterations)
No 2854.87 5850 16700989.50
2 B.G. Prestressed Monoblock Concrete sleepers
(pretensioned type Category-I) as per RDSO Drg.No.
T-4186 (PSC-14) and conforming to IRS
Specification T 39(with latest alterations, if any)
No 2969.69 387 1149270.03
IPRCL
13 | P a g e
Signature of Tenderer Under seal of the firm
3 B.G.Level Crossing Prestressed Monoblock Concrete
sleepers (pretensioned type Category-I) as per RDSO
Drg.No. T-4148 and IRS Specification T 39(with
latest alterations, if any)
No 2991.63 88 263263.44
4 B.G.PSC Sleepers (pretensioned type Category-I) for
1 in 8.1/2 Turn-Out including approach and exit
sleepers as per Turn Out assembly RDSO Drg.No. T-
4865 with upto date alterations and conforming to IRS
Specification T-45-1996. (LH=02 Sets, RH=03 Sets)
SET 352513.22 5 1762566.10
5 B.G. Concrete Sleepers for 1 in 12 Points & Crossings
(Fan Shapped) as per RDSO Drg.No .T-4218 with
Approach Sleeper as per Drg.No.T-4786 to T-4790to
T-4790, Exit sleeper as per T-5471 to T-5474. Points
& Crossings as per Drg. No.T-4512, T-4594.
( LH=03Set)
SET 448479.50 3 1345438.51
6 Supply of 1 in 8 ½ Switches & Crossing with 60 Kg
(IRS-T-12) 90 UTS 1st Quality rails including lead rail
and CMS crossing on PSC Sleepers layout as per
RDSO Drg. No. T-4865, T-4966 & T-4967 with all
fittings & fastenings, 2 pair of 1m long fish plates
with bolts & nuts including all fittings & fastenings of
lead portion, Lead Rails, Standard Fish plates (
610mm long) and fish bolts & nuts complete in all
respect but exclusive of PSC Sleepers. (LH- 10 set.,
RH- 3 set.)
SET 750000.00 5 3750000.00
7 Supply of 1 in 12 Switches & Crossing (CMS) with
60 Kg (IRS-T-12) 90 UTS 1st Quality rails including
lead rail and CMS crossing on PSC Sleepers layout as
per RDSO Drg. No.T-4512, T-4594 with all fittings
& fastenings, 2 pair of 1m long fish plates with bolts
& nuts including all fittings & fastenings of lead
portion, Lead Rails, Standard Fish plates and fish
bolts & nuts complete in all respect but exclusive of
PSC Sleepers. (RH-02 Sets.)
SET 1152690.00 3 3458070.00
Total of Schedule -"F" (Supply of Rail Sleeper &
Switches)
F 28429597.58
(G) Any other unforseen item
1 Any other unforseen item which are not covered by
the above item of works will be executed as per S. E.
Rly's Unified SOR - 2010
LS 2500000.00 2500000.00
Total of Schedule -"G" (Any other unforeseen
item)
H 2500000.00
Total of Schedule -(A+B+C+D+E+F+G)
239722738.13